11140 N RHODESIA AVE 91040

Certificate Information: 11140 N RHODESIA AVE 91040

Application / Permit
17014-10000-00176
Plan Check / Job No.
B17LA00752
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 1 STORY GROUND-FLOOR ADDITION (10'-2" x 21'-10", 221 SF) AT REAR OF (E) ONE-STORY SFD TO EXPAND KITCHEN.
Permit Issued
Issued on 2/14/2017
Issuing Office
Valley
Current Status
CofO Issued on 1/16/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/19/2017 APPLICANT
Assigned to Plan Check Engineer 1/19/2017 CHRISTOPHER KOMANCHECK
Corrections Issued 1/19/2017 CHRISTOPHER KOMANCHECK
Plan Check Approved 2/9/2017 ARSALAN SHABESTARI
Issued 2/14/2017 LADBS
CofO in Progress 11/6/2020 JACK KARGODORIAN
Permit Finaled 1/16/2021 MICHAEL SMITH
CofO Issued 1/16/2021 MICHAEL SMITH
Permit Finaled 1/16/2021 MICHAEL SMITH

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 1/26/2017 ADRIAN SANCHEZ
BHO/Hillside ordinance Cleared 1/26/2017 ADRIAN SANCHEZ
BHO/Hillside ordinance Cleared 1/26/2017 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 1/26/2017 ADRIAN SANCHEZ
Roof/Waste drainage to street Cleared 1/26/2017 ADRIAN SANCHEZ
Grading Pre-Inspection Cleared 2/2/2017 CHRISTOPHER KOMANCHECK

Contact Information

Contractor Owner-Builder       ,

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/15/2017 Approved BEAU COLLINS
Footing/Foundation/Slab 2/15/2017 Approved BEAU COLLINS
BUILDING-Rough-Frame 3/10/2017 Partial Approval COREY HUPP
BUILDING-Rough-Frame 4/7/2017 Corrections Issued BEAU COLLINS
Drywall Nailing 4/7/2017 Not Ready for Inspection BEAU COLLINS
Final 4/7/2017 Not Ready for Inspection BEAU COLLINS
SGSOV-Seismic Gas S/O Valve 4/7/2017 SGSOV Not Ready BEAU COLLINS
Smoke Detectors 4/7/2017 Not Ready for Inspection BEAU COLLINS
Gas Test 5/10/2017 Partial Approval BEAU COLLINS
Rough-Elec/Plmb/HVAC 5/10/2017 Partial Approval BEAU COLLINS
BUILDING-Rough-Frame 2/20/2018 No Access for Inspection ROLLIN GETTLE III
Drywall Nailing 2/20/2018 No Access for Inspection ROLLIN GETTLE III
Final 2/20/2018 No Access for Inspection ROLLIN GETTLE III
SGSOV-Seismic Gas S/O Valve 2/20/2018 SGSOV Not Ready ROLLIN GETTLE III
Smoke Detectors 2/20/2018 No Access for Inspection ROLLIN GETTLE III
BUILDING-Rough-Frame 3/7/2018 Corrections Issued BEAU COLLINS
Drywall Nailing 3/7/2018 Approved BEAU COLLINS
Final 3/7/2018 Not Ready for Inspection BEAU COLLINS
SGSOV-Seismic Gas S/O Valve 3/7/2018 SGSOV Not Ready BEAU COLLINS
Smoke Detectors 3/7/2018 Approved BEAU COLLINS
Final 9/28/2018 No Access for Inspection JOHN HAYES
BUILDING-Rough-Frame 3/9/2020 Corrections Issued MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 3/9/2020 SGSOV Not Ready MATTHEW NELSON
BUILDING-Rough-Frame 11/6/2020 Approved JACK KARGODORIAN
Final 11/6/2020 OK to Issue CofO JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 11/6/2020 SGSOV Approved JACK KARGODORIAN