477 1/2 W 19TH ST 90731
Certificate Information: 477 1/2 W 19TH ST 90731
- Application / Permit
- 17010-40000-01057
- Plan Check / Job No.
- B17SP00201
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Fully sprinklered 26' x 41'-1" irreg. shaped two story building; accessory dwelling unit above four car garage
- Permit Issued
- Issued on 2/5/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/7/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/10/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 4/20/2017 | STEVEN KIM |
| Corrections Issued | 4/25/2017 | STEVEN KIM |
| Quality Review Completed | 4/27/2017 | FELIX FIGUEROA |
| Building Plans Picked Up | 6/15/2017 | APPLICANT |
| Green Plans Picked Up | 6/15/2017 | APPLICANT |
| Plan Check Approved | 2/5/2020 | STEVEN KIM |
| Issued | 2/5/2020 | LADBS |
| CofO in Progress | 1/30/2021 | JOHN KLARIN |
| CofO in Progress | 5/5/2021 | JOHN KLARIN |
| Permit Finaled | 6/7/2021 | DEROLD HAUFF |
| CofO Issued | 6/7/2021 | DEROLD HAUFF |
| Permit Finaled | 6/7/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/22/2017 | FATIMA GUERRA |
| Highway dedication | Cleared | 6/22/2017 | FATIMA GUERRA |
| Permit | Cleared | 6/22/2017 | FATIMA GUERRA |
| Eng Process Fee Ord 176,300 | Cleared | 9/8/2017 | CARLA VALLADARES |
| Hydrant and Access approval | Cleared | 9/8/2017 | JOHN CONNEALLY |
| Sewer availability | Cleared | 9/8/2017 | CARLA VALLADARES |
| Low Impact Development | Cleared | 10/3/2017 | SAM NAVID |
| Roof/Waste drainage to street | Cleared | 10/3/2017 | STEVE MELGAR |
| Green Code | Cleared | 11/21/2017 | BRYAN MEYER |
| Coastal Zone | Cleared | 6/11/2019 | LATANYA ROUX |
| Miscellaneous | Cleared | 6/11/2019 | LATANYA ROUX |
| Specific Plan | Cleared | 6/11/2019 | LATANYA ROUX |
| Project located in CRA area | Cleared | 7/2/2019 | JIM URQUHART |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chen,, Yeshen Jason; Lic. No.: C40169 | 20601 ALDA CT WALNUT, CA 91789 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/1/2020 | Corrections Issued | JOHN KLARIN |
| Excavation/Setback/Form/Re-Bar | 4/3/2020 | Corrections Issued | JOHN KLARIN |
| Footing/Foundation/Slab | 4/9/2020 | Corrections Issued | JOHN KLARIN |
| Footing/Foundation/Slab | 4/16/2020 | Corrections Issued | JOHN KLARIN |
| Footing/Foundation/Slab | 4/20/2020 | Corrections Issued | JOHN KLARIN |
| Footing/Foundation/Slab | 4/29/2020 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 4/30/2020 | Partial Inspection | JOHN KLARIN |
| BUILDING-Rough-Frame | 5/27/2020 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 5/27/2020 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/27/2020 | Approved | JOHN KLARIN |
| Green Building Rough | 5/27/2020 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 5/27/2020 | Approved | JOHN KLARIN |
| Verify Sprinkler Sign Off | 5/27/2020 | Approved | JOHN KLARIN |
| Drywall Nailing | 6/5/2020 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 6/5/2020 | Approved | JOHN KLARIN |
| Final | 7/27/2020 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 7/27/2020 | Corrections Issued | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 7/27/2020 | SGSOV Approved | JOHN KLARIN |
| Service/Power Release | 7/27/2020 | Not Ready for Inspection | JOHN KLARIN |
| Smoke Detectors | 7/27/2020 | Not Ready for Inspection | JOHN KLARIN |
| Final | 8/3/2020 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 8/3/2020 | Not Ready for Inspection | JOHN KLARIN |
| Service/Power Release | 8/3/2020 | Not Ready for Inspection | JOHN KLARIN |
| Smoke Detectors | 8/3/2020 | Not Ready for Inspection | JOHN KLARIN |
| Final | 9/25/2020 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 9/25/2020 | Approved | JOHN KLARIN |
| Service/Power Release | 9/25/2020 | Not Ready for Inspection | JOHN KLARIN |
| Smoke Detectors | 9/25/2020 | Approved | JOHN KLARIN |
| Final | 1/6/2021 | Not Ready for Inspection | JOHN KLARIN |
| Service/Power Release | 1/6/2021 | Approved | JOHN KLARIN |
| Final | 1/12/2021 | Partial Approval | JOHN KLARIN |
| Final | 1/28/2021 | OK to Issue CofO | JOHN KLARIN |
| Service/Power Release | 1/28/2021 | Approved | JOHN KLARIN |
| Service/Power Release | 2/22/2021 | Approved | JOHN KLARIN |
| Special/Order Compliance | 3/18/2021 | Corrections Issued | JOHN KLARIN |
| Final | 5/4/2021 | OK to Issue CofO | JOHN KLARIN |
| Special/Order Compliance | 5/4/2021 | Approved | JOHN KLARIN |