4847 W BEVERLY BLVD 90004
Certificate Information: 4847 W BEVERLY BLVD 90004
- Application / Permit
- 17010-30000-05074
- Plan Check / Job No.
- B17WL07528
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- (N) 4 STORY APARTMENT BUILDING (16-UNITS) OVER A BASEMENT PARKING GARAGE
- Permit Issued
- Issued on 8/30/2018
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 5/10/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/22/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 1/18/2018 | TARIK SAOUD |
| Disabled Access Plans Picked Up | 1/25/2018 | APPLICANT |
| Corrections Issued | 1/31/2018 | TARIK SAOUD |
| Quality Review Completed | 2/8/2018 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 2/8/2018 | APPLICANT |
| Plan Check Approved | 8/29/2018 | TARIK SAOUD |
| Issued | 8/30/2018 | LADBS |
| TCO Issued (Expire Date: 10-27-2021) | 4/30/2021 | DAVID TSAU |
| CofO in Progress | 5/10/2021 | DANIEL MC AULIFFE |
| Permit Finaled | 5/10/2021 | TERRY HERR |
| CofO Issued | 5/10/2021 | TERRY HERR |
| Permit Finaled | 5/10/2021 | TERRY HERR |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 4/25/2018 | GEORGE SUCHAND |
| Address approval | Cleared | 5/3/2018 | KAREN LE |
| Eng Process Fee Ord 176,300 | Cleared | 5/3/2018 | KAREN LE |
| Permit | Cleared | 5/3/2018 | KAREN LE |
| DAS Clearance | Cleared | 5/7/2018 | SHINE LIN |
| Bicycle Parking | Cleared | 5/11/2018 | FATIMA GUERRA |
| Highway dedication | Cleared | 5/11/2018 | ADRIAN SANCHEZ |
| Frnt yard landscape/Water mgmt | Cleared | 5/14/2018 | SOPHIE GABEL-SCHEINBAU |
| Opn space landscape/Water mgmt | Cleared | 5/14/2018 | SOPHIE GABEL-SCHEINBAU |
| Fire Marshall Fire Life Safety | Cleared | 5/30/2018 | ANDREW KO |
| Construction near power lines | Cleared | 8/7/2018 | RIDWAN HARDY |
| Low Impact Development | Cleared | 8/16/2018 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 8/17/2018 | ADRIAN SANCHEZ |
| Green Code | Cleared | 8/22/2018 | BRYAN MEYER |
| Sewer availability | Cleared | 8/27/2018 | KRISTEN LY |
| Building over 3-story or 36-ft | Cleared | 8/29/2018 | CALOSHA APPROVED |
| Excavation more than 5-ft deep | Cleared | 8/29/2018 | CALOSHA APPROVED |
Contact Information
| Architect | Bittoni, Mark Christopher; Lic. No.: C34136 | 434 N GREENCRAIG ROAD LOS ANGELES, CA 90049 |
| Contractor | Owner-Builder | , |
| Engineer | Eden, Joseph Taki; Lic. No.: C39955 | 14416 FRIAR ST STE A VAN NUYS, CA 91401 |
| Engineer | Melnyk, Matthew John; Lic. No.: S5853 | 2100 N MAIN STREET, SUITE A1 LOS ANGELES, CA 90031 |
| Engineer | Tucker, Keith D; Lic. No.: GE841 | PO BOX 8133 HUNTINGTON BEACH, CA 92615 |
Inspector Information
| DAVID BURKHEAD, (213) 482-7294 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/6/2018 | Approved | TED RIES |
| Footing/Foundation/Slab | 12/27/2018 | Partial Approval | TED RIES |
| Footing/Foundation/Slab | 1/3/2019 | Partial Approval | TED RIES |
| Deputy Reinf. Concrete | 1/4/2019 | Approved | TED RIES |
| Deputy Shotcrete | 1/25/2019 | Approved | TED RIES |
| Deputy Shotcrete | 1/28/2019 | Approved | JEFF BYTHEWAY |
| Footing/Foundation/Slab | 1/30/2019 | Partial Approval | TED RIES |
| Deputy Shotcrete | 2/25/2019 | Approved | JEFF BYTHEWAY |
| Deputy Reinf. Concrete | 2/26/2019 | Approved | TED RIES |
| Deputy Reinf. Concrete | 3/14/2019 | Approved | JEFF BYTHEWAY |
| Footing/Foundation/Slab | 3/19/2019 | Conditional Approval | TED RIES |
| Footing/Foundation/Slab | 3/20/2019 | Partial Approval | TED RIES |
| Footing/Foundation/Slab | 4/3/2019 | Partial Inspection | ERNESTO CORRAL |
| Deputy Reinf. Concrete | 4/5/2019 | Approved | TED RIES |
| Footing/Foundation/Slab | 4/16/2019 | Corrections Issued | TED RIES |
| Deputy Reinf. Concrete | 4/17/2019 | Approved | TED RIES |
| Footing/Foundation/Slab | 4/19/2019 | Partial Approval | TED RIES |
| Footing/Foundation/Slab | 5/3/2019 | Partial Approval | TED RIES |
| Reinforced Masonry Frame | 5/9/2019 | Partial Approval | TED RIES |
| Footing/Foundation/Slab | 5/13/2019 | Partial Approval | TED RIES |
| Footing/Foundation/Slab | 6/11/2019 | Partial Inspection | TED RIES |
| Reinforced Masonry Frame | 7/9/2019 | Partial Approval | DANIEL MC AULIFFE |
| Footing/Foundation/Slab | 7/10/2019 | Not Ready for Inspection | DANIEL MC AULIFFE |
| Piling/Pier/Caisson | 7/11/2019 | Partial Approval | DANIEL MC AULIFFE |
| Footing/Foundation/Slab | 7/12/2019 | Not Ready for Inspection | DANIEL MC AULIFFE |
| Deputy Steel/Welding | 8/12/2019 | Conditional Approval | DANIEL MC AULIFFE |
| Green Building Rough | 8/29/2019 | Not Ready for Inspection | DANIEL MC AULIFFE |
| Verify Sprinkler Sign Off | 8/29/2019 | Not Ready for Inspection | DANIEL MC AULIFFE |
| Wood Frame | 8/29/2019 | Partial Approval | DANIEL MC AULIFFE |
| Green Building Rough | 9/13/2019 | Approved | DANIEL MC AULIFFE |
| Verify Sprinkler Sign Off | 9/13/2019 | Not Ready for Inspection | DANIEL MC AULIFFE |
| Wood Frame | 9/13/2019 | Partial Approval | DANIEL MC AULIFFE |
| Deputy Steel/Welding | 9/25/2019 | Conditional Approval | DANIEL MC AULIFFE |
| Verify Sprinkler Sign Off | 9/25/2019 | Not Ready for Inspection | DANIEL MC AULIFFE |
| Wood Frame | 9/25/2019 | Partial Approval | DANIEL MC AULIFFE |
| Verify Sprinkler Sign Off | 10/4/2019 | Partial Approval | DANIEL MC AULIFFE |
| Wood Frame | 10/4/2019 | Partial Approval | DANIEL MC AULIFFE |
| Verify Sprinkler Sign Off | 10/18/2019 | Approved | DANIEL MC AULIFFE |
| Wood Frame | 10/18/2019 | Partial Approval | DANIEL MC AULIFFE |
| Deputy Steel/Welding | 10/28/2019 | Conditional Approval | DANIEL MC AULIFFE |
| Wood Frame | 11/4/2019 | Partial Approval | DANIEL MC AULIFFE |
| Wood Frame | 12/17/2019 | Partial Approval | DANIEL MC AULIFFE |
| Deputy Steel/Welding | 12/31/2019 | Conditional Approval | DANIEL MC AULIFFE |
| Deputy Steel/Welding | 1/8/2020 | Conditional Approval | DANIEL MC AULIFFE |
| Floor/Roof Diaphrgm/Shear Wall | 1/9/2020 | Partial Inspection | DANIEL MC AULIFFE |
| Deputy Wood Construction | 2/5/2020 | Conditional Approval | DANIEL MC AULIFFE |
| Floor/Roof Diaphrgm/Shear Wall | 2/5/2020 | Partial Inspection | DANIEL MC AULIFFE |
| Deputy Steel/Welding | 2/11/2020 | Conditional Approval | DANIEL MC AULIFFE |
| Floor/Roof Diaphrgm/Shear Wall | 2/11/2020 | Not Ready for Inspection | DANIEL MC AULIFFE |
| Deputy Wood Construction | 2/18/2020 | Conditional Approval | DANIEL MC AULIFFE |
| Deputy Steel/Welding | 2/19/2020 | Conditional Approval | DANIEL MC AULIFFE |
| Insulation | 2/19/2020 | Partial Approval | DANIEL MC AULIFFE |
| Deputy Steel/Welding | 2/21/2020 | Conditional Approval | DANIEL MC AULIFFE |
| Deputy Drilled-In Anchors | 3/2/2020 | Conditional Approval | DANIEL MC AULIFFE |
| Deputy Wood Construction | 3/3/2020 | Conditional Approval | DANIEL MC AULIFFE |
| Deputy Steel/Welding | 3/4/2020 | Conditional Approval | DANIEL MC AULIFFE |
| Wood Frame | 3/4/2020 | Partial Approval | DANIEL MC AULIFFE |
| Deputy Wood Construction | 3/5/2020 | Conditional Approval | DANIEL MC AULIFFE |
| Insulation | 3/20/2020 | Partial Approval | DANIEL MC AULIFFE |
| Interior/Exterior Lathing | 3/27/2020 | Partial Approval | DANIEL MC AULIFFE |
| Insulation | 4/16/2020 | Partial Approval | DANIEL MC AULIFFE |
| Drywall Nailing | 5/1/2020 | Partial Approval | DANIEL MC AULIFFE |
| Wood Frame | 5/4/2020 | Not Ready for Inspection | DANIEL MC AULIFFE |
| Deputy Wood Construction | 5/5/2020 | Conditional Approval | DANIEL MC AULIFFE |
| Deputy Wood Construction | 5/7/2020 | Conditional Approval | DANIEL MC AULIFFE |
| Wood Frame | 6/11/2020 | Partial Approval | DANIEL MC AULIFFE |
| Insulation | 6/15/2020 | Partial Approval | DANIEL MC AULIFFE |
| Wood Frame | 6/24/2020 | Approved | DANIEL MC AULIFFE |
| Drywall Nailing | 6/26/2020 | Partial Approval | DANIEL MC AULIFFE |
| Insulation | 7/1/2020 | Partial Approval | DANIEL MC AULIFFE |
| Drywall Nailing | 7/13/2020 | Approved | DANIEL MC AULIFFE |
| Interior/Exterior Lathing | 7/27/2020 | Partial Inspection | DANIEL MC AULIFFE |
| Interior/Exterior Lathing | 8/3/2020 | Partial Approval | DANIEL MC AULIFFE |
| Interior/Exterior Lathing | 8/10/2020 | Approved | DANIEL MC AULIFFE |
| Deputy Steel/Welding | 9/21/2020 | Conditional Approval | DANIEL MC AULIFFE |
| Deputy Steel/Welding | 10/8/2020 | Conditional Approval | DANIEL MC AULIFFE |
| Deputy Drilled-In Anchors | 10/13/2020 | Conditional Approval | DAVID BURKHEAD |
| Deputy Steel/Welding | 10/13/2020 | Conditional Approval | DAVID BURKHEAD |
| Deputy Reinf. Concrete | 10/19/2020 | No Access for Inspection | DANIEL MC AULIFFE |
| Structural Steel Frame | 10/21/2020 | Partial Inspection | DANIEL MC AULIFFE |
| Pre-Inspection | 11/10/2020 | Partial Inspection | DANIEL MC AULIFFE |
| Deputy Steel/Welding | 2/1/2021 | Conditional Approval | DANIEL MC AULIFFE |
| Deputy Steel/Welding | 2/2/2021 | Conditional Approval | DANIEL MC AULIFFE |
| Reinforced Concrete Frame | 2/4/2021 | Partial Approval | DANIEL MC AULIFFE |
| Special/Order Compliance | 2/12/2021 | Off-Hour Fees Due | |
| Pre-Inspection | 2/16/2021 | Partial Inspection | DANIEL MC AULIFFE |
| Final | 4/16/2021 | Conditional Approval | DANIEL MC AULIFFE |
| Footing/Foundation/Slab | 4/16/2021 | Approved | DANIEL MC AULIFFE |
| Green Building Final | 4/16/2021 | Approved | DANIEL MC AULIFFE |
| Reinforced Concrete Frame | 4/16/2021 | Approved | DANIEL MC AULIFFE |
| SGSOV-Seismic Gas S/O Valve | 4/16/2021 | SGSOV Approved | DANIEL MC AULIFFE |
| Smoke Detectors | 4/16/2021 | Approved | DANIEL MC AULIFFE |
| Structural Steel Frame | 4/16/2021 | Approved | DANIEL MC AULIFFE |
| Final | 4/20/2021 | Conditional Approval | DANIEL MC AULIFFE |