9650 W CEDARBROOK DR 90210
Certificate Information: 9650 W CEDARBROOK DR 90210
- Application / Permit
- 17010-40000-00872
- Plan Check / Job No.
- B17SP00159
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 4-STORY S.F.D. OVER BASEMENT
- Permit Issued
- Issued on 3/19/2018
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 3/19/2018
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/3/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 4/13/2017 | ZAW HAN |
| Green Plans Picked Up | 4/19/2017 | APPLICANT |
| Corrections Issued | 6/8/2017 | ZAW HAN |
| Quality Review Completed | 6/15/2017 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 2/11/2018 | ZAW HAN |
| Applicant returned to address corrections | 3/7/2018 | ZAW HAN |
| Applicant returned to address corrections | 3/8/2018 | ZAW HAN |
| Plan Check Approved | 3/16/2018 | Zaw Han |
| Issued | 3/19/2018 | LADBS |
| Permit Expired | 11/8/2018 | ELMER BLAND |
| Intent to Revoke-Status Void | 2/28/2019 | SHAHEN AKELYAN |
| Re-Activate Permit | 5/16/2019 | VICTOR CUEVAS |
| Intent to Revoke-Status Void | 10/29/2019 | VICTOR CUEVAS |
| Re-Activate Permit | 5/19/2020 | VICTOR CUEVAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/9/2018 | MAHELET GEBEYHU |
| BHO/Hillside ordinance | Cleared | 1/9/2018 | MAHELET GEBEYHU |
| BHO/Hillside ordinance | Cleared | 1/9/2018 | MAHELET GEBEYHU |
| BHO/Hillside ordinance | Cleared | 1/9/2018 | MAHELET GEBEYHU |
| Eng Process Fee Ord 176,300 | Cleared | 1/9/2018 | MAHELET GEBEYHU |
| Permit | Cleared | 1/9/2018 | MAHELET GEBEYHU |
| Grading in hillside | Cleared | 1/10/2018 | TREVOR MARTIN |
| Miscellaneous | Cleared | 1/10/2018 | TREVOR MARTIN |
| Miscellaneous | Cleared | 1/10/2018 | TREVOR MARTIN |
| Miscellaneous | Cleared | 1/10/2018 | TREVOR MARTIN |
| Miscellaneous | Cleared | 1/10/2018 | TREVOR MARTIN |
| Low Impact Development | Cleared | 2/7/2018 | RYAN HUDSON |
| Certificate of Compliance | Cleared | 2/28/2018 | MARC WOERSCHING |
| Roof/Waste drainage to street | Cleared | 3/5/2018 | DENNIS BRAGIN |
| Hydrant and Access approval | Cleared | 3/6/2018 | ROBERT DUFF |
| Green Code | Cleared | 3/7/2018 | KATHRYN BUTTERWORTH |
| Sewer availability | Cleared | 3/7/2018 | OSCAR GUTIERREZ |
| GPI Written Notices | Cleared | 3/8/2018 | KIRK LINKLATER |
| Grading Pre-Inspection | Cleared | 3/8/2018 | KIRK LINKLATER |
| Building over 3-story or 36-ft | Cleared | 3/15/2018 | CALOSHA APPROVED |
| Excavation more than 5-ft deep | Cleared | 3/15/2018 | CALOSHA APPROVED |
| Disturb/Remove Protected Trees | Cleared | 3/16/2018 | ADRIAN SANCHEZ |
Contact Information
| Architect | Ignacio, Rodriguez Ir Architects; Lic. No.: C35166 | 18012 OSBORNE STREET NORTHRIDGE, CA 91325 |
| Contractor | Owner-Builder | , |
| Engineer | Joshua, F Danz; Lic. No.: C84764 | 569 HAMPSHIRE RD APT 108 WESTLAKE VILLAGE, CA 91361 |
| Engineer | Lau, David Harkwong; Lic. No.: C34961 | 12467 W WASHINGTON BLVD LOS ANGELES, CA 90066 |
| Engineer | Schmahl, Lawrence Joseph; Lic. No.: L5748 | 11209 HOWARD STREET WHITTIER, CA 90606 |
Inspector Information
| ROY SPAULDING, (213) 202-3461 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/26/2019 | Not Ready for Inspection | DANNY TOLENTINO |
| Pre-Inspection | 7/2/2019 | Partial Inspection | DANNY TOLENTINO |
| Deputy Grading | 7/3/2019 | No Access for Inspection | DANNY TOLENTINO |
| Deputy Grading | 7/5/2019 | Conditional Approval | DANNY TOLENTINO |
| Deputy Grading | 7/8/2019 | Conditional Approval | RICHARD STEINBACH |
| Deputy Grading | 7/9/2019 | Conditional Approval | RICHARD STEINBACH |
| Deputy Grading | 7/10/2019 | Conditional Approval | RICHARD STEINBACH |
| Deputy Grading | 7/11/2019 | Conditional Approval | RICHARD STEINBACH |
| Deputy Grading | 7/12/2019 | Conditional Approval | RICHARD STEINBACH |
| Deputy Grading | 7/15/2019 | Conditional Approval | RICHARD STEINBACH |
| Deputy Grading | 7/16/2019 | Conditional Approval | RICHARD STEINBACH |
| Deputy Grading | 7/17/2019 | Conditional Approval | RICHARD STEINBACH |
| Deputy Grading | 7/18/2019 | Conditional Approval | RICHARD STEINBACH |
| Deputy Grading | 7/19/2019 | Conditional Approval | RICHARD STEINBACH |
| Deputy Grading | 7/22/2019 | Conditional Approval | RICHARD STEINBACH |
| Deputy Grading | 7/23/2019 | Conditional Approval | RICHARD STEINBACH |
| Special/Order Compliance | 7/23/2019 | Partial Inspection | RICHARD STEINBACH |
| Deputy Grading | 7/24/2019 | Conditional Approval | RICHARD STEINBACH |
| Deputy Grading | 7/26/2019 | Conditional Approval | RICHARD STEINBACH |
| Deputy Grading | 7/29/2019 | Conditional Approval | RICHARD STEINBACH |
| Deputy Grading | 7/30/2019 | Conditional Approval | RICHARD STEINBACH |
| Deputy Grading | 7/31/2019 | Conditional Approval | RICHARD STEINBACH |
| Deputy Grading | 8/2/2019 | Conditional Approval | MICHAEL PELHAM |
| Deputy Grading | 8/12/2019 | Conditional Approval | RICHARD STEINBACH |
| Deputy Grading | 8/13/2019 | Conditional Approval | RICHARD STEINBACH |
| Deputy Grading | 8/14/2019 | Conditional Approval | RICHARD STEINBACH |
| Deputy Grading | 8/15/2019 | Conditional Approval | RICHARD STEINBACH |
| Deputy Grading | 8/16/2019 | Conditional Approval | RICHARD STEINBACH |
| Deputy Grading | 8/19/2019 | Conditional Approval | RAUL BARAJAS |
| Deputy Grading | 8/20/2019 | Conditional Approval | RICHARD STEINBACH |
| Deputy Grading | 8/21/2019 | Conditional Approval | RICHARD STEINBACH |
| Deputy Grading | 8/22/2019 | Conditional Approval | RICHARD STEINBACH |
| Deputy Grading | 8/23/2019 | Conditional Approval | RICHARD STEINBACH |
| Deputy Grading | 8/26/2019 | Conditional Approval | RICHARD STEINBACH |
| Deputy Grading | 8/27/2019 | Conditional Approval | RICHARD STEINBACH |
| Deputy Grading | 8/29/2019 | Conditional Approval | RICHARD STEINBACH |
| Deputy Grading | 9/3/2019 | Conditional Approval | RICHARD STEINBACH |
| Piling/Pier/Caisson | 9/19/2019 | Partial Approval | RICHARD STEINBACH |
| Special/Order Compliance | 9/20/2019 | Corrections Issued | BRIAN SULLIVAN |
| Deputy Grading | 10/1/2019 | No Access for Inspection | BRIAN SULLIVAN |
| Deputy Grading | 10/2/2019 | No Access for Inspection | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 5/21/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| Deputy Grading | 5/22/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 5/26/2020 | Conditional Approval | MATTHEW NUCKOLLS |
| Deputy Grading | 5/27/2020 | Approved | ELMER BLAND |
| Deputy Grading | 5/28/2020 | Approved | ELMER BLAND |
| Deputy Grading | 5/29/2020 | Approved | BRAD BESCOS |
| Deputy Grading | 5/29/2020 | Approved | ELMER BLAND |
| Deputy Grading | 6/2/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 6/3/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 6/4/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Steel/Welding | 6/4/2020 | No Access for Inspection | BRIAN SULLIVAN |
| Deputy Grading | 6/5/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Steel/Welding | 6/5/2020 | Conditional Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 6/5/2020 | Corrections Issued | BRAD BESCOS |
| Piling/Pier/Caisson | 6/5/2020 | Partial Approval | BRIAN SULLIVAN |
| Deputy Grading | 6/8/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 6/8/2020 | Conditional Approval | BRIAN SULLIVAN |
| Piling/Pier/Caisson | 6/8/2020 | Partial Approval | BRIAN SULLIVAN |
| Deputy Grading | 6/9/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 6/10/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 6/11/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 6/12/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Steel/Welding | 6/12/2020 | No Access for Inspection | BRIAN SULLIVAN |
| Deputy Grading | 6/15/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 6/15/2020 | No Access for Inspection | BRIAN SULLIVAN |
| Deputy Grading | 6/16/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 6/16/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 6/17/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 6/17/2020 | Conditional Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 6/17/2020 | Partial Approval | BRIAN SULLIVAN |
| Deputy Grading | 6/18/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 6/18/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 6/19/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 6/22/2020 | Conditional Approval | BRIAN SULLIVAN |
| Piling/Pier/Caisson | 6/22/2020 | Partial Approval | BRIAN SULLIVAN |
| Deputy Grading | 6/23/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 6/23/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 6/24/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 6/25/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 6/26/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 6/29/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 6/29/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 6/30/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 6/30/2020 | No Access for Inspection | BRIAN SULLIVAN |
| Deputy Grading | 7/1/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 7/1/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 7/2/2020 | Conditional Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 7/2/2020 | Partial Approval | BRIAN SULLIVAN |
| Piling/Pier/Caisson | 7/2/2020 | Partial Approval | BRIAN SULLIVAN |
| Deputy Grading | 7/6/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 7/7/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 7/7/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 7/8/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 7/8/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 7/9/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 7/9/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 7/10/2020 | Conditional Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 7/10/2020 | Partial Approval | BRIAN SULLIVAN |
| Piling/Pier/Caisson | 7/10/2020 | Partial Approval | BRIAN SULLIVAN |
| Deputy Grading | 7/13/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 7/13/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 7/14/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 7/14/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 7/15/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 7/15/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 7/16/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 7/17/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 7/20/2020 | Conditional Approval | BRIAN SULLIVAN |
| Piling/Pier/Caisson | 7/20/2020 | Partial Approval | BRIAN SULLIVAN |
| Deputy Grading | 7/21/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 7/22/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 7/23/2020 | Conditional Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 7/27/2020 | Partial Approval | BRAD BESCOS |
| Deputy Reinf. Concrete | 7/28/2020 | No Access for Inspection | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 7/29/2020 | No Access for Inspection | ELMER BLAND |
| Deputy Reinf. Concrete | 7/30/2020 | No Access for Inspection | BRAD BESCOS |
| Deputy Grading | 8/3/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 8/4/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 8/5/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 8/6/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 8/7/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 8/10/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 8/11/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 8/12/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 8/13/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 8/14/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 8/17/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 8/18/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 8/19/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 8/20/2020 | Approved | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 8/20/2020 | Partial Approval | BRIAN SULLIVAN |
| Deputy Grading | 8/21/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 8/24/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 8/25/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 8/26/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 8/27/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 8/28/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 8/31/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 9/1/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 9/2/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 9/3/2020 | Conditional Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 9/3/2020 | Corrections Issued | BRIAN SULLIVAN |
| Deputy Grading | 9/4/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 9/8/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 9/9/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 9/10/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 9/11/2020 | Conditional Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 9/15/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Special/Order Compliance | 9/15/2021 | Partial Inspection | BRAD BESCOS |