556 N WINDSOR BLVD 90004
Certificate Information: 556 N WINDSOR BLVD 90004
- Application / Permit
- 17014-10000-00551
- Plan Check / Job No.
- B17LA02051
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- Add 2nd Floor and unit to existing single story family dwelling.
- Permit Issued
- Issued on 11/14/2017
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/18/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/10/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 3/23/2017 | SALVADOR QUINTANILLA |
| Corrections Issued | 4/3/2017 | SALVADOR QUINTANILLA |
| Quality Review Completed | 4/5/2017 | BINH PHAN |
| Building Plans Picked Up | 4/18/2017 | APPLICANT |
| Green Plans Picked Up | 8/16/2017 | APPLICANT |
| Plan Check Approved | 11/13/2017 | SALVADOR QUINTANILLA |
| Issued | 11/14/2017 | LADBS |
| CofO in Progress | 9/18/2019 | LUIS BARRALES |
| Permit Finaled | 12/18/2021 | DEROLD HAUFF |
| CofO Issued | 12/18/2021 | DEROLD HAUFF |
| Permit Finaled | 12/18/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/18/2017 | ROCHELLE DUNGCA |
| Eng Process Fee Ord 176,300 | Cleared | 7/27/2017 | RAVIL MANAPOV |
| Low Impact Development | Cleared | 7/27/2017 | MATTHEW JIMENEZ |
| Roof/Waste drainage to street | Cleared | 7/27/2017 | RAVIL MANAPOV |
| Sewer availability | Cleared | 8/2/2017 | ADRIAN SANCHEZ |
| Green Code | Cleared | 9/22/2017 | WILLIAM ROSE |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/26/2018 | Approved | JOEL WILLIAMS |
| Special/Order Compliance | 2/26/2018 | Corrections Issued | JOEL WILLIAMS |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2018 | Partial Approval | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 5/14/2018 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2018 | Partial Approval | JOSEPH MCGARRY |
| Green Building Rough | 6/18/2018 | No Access for Inspection | JOSEPH MCGARRY |
| Wood Frame | 6/18/2018 | Not Ready for Inspection | JOSEPH MCGARRY |
| Insulation | 7/5/2018 | Partial Approval | ARAM AVEDISIAN |
| Deputy Wood Construction | 7/13/2018 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2018 | Corrections Issued | JOSEPH MCGARRY |
| Pre-Inspection | 7/18/2018 | Approved | JOSEPH MCGARRY |
| Wood Frame | 7/19/2018 | Not Ready for Inspection | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2018 | Partial Approval | JOSEPH MCGARRY |
| Green Building Rough | 8/28/2018 | Not Ready for Inspection | JOSEPH MCGARRY |
| Green Building Rough | 10/1/2018 | Not Ready for Inspection | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 10/1/2018 | Not Ready for Inspection | JOSEPH MCGARRY |
| Wood Frame | 10/1/2018 | Not Ready for Inspection | JOSEPH MCGARRY |
| Green Building Rough | 11/15/2018 | Approved | JOSEPH MCGARRY |
| Wood Frame | 11/15/2018 | Partial Approval | JOSEPH MCGARRY |
| Insulation | 12/4/2018 | Partial Approval | JOSEPH MCGARRY |
| Drywall Nailing | 6/26/2019 | Approved | LUIS BARRALES |
| Final | 6/26/2019 | Not Ready for Inspection | LUIS BARRALES |
| Green Building Final | 6/26/2019 | Approved | LUIS BARRALES |
| SGSOV-Seismic Gas S/O Valve | 6/26/2019 | SGSOV Not Ready | LUIS BARRALES |
| Smoke Detectors | 6/26/2019 | Not Ready for Inspection | LUIS BARRALES |
| Wood Frame | 6/26/2019 | Approved | LUIS BARRALES |
| Final | 8/7/2019 | Corrections Issued | LUIS BARRALES |
| SGSOV-Seismic Gas S/O Valve | 8/7/2019 | SGSOV Not Ready | LUIS BARRALES |
| Smoke Detectors | 8/7/2019 | Not Ready for Inspection | LUIS BARRALES |
| Final | 9/17/2019 | OK to Issue CofO | LUIS BARRALES |
| SGSOV-Seismic Gas S/O Valve | 9/17/2019 | SGSOV Approved | LUIS BARRALES |
| Smoke Detectors | 9/17/2019 | Approved | LUIS BARRALES |