7401 N LANKERSHIM BLVD 91605

Certificate Information: 7401 N LANKERSHIM BLVD 91605

Application / Permit
17010-30003-02985
Plan Check / Job No.
B19WL01487
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(7) Garage - Private
Work Description
Early start foundation only for new 5-story mixed use commercial residential building. 4-story, 108 units (9 units (8%) set aside for Extremely low income household), Type VA apartment building over one level Type I podium commercial/parking over one level basement parking. (TOC project)
Permit Issued
Issued on 4/4/2019
Issuing Office
Valley
Current Status
Permit Finaled on 4/14/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/19/2019 APPLICANT
Assigned to Plan Check Engineer 3/19/2019 KAMRAN GHOTBI RAVANDI
Corrections Issued 3/19/2019 KAMRAN GHOTBI RAVANDI
Plan Check Approved 4/2/2019 KAMRAN GHOTBI RAVANDI
No Progress 4/2/2019 KAMRAN GHOTBI RAVANDI
Plan Check Approved 4/2/2019 KAMRAN GHOTBI RAVANDI
Issued 4/4/2019 LADBS
Permit Finaled 4/14/2021 DANNY RODRIGUEZ

Permit Application Clearance Information

"Q" conditions Cleared 3/19/2019 DAISY BENICIA
"T" removal Cleared 3/19/2019 DAISY BENICIA
CPC Cleared 3/19/2019 DAISY BENICIA
Tract Map conditions Cleared 3/19/2019 DAISY BENICIA
Address approval Cleared 3/21/2019 JEANETTE VONG
Construction near power lines Cleared 3/21/2019 OSCAR CASTRO
Density Bonus 12.22.A.31 Cleared 3/21/2019 JAMES MCCARTHY
Driveway location Cleared 3/21/2019 KEN AITCHISON
Highway dedication Cleared 3/21/2019 JEANETTE VONG
Hydrant and Access approval Cleared 3/21/2019 GEORGE SUCHAND
Internal circulation Cleared 3/21/2019 KEN AITCHISON
Low Impact Development Cleared 3/21/2019 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 3/21/2019 JEANETTE VONG
DAS Clearance Cleared 3/22/2019 NORLITO MEDRANO
Eng Process Fee Ord 176,300 Cleared 3/22/2019 ISRAEL TAMIRU
Green Code Cleared 3/22/2019 KAMRAN GHOTBI RAVANDI
Permit Cleared 3/22/2019 ISRAEL TAMIRU
Sewer availability Cleared 3/22/2019 ISRAEL TAMIRU
Work Adjacent to Public Way Cleared 3/22/2019 ISRAEL TAMIRU
Miscellaneous Cleared 3/26/2019 DAISY BENICIA
Site Plan review Cleared 3/26/2019 DAISY BENICIA
Fire Marshall Fire Life Safety Cleared 3/28/2019 OSCAR SALGADO JR
Building over 3-story or 36-ft Cleared 4/2/2019 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 4/2/2019 CALOSHA APPROVED

Contact Information

Contractor Jasco Enterprise Inc; Lic. No.: 871467-B 12439 MAGNOLIA BL 185      VALLEY VILLAGE, CA 91607
Engineer Gharai,, Armin; Lic. No.: C61464 6701 CORIE LN      WEST HILLS, CA 91307
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065
Engineer Vidal, Juan Alonso; Lic. No.: GE861 15331 DOGWOOD ST      WESTMINSTER, CA 92683

Inspector Information

JOHN KITCKO, (818) 374-1109 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/30/2019 Partial Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 6/4/2019 Conditional Approval ANDREW DORSO
Deputy Reinf. Concrete 6/26/2019 Approved ROBERT DAVIS
Footing/Foundation/Slab 7/23/2019 Partial Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 7/25/2019 Approved DANNY RODRIGUEZ
Footing/Foundation/Slab 7/25/2019 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 7/25/2019 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 7/26/2019 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 7/29/2019 Conditional Approval JAMES STEPHENS
Footing/Foundation/Slab 7/29/2019 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/1/2019 Conditional Approval ROBERT COLE
Footing/Foundation/Slab 8/1/2019 Partial Approval ROBERT COLE
Deputy Reinf. Concrete 8/2/2019 Conditional Approval ROBERT COLE
Excavation/Setback/Form/Re-Bar 8/2/2019 Not Ready for Inspection ROBERT COLE
Deputy Reinf. Concrete 8/5/2019 Conditional Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 8/5/2019 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 8/6/2019 Partial Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 8/9/2019 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 8/9/2019 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 8/13/2019 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 8/13/2019 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 8/14/2019 Conditional Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 8/15/2019 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 8/15/2019 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 8/16/2019 Corrections Issued DANNY RODRIGUEZ
Reinforced Concrete Frame 8/16/2019 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 8/20/2019 Partial Approval JOHN KITCKO
Reinforced Concrete Frame 8/20/2019 Partial Approval JOHN KITCKO
Excavation/Setback/Form/Re-Bar 8/21/2019 Partial Approval DANNY RODRIGUEZ
Reinforced Concrete Frame 8/21/2019 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 8/23/2019 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 8/23/2019 Not Ready for Inspection JOHN KITCKO
Footing/Foundation/Slab 8/23/2019 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 8/26/2019 Approved DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 8/26/2019 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 8/26/2019 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 8/27/2019 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 8/27/2019 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 8/27/2019 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 8/28/2019 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 8/28/2019 Conditional Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 8/30/2019 Corrections Issued DANNY RODRIGUEZ
Reinforced Concrete Frame 8/30/2019 Partial Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 9/3/2019 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 9/3/2019 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 9/3/2019 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 9/12/2019 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 9/12/2019 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 9/13/2019 Partial Approval DANNY RODRIGUEZ
Reinforced Concrete Frame 9/13/2019 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 9/16/2019 Conditional Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 9/20/2019 Partial Approval DANNY RODRIGUEZ
Reinforced Concrete Frame 9/20/2019 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 9/23/2019 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 9/23/2019 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 9/25/2019 Partial Approval DANNY RODRIGUEZ
Reinforced Concrete Frame 9/25/2019 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 10/9/2019 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 10/11/2019 Conditional Approval RICKEY JACKSON
Deputy Reinf. Concrete 10/16/2019 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 10/17/2019 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 10/28/2019 Conditional Approval ROBERT COLE
Deputy Reinf. Concrete 11/4/2019 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/6/2019 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/7/2019 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/8/2019 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/13/2019 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/14/2019 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/15/2019 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/19/2019 Approved DANNY RODRIGUEZ
Deputy Drilled-In Anchors 11/20/2019 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/20/2019 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/21/2019 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/22/2019 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/25/2019 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/26/2019 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 12/5/2019 Approved DANNY RODRIGUEZ
Deputy Seismic Resistance 12/5/2019 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 12/16/2019 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 12/27/2019 Conditional Approval JAMES STEPHENS
Deputy Reinf. Concrete 1/8/2020 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 1/10/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 1/13/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 1/14/2020 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 1/24/2020 Conditional Approval JAMES STEPHENS
Deputy Reinf. Concrete 1/28/2020 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 1/29/2020 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 1/30/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 2/13/2020 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 2/26/2020 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 2/27/2020 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 3/4/2020 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 3/5/2020 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 3/6/2020 Conditional Approval JAMES STEPHENS
Drywall Nailing 10/6/2020 Not Ready for Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 10/6/2020 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 10/7/2020 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 10/7/2020 Not Ready for Inspection DANNY RODRIGUEZ