7823 S MAIN ST #1-#47 90003

Certificate Information: 7823 S MAIN ST #1-#47 90003

Application / Permit
17010-70000-02092
Plan Check / Job No.
B17SL00642
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW FOUR STORY 47 UNIT APARTMENT BUILDING (TOC 1 Project)
Permit Issued
Issued on 9/12/2019
Issuing Office
Metro
Current Status
Issued on 9/12/2019
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/31/2017 APPLICANT
Assigned to Plan Check Engineer 6/22/2017 LARRY LEE
Corrections Issued 7/14/2017 LARRY LEE
Quality Review Completed 7/19/2017 PETER KIM
Building Plans Picked Up 8/10/2017 APPLICANT
Green Plans Picked Up 8/10/2017 APPLICANT
Applicant returned to address corrections 11/20/2018 LARRY LEE
Disabled Access Plans Picked Up 12/5/2018 APPLICANT
Applicant returned to address corrections 3/8/2019 LARRY LEE
Applicant returned to address corrections 4/30/2019 LARRY LEE
Applicant returned to address corrections 5/30/2019 LARRY LEE
Plan Check Approved 9/12/2019 LARRY LEE
Issued 9/12/2019 LADBS
TCO Issued (Expire Date: 09-10-2023) 3/14/2023 ERNESTO CORRAL
TCO Issued (Expire Date: 02-19-2024) 8/23/2023 ERNESTO CORRAL
TCO Issued (Expire Date: 10-08-2024) 4/11/2024 WINSTON DUNNING
TCO Issued (Expire Date: 04-06-2025) 10/8/2024 ERNESTO CORRAL
TCO Issued (Expire Date: 09-09-2025) 3/13/2025 ERNESTO CORRAL
TCO Issued (Expire Date: 02-03-2026) 8/7/2025 RAFAEL ESPINOZA
TCO Issued (Expire Date: 09-07-2026) 3/11/2026 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 8/10/2017 RAVIL MANAPOV
Eng Process Fee Ord 176,300 Cleared 8/10/2017 RAVIL MANAPOV
Permit Cleared 8/10/2017 RAVIL MANAPOV
Hydrant and Access approval Cleared 8/14/2017 JOHN CONNEALLY
"Q" conditions Cleared 9/8/2017 EDBER MACEDO
Opn space landscape/Water mgmt Cleared 9/20/2017 EDBER MACEDO
Fire Marshall Fire Life Safety Cleared 9/25/2018 WILLIAM JOHNS
Low Impact Development Cleared 10/29/2018 ORVAL HERNANDEZ-MARCI
Project located in CRA area Cleared 10/30/2018 JIM URQUHART
Green Code Cleared 11/16/2018 WILLIAM ROSE
Roof/Waste drainage to street Cleared 11/28/2018 MICHAEL CASTILLO
DAS Clearance Cleared 3/29/2019 LARRY LEE
Sewer availability Cleared 4/16/2019 ELAINE LEI
Highway dedication Cleared 6/3/2019 JEANETTE VONG
Density Bonus 12.22.A.31 Cleared 9/3/2019 NICHOLAS KAWAZOE

Contact Information

Contractor La Casa Building Contractors; Lic. No.: 537961-B 5425 S CENTRAL AVE      LOS ANGELES, CA 90011
Engineer Carrizosa,, Richard Garcia; Lic. No.: C86224 1505 LYNDHURST AVE      HACIENDA HEIGHTS, CA 917452932
Engineer Lee,, Allen C; Lic. No.: GE2781 11823 SLAUSON AVE STE 46      SANTA FE SPRINGS, CA 90670
Engineer Lee,, Sang Youck; Lic. No.: S3821 3531 BROOKHILL ST      GLENDALE, CA 91214

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/29/2019 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 11/12/2019 Partial Approval JAMES POWERS
Masonry Wall/Backfill 11/18/2019 Partial Approval JOEY BUCHANAN
Deputy Reinf. Masonry 11/20/2019 Approved JOEY BUCHANAN
Deputy Reinf. Masonry 11/21/2019 Conditional Approval JOEY BUCHANAN
Deputy Reinf. Masonry 11/22/2019 Approved JOEY BUCHANAN
Deputy Reinf. Masonry 11/25/2019 Approved JOEY BUCHANAN
Deputy Reinf. Masonry 11/26/2019 Approved JOEY BUCHANAN
Deputy Reinf. Masonry 11/27/2019 Approved JOEY BUCHANAN
Deputy Reinf. Masonry 12/2/2019 Approved JOEY BUCHANAN
Deputy Reinf. Masonry 12/3/2019 Approved JOEY BUCHANAN
Deputy Reinf. Masonry 12/4/2019 Approved JOEY BUCHANAN
Deputy Reinf. Masonry 12/5/2019 Approved JOEY BUCHANAN
Deputy Reinf. Masonry 12/6/2019 Approved JOEY BUCHANAN
Deputy Reinf. Masonry 12/9/2019 Conditional Approval JOEY BUCHANAN
Deputy Reinf. Masonry 12/10/2019 Approved JOEY BUCHANAN
Deputy Reinf. Masonry 12/11/2019 Approved JOEY BUCHANAN
Deputy Reinf. Masonry 12/12/2019 Conditional Approval RUSSELL BONVOULOIR
Deputy Reinf. Masonry 12/13/2019 Approved JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 1/14/2020 Not Ready for Inspection JOEY BUCHANAN
Footing/Foundation/Slab 1/16/2020 Partial Approval JOEY BUCHANAN
Deputy Reinf. Concrete 1/17/2020 Approved JOEY BUCHANAN
Green Building Rough 1/30/2020 Approved JOEY BUCHANAN
Reinforced Concrete Frame 1/30/2020 Not Ready for Inspection JOEY BUCHANAN
Verify Sprinkler Sign Off 1/30/2020 Not Ready for Inspection JOEY BUCHANAN
Footing/Foundation/Slab 1/31/2020 Partial Approval JOEY BUCHANAN
Deputy Other (see comments) 2/14/2020 Conditional Approval RUSSELL BONVOULOIR
Footing/Foundation/Slab 2/14/2020 Conditional Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 2/19/2020 Conditional Approval LEOPOLDO MENDOZA
Floor/Roof Diaphrgm/Shear Wall 3/26/2020 Partial Approval LEOPOLDO MENDOZA
Verify Sprinkler Sign Off 3/26/2020 Not Ready for Inspection LEOPOLDO MENDOZA
Verify Sprinkler Sign Off 4/24/2020 Conditional Approval LEOPOLDO MENDOZA
Wood Frame 4/24/2020 Partial Approval LEOPOLDO MENDOZA
Deputy Wood Construction 6/11/2020 Conditional Approval LANNY MERRICK
Floor/Roof Diaphrgm/Shear Wall 6/12/2020 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 6/17/2020 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 6/17/2020 Not Ready for Inspection JAMES POWERS
Deputy Drilled-In Anchors 7/31/2020 Conditional Approval LEOPOLDO MENDOZA
Deputy Wood Construction 7/31/2020 Conditional Approval LEOPOLDO MENDOZA
Deputy Wood Construction 8/11/2020 Conditional Approval LEOPOLDO MENDOZA
Verify Sprinkler Sign Off 8/14/2020 Not Ready for Inspection JAMES POWERS
Wood Frame 8/14/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 8/21/2020 Conditional Approval RUSSELL BONVOULOIR
Verify Sprinkler Sign Off 8/27/2020 Not Ready for Inspection JAMES POWERS
Wood Frame 8/27/2020 Not Ready for Inspection JAMES POWERS
Wood Frame 8/28/2020 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 9/1/2020 Approved JOEY BUCHANAN
Wood Frame 9/1/2020 Conditional Approval JOEY BUCHANAN
Insulation 9/9/2020 Partial Approval JAMES POWERS
Insulation 9/15/2020 Approved JAMES POWERS
Drywall Nailing 9/25/2020 Partial Approval JAMES POWERS
Drywall Nailing 10/14/2020 Partial Approval JAMES POWERS
Special/Order Compliance 11/10/2020 Approved JAMES POWERS
Interior/Exterior Lathing 11/24/2020 Approved JAMES POWERS
Drywall Nailing 9/13/2021 Conditional Approval DARRYL ARNOLD
Pre-Inspection 12/19/2022 Approved JAMES POWERS
Final 2/22/2023 Not Ready for Inspection JAMES POWERS
Smoke Detectors 2/22/2023 Approved JAMES POWERS
Drywall Nailing 3/13/2023 Approved JAMES POWERS
Final 3/13/2023 OK for TCO JAMES POWERS
Footing/Foundation/Slab 3/13/2023 Approved JAMES POWERS
Green Building Final 3/13/2023 Approved JAMES POWERS
Reinforced Concrete Frame 3/13/2023 Approved JAMES POWERS
Reinforced Masonry Frame 3/13/2023 Approved JAMES POWERS
SGSOV-Seismic Gas S/O Valve 3/13/2023 SGSOV Approved JAMES POWERS
Structural Steel Frame 3/13/2023 Approved JAMES POWERS
Wood Frame 3/13/2023 Approved JAMES POWERS
Special/Order Compliance 8/16/2023 Approved JAMES POWERS
Special/Order Compliance 1/23/2024 Partial Approval JAMES POWERS
Pre-Inspection 4/9/2024 Not Ready for Inspection JAMES POWERS
Special/Order Compliance 9/10/2024 Approved JAMES POWERS
Special/Order Compliance 3/11/2025 Partial Approval JAMES POWERS
Final 3/18/2025 Not Ready for Inspection JAMES POWERS
Special/Order Compliance 1/6/2026 Partial Approval JAMES POWERS