5612 W SATURN ST 90019

Certificate Information: 5612 W SATURN ST 90019

Application / Permit
17014-10000-01059
Plan Check / Job No.
B17LA03824
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
42'-2" X 25'-4" (2) STORY ADDITION TO EXISTING SINGLE FAMILY DWELLING.
Permit Issued
Issued on 12/6/2018
Issuing Office
Valley
Current Status
CofO Issued on 3/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/13/2017 APPLICANT
Green Plans Picked Up 3/28/2017 APPLICANT
Assigned to Plan Check Engineer 4/6/2017 LOC TRUONG
Corrections Issued 4/8/2017 LOC TRUONG
Quality Review Completed 4/14/2017 BINH PHAN
Building Plans Picked Up 4/19/2017 APPLICANT
Plan Check Approved 12/6/2018 MICHAEL PEREZ
Issued 12/6/2018 LADBS
CofO in Progress 9/14/2020 DAVID CHAN
Permit Finaled 3/4/2023 DANIEL ORRANTE
CofO Issued 3/4/2023 DANIEL ORRANTE
Permit Finaled 3/4/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/12/2018 EDUARDO PEDROZA
Roof/Waste drainage to street Cleared 1/12/2018 EDUARDO PEDROZA
Green Code Cleared 6/13/2018 KATHRYN BUTTERWORTH
Low Impact Development Cleared 9/18/2018 IDA MEISAMI-FARD
Sewer availability Cleared 12/6/2018 STEVE MELGAR

Contact Information

Contractor Owner-Builder       ,
Engineer Barakat, Fouad Chafic; Lic. No.: C67449 5211 GOLDEN WEST AVE      TEMPLE CITY, CA 91780

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/11/2018 Approved KATHRYN BUTTERWORTH
Footing/Foundation/Slab 1/7/2019 Corrections Issued KATHRYN BUTTERWORTH
METHANE-Barrier 1/7/2019 Approved KATHRYN BUTTERWORTH
METHANE-Subgrade 1/7/2019 Approved KATHRYN BUTTERWORTH
Excavation/Setback/Form/Re-Bar 1/24/2019 Corrections Issued KATHRYN BUTTERWORTH
Footing/Foundation/Slab 1/24/2019 Not Ready for Inspection KATHRYN BUTTERWORTH
Excavation/Setback/Form/Re-Bar 1/31/2019 No Access for Inspection KATHRYN BUTTERWORTH
Footing/Foundation/Slab 1/31/2019 No Access for Inspection KATHRYN BUTTERWORTH
Excavation/Setback/Form/Re-Bar 2/11/2019 Corrections Issued KATHRYN BUTTERWORTH
Footing/Foundation/Slab 2/11/2019 Corrections Issued KATHRYN BUTTERWORTH
Excavation/Setback/Form/Re-Bar 8/23/2019 Not Ready for Inspection KATHRYN BUTTERWORTH
Pre-Inspection 8/23/2019 Not Ready for Inspection KATHRYN BUTTERWORTH
Footing/Foundation/Slab 10/30/2019 Not Ready for Inspection AJA COLLAY
Floor/Roof Diaphrgm/Shear Wall 12/19/2019 Approved KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 1/29/2020 Corrections Issued DAVID CHAN
HVAC-Rough 2/19/2020 Not Ready for Inspection DAVID CHAN
HVAC-Rough 3/11/2020 Approved HORACE FULTZ
PLUMBING-Rough 3/11/2020 Partial Approval HORACE FULTZ
BUILDING-Rough-Frame 3/13/2020 Corrections Issued DAVID CHAN
PLUMBING-Rough 3/13/2020 Corrections Issued DAVID CHAN
BUILDING-Rough-Frame 3/19/2020 Not Ready for Inspection MATTHEW NUCKOLLS
Green Building Rough 3/19/2020 Not Ready for Inspection MATTHEW NUCKOLLS
METHANE-Rough 3/19/2020 Approved MATTHEW NUCKOLLS
PLUMBING-Rough 3/19/2020 Not Ready for Inspection MATTHEW NUCKOLLS
Deputy Wood Construction 3/20/2020 Conditional Approval MATTHEW NUCKOLLS
Insulation 4/17/2020 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 4/17/2020 Partial Approval CHRISTOPHER DELLEFIELD
Shower Pan 5/4/2020 Approved THOMAS LOGRASSO
Drywall Nailing 5/12/2020 Corrections Issued THOMAS LOGRASSO
Green Building Rough 5/12/2020 Not Ready for Inspection THOMAS LOGRASSO
Insulation 5/12/2020 Conditional Approval THOMAS LOGRASSO
ELECTRICAL-Final 6/29/2020 Corrections Issued DAVID CHAN
Gas Test 6/29/2020 Approved DAVID CHAN
PLUMBING-Final 6/29/2020 Not Ready for Inspection DAVID CHAN
Service/Power Release 6/29/2020 Not Ready for Inspection DAVID CHAN
ELECTRICAL-Final 7/8/2020 Not Ready for Inspection DAVID CHAN
PLUMBING-Final 7/8/2020 Not Ready for Inspection DAVID CHAN
Service/Power Release 7/8/2020 Not Ready for Inspection DAVID CHAN
BUILDING-Rough-Frame 7/13/2020 Not Ready for Inspection DAVID CHAN
ELECTRICAL-Final 7/13/2020 Not Ready for Inspection DAVID CHAN
PLUMBING-Rough 7/13/2020 Approved DAVID CHAN
BUILDING-Rough-Frame 7/22/2020 Approved DAVID CHAN
Green Building Rough 7/22/2020 Approved DAVID CHAN
PLUMBING-Rough 7/22/2020 Approved DAVID CHAN
Service/Power Release 7/22/2020 Approved DAVID CHAN
SGSOV-Seismic Gas S/O Valve 8/3/2020 SGSOV Not Ready DAVID CHAN
Drywall Nailing 8/10/2020 Approved DAVID CHAN
Final 8/10/2020 Corrections Issued DAVID CHAN
Footing/Foundation/Slab 8/10/2020 Approved DAVID CHAN
Green Building Final 8/10/2020 Approved DAVID CHAN
HVAC-Final 8/10/2020 Approved DAVID CHAN
PLUMBING-Final 8/10/2020 Approved DAVID CHAN
SGSOV-Seismic Gas S/O Valve 8/10/2020 SGSOV Approved DAVID CHAN
Smoke Detectors 8/10/2020 Approved DAVID CHAN
Final 8/21/2020 Not Ready for Inspection DAVID CHAN
Final 8/31/2020 Conditional Approval DAVID CHAN
Final 9/9/2020 OK to Issue CofO DAVID CHAN