7024 W LEXINGTON AVE 90038
Certificate Information: 7024 W LEXINGTON AVE 90038
- Application / Permit
- 17010-30000-04174
- Plan Check / Job No.
- B17WL06303
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- a proposed 3 story s.f.d. w/ attached garage for small lot subdivision (Lot C ) "SMALL LOT SUBDIVISION PURSUANT TO PRELIMINARY PARCEL MAP NO. AA-2015-4693-PMLA-SL. A CERTIFICATE OF OCCUPANCY (TEMPORARY OR FINAL) SHALL NOT BE ISSUED UNTIL AFTER THE FINAL MAP IS RECORDED"
- Permit Issued
- Issued on 1/9/2019
- Issuing Office
- Valley
- Current Status
- Issued on 1/9/2019
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/27/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 11/2/2017 | TARIK SAOUD |
| Corrections Issued | 11/15/2017 | TARIK SAOUD |
| Quality Review Completed | 11/22/2017 | KAMRAN GHOTBI RAVANDI |
| Green Plans Picked Up | 11/30/2017 | APPLICANT |
| Building Plans Picked Up | 12/26/2017 | APPLICANT |
| Plan Check Approved | 9/25/2018 | TARIK SAOUD |
| Issued | 1/9/2019 | LADBS |
Permit Application Clearance Information
| Address approval | Cleared | 5/30/2018 | NAZILA NOORIFAR |
| Low Impact Development | Cleared | 5/30/2018 | MATTHEW JIMENEZ |
| Miscellaneous | Cleared | 5/30/2018 | SOPHEA EK |
| Permit | Cleared | 5/30/2018 | SOPHEA EK |
| Roof/Waste drainage to street | Cleared | 6/4/2018 | SOPHEA EK |
| Eng Process Fee Ord 176,300 | Cleared | 7/13/2018 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 7/13/2018 | MARKOS PEREZ-BRAN |
| Hydrant and Access approval | Cleared | 7/24/2018 | GEORGE SUCHAND |
| Green Code | Cleared | 9/6/2018 | TARIK SAOUD |
| Miscellaneous | Cleared | 9/14/2018 | NOAH MCCOY |
| Hold | Cleared | 7/14/2021 | JASON SHEETS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/26/2021 | Partial Inspection | SCOTT FINNILA |
| Deputy Reinf. Concrete | 4/22/2021 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 4/22/2021 | Conditional Approval | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 7/15/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 7/15/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 9/13/2021 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 9/17/2021 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 10/29/2021 | Approved | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2021 | Partial Approval | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 11/29/2021 | Partial Approval | SCOTT FINNILA |
| Deputy Steel/Welding | 11/30/2021 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2021 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2021 | Partial Approval | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 12/29/2021 | Corrections Issued | SCOTT FINNILA |
| Drywall Nailing | 2/9/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 2/25/2022 | Partial Inspection | SCOTT FINNILA |
| Drywall Nailing | 3/7/2022 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2022 | Partial Approval | SCOTT FINNILA |
| Drywall Nailing | 3/23/2022 | Corrections Issued | SCOTT FINNILA |
| Drywall Nailing | 4/1/2022 | Partial Inspection | SCOTT FINNILA |
| Drywall Nailing | 4/5/2022 | Partial Approval | SCOTT FINNILA |
| Wood Frame | 4/29/2022 | Partial Approval | SCOTT FINNILA |
| Wood Frame | 5/10/2022 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2022 | Partial Approval | SCOTT FINNILA |
| HVAC-Rough | 9/29/2022 | Partial Inspection | SCOTT FINNILA |
| Deputy Wood Construction | 12/4/2023 | Conditional Approval | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 12/14/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Rough | 12/14/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 12/14/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 1/3/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Special/Order Compliance | 2/8/2024 | Corrections Issued | BRENDAN MORELLI |
| ELECTRICAL-Rough | 3/13/2024 | Partial Inspection | JOSEPH MCGARRY |
| HVAC-Rough | 3/13/2024 | Partial Inspection | JOSEPH MCGARRY |
| PLUMBING-Rough | 3/13/2024 | Partial Inspection | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 4/1/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2024 | Partial Approval | JOSEPH MCGARRY |
| Green Building Rough | 4/1/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 4/1/2024 | SGSOV Not Ready | JOSEPH MCGARRY |
| Service/Power Release | 4/1/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
| Smoke Detectors | 4/1/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
| Structural Steel Frame | 4/1/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 4/1/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
| Deck | 5/1/2024 | Partial Inspection | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2024 | Corrections Issued | JOSEPH MCGARRY |
| Special/Order Compliance | 5/7/2024 | Approved | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 7/3/2024 | Corrections Issued | SCOTT FINNILA |
| BUILDING-Rough-Frame | 8/15/2024 | Partial Approval | BRENDAN MORELLI |
| Rough-Elec/Plmb/HVAC | 8/15/2024 | Corrections Issued | BRENDAN MORELLI |
| Verify Sprinkler Sign Off | 8/15/2024 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 9/6/2024 | Approved | BRENDAN MORELLI |
| Green Building Rough | 9/6/2024 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 9/6/2024 | Partial Approval | BRENDAN MORELLI |
| Rough-Elec/Plmb/HVAC | 9/6/2024 | Approved | BRENDAN MORELLI |
| Special/Order Compliance | 9/6/2024 | Corrections Issued | BRENDAN MORELLI |
| Insulation | 9/13/2024 | Approved | BRENDAN MORELLI |
| Drywall Nailing | 10/10/2024 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 12/3/2024 | Approved | BRENDAN MORELLI |
| Shower Pan | 12/3/2024 | Approved | BRENDAN MORELLI |
| Special/Order Compliance | 12/3/2024 | Corrections Issued | BRENDAN MORELLI |
| Special/Order Compliance | 12/9/2025 | Corrections Issued | BRENDAN MORELLI |
| Special/Order Compliance | 1/9/2026 | Partial Approval | BRENDAN MORELLI |