1726 N NORTH SPRING ST 90012
Certificate Information: 1726 N NORTH SPRING ST 90012
- Application / Permit
- 17010-30001-03758
- Plan Check / Job No.
- B22WL02839
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (22) Storage Building
- Work Description
- SUPPLEMENTAL TO PERMIT NO. 17010-30000-03758 TO RELOCATE PROPOSED NEW UTILITY ROOM BUILDING.
- Permit Issued
- Issued on 5/1/2023
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 5/1/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/20/2022 | SERGIO SILVA |
| Corrections Issued | 7/20/2022 | SERGIO SILVA |
| Plan Check Approved | 8/24/2022 | SERGIO SILVA |
| Building Plans Picked Up | 4/20/2023 | APPLICANT |
| Issued | 5/1/2023 | APPLICANT |
Permit Application Clearance Information
| Specific Plan | Cleared | 8/3/2022 | RUBEN VASQUEZ |
| ZA Case | Cleared | 8/3/2022 | RUBEN VASQUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/8/2022 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 8/8/2022 | CELINA MORENO |
| Green Code | Cleared | 8/9/2022 | SERGIO SILVA |
| DAS Clearance | Cleared | 8/15/2022 | SERGIO SILVA |
Contact Information
| Contractor | Torres General Contractors Inc; Lic. No.: 1065627-B | 2271 W MALVERN AVENUE #150 FULLERTON, CA 92833 |
| Engineer | Valancius, Joseph; Lic. No.: S3609 | 2550 N HOLLYWOOD WY STE 500 BURBANK, CA 91505 |
Inspector Information
| RONALD JIMENEZ, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| LARRY ARNICK, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEY BUCHANAN, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| ERNESTO CORRAL, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL ESPINOZA, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/7/2023 | Conditional Approval | JULIAN CAPUCETTI |
| Reinforced Concrete Frame | 8/10/2023 | Not Ready for Inspection | JULIAN CAPUCETTI |
| Deputy Reinf. Masonry | 8/14/2023 | Conditional Approval | JULIAN CAPUCETTI |
| Deputy Reinf. Masonry | 8/15/2023 | Conditional Approval | JULIAN CAPUCETTI |
| Deputy Reinf. Masonry | 8/23/2023 | Conditional Approval | JULIAN CAPUCETTI |
| Masonry Wall/Backfill | 8/24/2023 | Partial Approval | JULIAN CAPUCETTI |
| Masonry Wall/Backfill | 9/20/2023 | Partial Approval | RAFAEL CORTES |
| Masonry Wall/Backfill | 10/26/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Reinforced Masonry Frame | 10/27/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Pre-Inspection | 10/30/2023 | Approved | RAFAEL CORTES |
| Excavation/Setback/Form/Re-Bar | 12/29/2023 | Approved | RAFAEL ESPINOZA |
| Drywall Nailing | 4/24/2025 | Not Ready for Inspection | JEFFREY FULTON |
| Final | 4/24/2025 | Not Ready for Inspection | JEFFREY FULTON |
| Pre-Inspection | 4/24/2025 | Not Ready for Inspection | JEFFREY FULTON |
| Reinforced Masonry Frame | 4/24/2025 | Not Ready for Inspection | JEFFREY FULTON |
| Structural Steel Frame | 4/24/2025 | Not Ready for Inspection | JEFFREY FULTON |