17852 W RIDGEWAY ROAD 91344
Certificate Information: 17852 W RIDGEWAY ROAD 91344
- Application / Permit
- 17014-10000-00787
- Plan Check / Job No.
- B17LA02878
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED ADDITION TO (E) 2 STORY SFD
- Permit Issued
- Issued on 2/28/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/27/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 3/16/2017 | NEGAR NEJAD |
| Green Plans Picked Up | 3/17/2017 | APPLICANT |
| Corrections Issued | 4/10/2017 | NEGAR NEJAD |
| Quality Review Completed | 4/21/2017 | DAVID CHANG |
| Building Plans Picked Up | 4/24/2017 | APPLICANT |
| Applicant returned to address corrections | 9/29/2017 | NEGAR NEJAD |
| Applicant returned to address corrections | 10/26/2017 | NEGAR NEJAD |
| Applicant returned to address corrections | 2/19/2020 | NEGAR NEJAD |
| Applicant returned to address corrections | 2/21/2020 | NEGAR NEJAD |
| Plan Check Approved | 2/27/2020 | NEGAR NEJAD |
| Issued | 2/28/2020 | LADBS |
| CofO in Progress | 9/23/2025 | DAVID SCANTLIN |
| Permit Finaled | 9/25/2025 | MICHAEL PELHAM |
| CofO Issued | 9/25/2025 | MICHAEL PELHAM |
| Permit Finaled | 9/25/2025 | MICHAEL PELHAM |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/13/2018 | STEVE MELGAR |
| Low Impact Development | Cleared | 3/14/2018 | MARTIN FRAGOSO |
| Hydrant and Access approval | Cleared | 3/15/2018 | GILBERT URREA |
| BHO/Hillside ordinance | Cleared | 1/23/2020 | ADRIAN CASTRO |
| Permit | Cleared | 1/23/2020 | ADRIAN CASTRO |
| BHO/Hillside ordinance | Cleared | 1/24/2020 | APEKSHYA BAJRACHARYA |
| CPC | Cleared | 1/27/2020 | HERMINIGILDO AGUSTIN |
| CPC | Cleared | 1/27/2020 | HERMINIGILDO AGUSTIN |
| ZI | Cleared | 1/27/2020 | HERMINIGILDO AGUSTIN |
| Green Code | Cleared | 2/4/2020 | JOHN KLARIN |
| Roof/Waste drainage to street | Cleared | 2/14/2020 | JEANETTE VONG |
| Low Impact Development | Cleared | 2/18/2020 | ANDRES COVARRUBIAS |
| ZA Case | Cleared | 2/18/2020 | STEVEN WECHSLER |
| GPI Written Notices | Cleared | 2/27/2020 | NEGAR NEJAD |
| Grading Pre-Inspection | Cleared | 2/27/2020 | NEGAR NEJAD |
| Private sewage disp. approval | Cleared | 2/27/2020 | DAN RYAN EVANGELISTA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Martirossyan, Armen; Lic. No.: C64223 | 802 PORTOLA AVE GLENDALE, CA 91206 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/3/2020 | Approved | DAVID SCANTLIN |
| Grading Pre-Inspection | 6/24/2020 | Not Ready for Inspection | DAVID SCANTLIN |
| Deputy Drilled-In Anchors | 7/1/2020 | Approved | DAVID SCANTLIN |
| Excavation/Setback/Form/Re-Bar | 7/1/2020 | Partial Approval | DAVID SCANTLIN |
| Footing/Foundation/Slab | 7/14/2020 | Partial Approval | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 4/22/2021 | Corrections Issued | MICHAEL PELHAM |
| ELECTRICAL-Rough | 4/22/2021 | Not Ready for Inspection | MICHAEL PELHAM |
| Gas Test | 4/22/2021 | Not Ready for Inspection | MICHAEL PELHAM |
| Green Building Rough | 4/22/2021 | Not Ready for Inspection | MICHAEL PELHAM |
| HVAC-Rough | 4/22/2021 | Not Ready for Inspection | MICHAEL PELHAM |
| PLUMBING-Rough | 4/22/2021 | Not Ready for Inspection | MICHAEL PELHAM |
| Pre-Inspection | 4/22/2021 | Partial Inspection | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 4/22/2021 | Not Ready for Inspection | MICHAEL PELHAM |
| Wood Frame | 4/22/2021 | Not Ready for Inspection | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 1/14/2022 | Not Ready for Inspection | SEAN HAUPT |
| Green Building Rough | 1/14/2022 | Not Ready for Inspection | SEAN HAUPT |
| Verify Sprinkler Sign Off | 1/14/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Rough | 1/28/2022 | Approved | DAVID SCANTLIN |
| HVAC-Rough | 1/28/2022 | Approved | DAVID SCANTLIN |
| PLUMBING-Rough | 1/28/2022 | Approved | DAVID SCANTLIN |
| Rough-Elec/Plmb/HVAC | 1/28/2022 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 3/4/2022 | Approved | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2022 | Approved | DAVID SCANTLIN |
| Green Building Rough | 3/4/2022 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 3/4/2022 | Partial Approval | DAVID SCANTLIN |
| Drywall Nailing | 9/20/2022 | Approved | DAVID SCANTLIN |
| Insulation | 9/20/2022 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 9/20/2022 | Approved | DAVID SCANTLIN |
| Shower Pan | 9/20/2022 | Approved | DAVID SCANTLIN |
| Deputy Reinf. Concrete | 5/21/2024 | Conditional Approval | STEVEN BACK |
| Final | 6/13/2025 | Corrections Issued | DAVID SCANTLIN |
| Footing/Foundation/Slab | 6/13/2025 | Approved | DAVID SCANTLIN |
| Green Building Final | 6/13/2025 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 6/13/2025 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 6/13/2025 | Approved | DAVID SCANTLIN |
| Final | 9/22/2025 | OK to Issue CofO | DAVID SCANTLIN |