1800 N DOHENY DR 90069
Certificate Information: 1800 N DOHENY DR 90069
- Application / Permit
- 17010-30000-04488
- Plan Check / Job No.
- B17WL06685
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 2 story single family dwelling with basement/garage
- Permit Issued
- Issued on 10/16/2019
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 10/16/2019
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/15/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2017 | KAMRAN GHOTBI RAVANDI |
| Corrections Issued | 11/27/2017 | KAMRAN GHOTBI RAVANDI |
| Quality Review Completed | 12/5/2017 | FELIX FIGUEROA |
| Building Plans Picked Up | 12/5/2017 | APPLICANT |
| Applicant returned to address corrections | 5/24/2018 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 7/11/2018 | KAMRAN GHOTBI RAVANDI |
| Green Plans Picked Up | 9/25/2018 | APPLICANT |
| Applicant returned to address corrections | 10/5/2018 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 10/12/2018 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 4/23/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 5/7/2019 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 10/9/2019 | KAMRAN GHOTBI RAVANDI |
| Issued | 10/16/2019 | LADBS |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 12/5/2017 | ANDREW SLUSSER |
| BHO/Hillside ordinance | Cleared | 12/5/2017 | ANDREW SLUSSER |
| BHO/Hillside ordinance | Cleared | 12/5/2017 | ANDREW SLUSSER |
| CPC | Cleared | 12/5/2017 | TREVOR MARTIN |
| Eng Process Fee Ord 176,300 | Cleared | 12/5/2017 | ANDREW SLUSSER |
| Sewer availability | Cleared | 12/5/2017 | ANDREW SLUSSER |
| Hydrant and Access approval | Cleared | 7/13/2018 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 9/18/2018 | RYAN HUDSON |
| Permit | Cleared | 9/18/2018 | MICHAEL CASTILLO |
| Roof/Waste drainage to street | Cleared | 9/18/2018 | MICHAEL CASTILLO |
| Green Code | Cleared | 10/10/2018 | KAMRAN GHOTBI RAVANDI |
| Excavation more than 5-ft deep | Cleared | 10/12/2018 | CALOSHA APPROVED |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Daneshfar, Kourosh Dan; Lic. No.: C68377 | 19722 ARMINTA ST WINNETKA, CA 91306 |
| Engineer | Lau, David Harkwong; Lic. No.: C34961 | 12467 W WASHINGTON BLVD LOS ANGELES, CA 90066 |
| Geologist | Feffer, Joshua Rafael; Lic. No.: EG2138 | 12253 GORHAM AVE LOS ANGELES, CA 90049 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 12/6/2023 | Conditional Approval | RAUL BARAJAS |
| Piling/Pier/Caisson | 12/7/2023 | Partial Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 12/8/2023 | Conditional Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 1/5/2024 | Conditional Approval | RAUL BARAJAS |
| Reinforced Concrete Frame | 1/5/2024 | Partial Inspection | RAUL BARAJAS |
| Deputy Reinf. Concrete | 1/16/2024 | Conditional Approval | RAUL BARAJAS |
| Underground Mechanical | 1/17/2024 | Corrections Issued | RAUL BARAJAS |
| Underground Mechanical | 1/22/2024 | Not Ready for Inspection | RAUL BARAJAS |
| Deputy Reinf. Concrete | 3/15/2024 | Conditional Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 3/18/2024 | Conditional Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 3/18/2024 | Partial Approval | RAUL BARAJAS |
| Underground Mechanical | 3/18/2024 | Partial Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 3/20/2024 | Conditional Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 3/27/2024 | Conditional Approval | BRIAN SULLIVAN |
| Piling/Pier/Caisson | 3/27/2024 | Partial Approval | CRAIG VAUGHAN |
| Deputy Reinf. Concrete | 3/29/2024 | Conditional Approval | RAUL BARAJAS |
| Deputy Shotcrete | 4/4/2024 | Conditional Approval | RAUL BARAJAS |
| Reinforced Concrete Frame | 4/5/2024 | Partial Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 4/9/2024 | Conditional Approval | RAUL BARAJAS |
| Deputy Shotcrete | 4/9/2024 | Conditional Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 4/10/2024 | Approved | RAUL BARAJAS |
| Deputy Shotcrete | 4/10/2024 | Approved | RAUL BARAJAS |
| Deputy Drilled-In Anchors | 5/21/2024 | Conditional Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 6/6/2024 | Conditional Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 6/6/2024 | Partial Approval | RAUL BARAJAS |
| Reinforced Concrete Frame | 6/6/2024 | Partial Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 6/7/2024 | Conditional Approval | RAUL BARAJAS |
| Deputy Other (see comments) | 6/12/2024 | Conditional Approval | RAUL BARAJAS |
| Deputy Shotcrete | 6/12/2024 | Conditional Approval | RAUL BARAJAS |
| Deputy Steel/Welding | 10/8/2024 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Steel/Welding | 10/9/2024 | Conditional Approval | RAUL BARAJAS |
| Deputy Wood Construction | 10/23/2024 | Conditional Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2024 | Partial Approval | RAUL BARAJAS |
| Deputy Wood Construction | 11/18/2024 | Conditional Approval | NICHOLAS LOPEZ |
| Deputy Steel/Welding | 11/27/2024 | Conditional Approval | RAUL BARAJAS |
| Deputy Drilled-In Anchors | 12/13/2024 | Conditional Approval | RAUL BARAJAS |
| Deputy Wood Construction | 5/2/2025 | Conditional Approval | RAUL BARAJAS |
| PLUMBING-Rough | 6/27/2025 | Corrections Issued | BRENDAN MORELLI |
| Deputy Drilled-In Anchors | 11/19/2025 | Conditional Approval | ALEX COLIN |
| Footing/Foundation/Slab | 11/20/2025 | Partial Approval | DAVID WILLIAMS |
| Deputy Reinf. Concrete | 11/24/2025 | Conditional Approval | DAVID WILLIAMS |
| Deputy Reinf. Concrete | 11/25/2025 | Conditional Approval | ROY SPAULDING |
| Deputy Reinf. Concrete | 11/26/2025 | Conditional Approval | ROY SPAULDING |
| Deputy Reinf. Concrete | 12/4/2025 | Conditional Approval | DAVID WILLIAMS |
| Deputy Reinf. Concrete | 12/9/2025 | Conditional Approval | DAVID WILLIAMS |
| ELECTRICAL-Rough | 12/16/2025 | Approved | SCOTT FINNILA |
| Deputy Drilled-In Anchors | 1/7/2026 | Conditional Approval | DAVID WILLIAMS |
| Footing/Foundation/Slab | 1/12/2026 | Partial Approval | DAVID WILLIAMS |
| Deputy Reinf. Concrete | 1/14/2026 | Conditional Approval | DAVID WILLIAMS |
| HVAC-Rough | 1/16/2026 | Approved | DAVID WILLIAMS |
| PLUMBING-Rough | 1/22/2026 | Approved | DAVID WILLIAMS |
| Deputy Wood Construction | 1/29/2026 | Conditional Approval | CRAIG VAUGHAN |
| Sewer | 1/29/2026 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 1/30/2026 | Partial Approval | DAVID WILLIAMS |
| Green Building Rough | 1/30/2026 | Approved | DAVID WILLIAMS |
| Verify Sprinkler Sign Off | 1/30/2026 | Approved | DAVID WILLIAMS |
| Deputy Reinf. Concrete | 2/10/2026 | Conditional Approval | DAVID WILLIAMS |
| Footing/Foundation/Slab | 2/11/2026 | Partial Approval | DAVID WILLIAMS |
| Insulation | 2/19/2026 | Partial Approval | CRAIG VAUGHAN |
| Drywall Nailing | 3/13/2026 | Approved | DAVID WILLIAMS |
| Interior/Exterior Lathing | 3/27/2026 | Partial Approval | DAVID WILLIAMS |