5612 W SATURN ST 90019
Certificate Information: 5612 W SATURN ST 90019
- Application / Permit
- 17014-10000-01059
- Plan Check / Job No.
- B17LA03824
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 42'-2" X 25'-4" (2) STORY ADDITION TO EXISTING SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 12/6/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/13/2017 | APPLICANT |
| Green Plans Picked Up | 3/28/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 4/6/2017 | LOC TRUONG |
| Corrections Issued | 4/8/2017 | LOC TRUONG |
| Quality Review Completed | 4/14/2017 | BINH PHAN |
| Building Plans Picked Up | 4/19/2017 | APPLICANT |
| Plan Check Approved | 12/6/2018 | MICHAEL PEREZ |
| Issued | 12/6/2018 | LADBS |
| CofO in Progress | 9/14/2020 | DAVID CHAN |
| Permit Finaled | 3/4/2023 | DANIEL ORRANTE |
| CofO Issued | 3/4/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/4/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/12/2018 | EDUARDO PEDROZA |
| Roof/Waste drainage to street | Cleared | 1/12/2018 | EDUARDO PEDROZA |
| Green Code | Cleared | 6/13/2018 | KATHRYN BUTTERWORTH |
| Low Impact Development | Cleared | 9/18/2018 | IDA MEISAMI-FARD |
| Sewer availability | Cleared | 12/6/2018 | STEVE MELGAR |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Barakat, Fouad Chafic; Lic. No.: C67449 | 5211 GOLDEN WEST AVE TEMPLE CITY, CA 91780 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/11/2018 | Approved | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 1/7/2019 | Corrections Issued | KATHRYN BUTTERWORTH |
| METHANE-Barrier | 1/7/2019 | Approved | KATHRYN BUTTERWORTH |
| METHANE-Subgrade | 1/7/2019 | Approved | KATHRYN BUTTERWORTH |
| Excavation/Setback/Form/Re-Bar | 1/24/2019 | Corrections Issued | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 1/24/2019 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Excavation/Setback/Form/Re-Bar | 1/31/2019 | No Access for Inspection | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 1/31/2019 | No Access for Inspection | KATHRYN BUTTERWORTH |
| Excavation/Setback/Form/Re-Bar | 2/11/2019 | Corrections Issued | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 2/11/2019 | Corrections Issued | KATHRYN BUTTERWORTH |
| Excavation/Setback/Form/Re-Bar | 8/23/2019 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Pre-Inspection | 8/23/2019 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 10/30/2019 | Not Ready for Inspection | AJA COLLAY |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2019 | Approved | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 1/29/2020 | Corrections Issued | DAVID CHAN |
| HVAC-Rough | 2/19/2020 | Not Ready for Inspection | DAVID CHAN |
| HVAC-Rough | 3/11/2020 | Approved | HORACE FULTZ |
| PLUMBING-Rough | 3/11/2020 | Partial Approval | HORACE FULTZ |
| BUILDING-Rough-Frame | 3/13/2020 | Corrections Issued | DAVID CHAN |
| PLUMBING-Rough | 3/13/2020 | Corrections Issued | DAVID CHAN |
| BUILDING-Rough-Frame | 3/19/2020 | Not Ready for Inspection | MATTHEW NUCKOLLS |
| Green Building Rough | 3/19/2020 | Not Ready for Inspection | MATTHEW NUCKOLLS |
| METHANE-Rough | 3/19/2020 | Approved | MATTHEW NUCKOLLS |
| PLUMBING-Rough | 3/19/2020 | Not Ready for Inspection | MATTHEW NUCKOLLS |
| Deputy Wood Construction | 3/20/2020 | Conditional Approval | MATTHEW NUCKOLLS |
| Insulation | 4/17/2020 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 4/17/2020 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Shower Pan | 5/4/2020 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 5/12/2020 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Rough | 5/12/2020 | Not Ready for Inspection | THOMAS LOGRASSO |
| Insulation | 5/12/2020 | Conditional Approval | THOMAS LOGRASSO |
| ELECTRICAL-Final | 6/29/2020 | Corrections Issued | DAVID CHAN |
| Gas Test | 6/29/2020 | Approved | DAVID CHAN |
| PLUMBING-Final | 6/29/2020 | Not Ready for Inspection | DAVID CHAN |
| Service/Power Release | 6/29/2020 | Not Ready for Inspection | DAVID CHAN |
| ELECTRICAL-Final | 7/8/2020 | Not Ready for Inspection | DAVID CHAN |
| PLUMBING-Final | 7/8/2020 | Not Ready for Inspection | DAVID CHAN |
| Service/Power Release | 7/8/2020 | Not Ready for Inspection | DAVID CHAN |
| BUILDING-Rough-Frame | 7/13/2020 | Not Ready for Inspection | DAVID CHAN |
| ELECTRICAL-Final | 7/13/2020 | Not Ready for Inspection | DAVID CHAN |
| PLUMBING-Rough | 7/13/2020 | Approved | DAVID CHAN |
| BUILDING-Rough-Frame | 7/22/2020 | Approved | DAVID CHAN |
| Green Building Rough | 7/22/2020 | Approved | DAVID CHAN |
| PLUMBING-Rough | 7/22/2020 | Approved | DAVID CHAN |
| Service/Power Release | 7/22/2020 | Approved | DAVID CHAN |
| SGSOV-Seismic Gas S/O Valve | 8/3/2020 | SGSOV Not Ready | DAVID CHAN |
| Drywall Nailing | 8/10/2020 | Approved | DAVID CHAN |
| Final | 8/10/2020 | Corrections Issued | DAVID CHAN |
| Footing/Foundation/Slab | 8/10/2020 | Approved | DAVID CHAN |
| Green Building Final | 8/10/2020 | Approved | DAVID CHAN |
| HVAC-Final | 8/10/2020 | Approved | DAVID CHAN |
| PLUMBING-Final | 8/10/2020 | Approved | DAVID CHAN |
| SGSOV-Seismic Gas S/O Valve | 8/10/2020 | SGSOV Approved | DAVID CHAN |
| Smoke Detectors | 8/10/2020 | Approved | DAVID CHAN |
| Final | 8/21/2020 | Not Ready for Inspection | DAVID CHAN |
| Final | 8/31/2020 | Conditional Approval | DAVID CHAN |
| Final | 9/9/2020 | OK to Issue CofO | DAVID CHAN |