1804 N DOHENY DR 90069

Certificate Information: 1804 N DOHENY DR 90069

Application / Permit
17010-30001-04491
Plan Check / Job No.
B23WL03049
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Supplemental ref. to permit# 17010-30000-04491 to change the work description from new pool equipment room and BBQ structure to new deached 1-story ADU per state law (CA Govt. Code 65852.2 (e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d),(g))
Permit Issued
Issued on 8/9/2024
Issuing Office
Current Status
Issued on 8/9/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/13/2023 APPLICANT
Assigned to Plan Check Engineer 12/20/2023 HOOMAN HAJIZADEH
Corrections Issued 1/5/2024 HOOMAN HAJIZADEH
Quality Review Completed 1/18/2024 KAVIAN REFAHI
Applicant returned to address corrections 2/9/2024 HOOMAN HAJIZADEH
Applicant returned to address corrections 4/29/2024 HOOMAN HAJIZADEH
Building Plans Picked Up 5/10/2024 APPLICANT
Applicant returned to address corrections 6/11/2024 HOOMAN HAJIZADEH
Applicant returned to address corrections 7/11/2024 HOOMAN HAJIZADEH
Plan Check Approved 8/8/2024 HOOMAN HAJIZADEH
Issued 8/9/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 5/15/2024 JUSTIN BICOL
BHO/Hillside ordinance Cleared 5/15/2024 JUSTIN BICOL
BHO/Hillside ordinance Cleared 5/15/2024 JUSTIN BICOL
BHO/Hillside ordinance Cleared 5/15/2024 JUSTIN BICOL
BHO/Hillside ordinance Cleared 5/15/2024 JUSTIN BICOL
BHO/Hillside ordinance Cleared 5/15/2024 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 5/15/2024 JUSTIN BICOL
Sewer availability Cleared 5/15/2024 DAVID LOPEZ
Hydrant and Access approval Cleared 6/21/2024 JOHN CONNEALLY
GPI Written Notices Cleared 7/11/2024 HOOMAN HAJIZADEH
Grading Pre-Inspection Cleared 7/11/2024 HOOMAN HAJIZADEH
Low Impact Development (LID) Cleared 7/19/2024 ERNEST TSE
Roof/Waste drainage to street Cleared 7/22/2024 JUSTIN BICOL

Contact Information

Contractor Owner-Builder       ,
Contractor Williams Craig R Construction Inc; Lic. No.: 479539-B 2219 PONTIUS AVENUE      LOS ANGELES, CA 90064
Engineer Kile,, Johnny C; Lic. No.: C92658 3627 W 64TH STREET      LOS ANGELES, CA 90043
Engineer Lau, David Harkwong; Lic. No.: C34961 12467 W WASHINGTON BLVD      LOS ANGELES, CA 90066
Geologist Feffer, Joshua Rafael; Lic. No.: EG2138 12253 GORHAM AVE      LOS ANGELES, CA 90049

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 8/14/2024 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 8/27/2024 Conditional Approval RAUL BARAJAS
Footing/Foundation/Slab 8/28/2024 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 8/29/2024 Conditional Approval RAUL BARAJAS
Underground Mechanical 9/17/2024 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 9/25/2024 Conditional Approval RAUL BARAJAS
Footing/Foundation/Slab 9/25/2024 Approved RAUL BARAJAS
Deputy Reinf. Concrete 9/27/2024 Conditional Approval RAUL BARAJAS
Deputy Steel/Welding 10/8/2024 Conditional Approval BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 11/19/2024 Partial Approval RAUL BARAJAS
Structural Steel Frame 11/19/2024 Partial Approval RAUL BARAJAS
Insulation 1/24/2025 Partial Approval RAUL BARAJAS
Structural Steel Frame 1/24/2025 Not Ready for Inspection RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 4/28/2025 Not Ready for Inspection CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 5/29/2025 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Rough 6/27/2025 Corrections Issued BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 11/5/2025 Corrections Issued BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 11/12/2025 Partial Approval BRENDAN MORELLI
ELECTRICAL-Rough 12/16/2025 Approved SCOTT FINNILA
HVAC-Rough 1/21/2026 Approved DAVID WILLIAMS
PLUMBING-Rough 1/22/2026 Approved DAVID WILLIAMS
BUILDING-Rough-Frame 2/5/2026 Corrections Issued DAVID WILLIAMS
Green Building Rough 2/5/2026 Approved DAVID WILLIAMS
Verify Sprinkler Sign Off 2/5/2026 Approved DAVID WILLIAMS
Insulation 2/19/2026 Corrections Issued CRAIG VAUGHAN
Drywall Nailing 3/13/2026 Approved DAVID WILLIAMS
Interior/Exterior Lathing 3/27/2026 Partial Approval DAVID WILLIAMS