1837 W MIDDLETON PL 90062

Certificate Information: 1837 W MIDDLETON PL 90062

Application / Permit
17010-70000-02926
Plan Check / Job No.
B17SL00958
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(22) Storage Building
Work Description
NEW STORAGE AND WORKSHOP.
Permit Issued
Issued on 11/15/2017
Issuing Office
South Los Angeles
Current Status
CofO Issued on 6/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/28/2017 APPLICANT
Assigned to Plan Check Engineer 7/28/2017 WESLEY FARRELL
Corrections Issued 8/1/2017 WESLEY FARRELL
Applicant returned to address corrections 10/12/2017 WESLEY FARRELL
Plan Check Approved 10/13/2017 WESLEY FARRELL
Issued 11/15/2017 LADBS
Permit Finaled 6/25/2025 CLAUDIO MORENO
CofO Issued 6/25/2025 CLAUDIO MORENO
Permit Finaled 6/25/2025 CLAUDIO MORENO

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/5/2017 NAZILA NOORIFAR
Roof/Waste drainage to street Cleared 10/5/2017 NAZILA NOORIFAR
Sewer availability Cleared 10/5/2017 NAZILA NOORIFAR

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN PARKER, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
MICHAEL SERETTI, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
HECTOR RODRIGUEZ, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
BRUCE TODD, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
JAVIER RAMOS SR, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
MARIAN PODPORA, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/19/2018 Not Ready for Inspection ENRIQUE PREZA
Special/Order Compliance 1/19/2018 Corrections Issued ENRIQUE PREZA
ELECTRICAL-Final 6/8/2018 Not Ready for Inspection ENRIQUE PREZA
Insulation 6/8/2018 Not Ready for Inspection ENRIQUE PREZA
Footing/Foundation/Slab 12/11/2018 Not Ready for Inspection ENRIQUE PREZA
Excavation/Setback/Form/Re-Bar 4/17/2019 Approved ENRIQUE PREZA
PLUMBING-Rough 3/24/2021 Approved ENRIQUE PREZA
ELECTRICAL-Final 7/6/2022 Corrections Issued ENRIQUE PREZA
Wood Frame 12/5/2022 Corrections Issued ENRIQUE PREZA
Pre-Inspection 1/23/2025 Approved MICHAEL SERETTI
Drywall Nailing 2/26/2025 Approved MICHAEL SERETTI
Green Building Rough 2/26/2025 Approved MICHAEL SERETTI
Insulation 2/26/2025 Approved MICHAEL SERETTI
PLUMBING-Final 2/26/2025 Approved MICHAEL SERETTI
PLUMBING-Rough 2/26/2025 Approved MICHAEL SERETTI
SGSOV-Seismic Gas S/O Valve 2/26/2025 SGSOV Not Required MICHAEL SERETTI
Smoke Detectors 2/26/2025 Approved MICHAEL SERETTI
Verify Sprinkler Sign Off 2/26/2025 Approved MICHAEL SERETTI
BUILDING-Rough-Frame 5/16/2025 Approved MICHAEL SERETTI
Final 5/16/2025 Conditional Approval MICHAEL SERETTI
Footing/Foundation/Slab 5/16/2025 Approved MICHAEL SERETTI
Green Building Final 5/16/2025 Approved MICHAEL SERETTI
Service/Power Release 5/16/2025 Approved MICHAEL SERETTI