2239 W WASHINGTON BLVD 90018
Certificate Information: 2239 W WASHINGTON BLVD 90018
- Application / Permit
- 17010-30000-03982
- Plan Check / Job No.
- B17WL05952
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (16) Dental Clinic
- Work Description
- New three story commercial office building with two medical offices on first floor, and 5 general offices on 2nd and 3rd floor over one level subteranean garage.
- Permit Issued
- Issued on 4/27/2018
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 4/27/2018
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/12/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 10/19/2017 | KAMRAN GHOTBI RAVANDI |
| Corrections Issued | 10/24/2017 | KAMRAN GHOTBI RAVANDI |
| Disabled Access Plans Picked Up | 10/25/2017 | APPLICANT |
| Green Plans Picked Up | 10/26/2017 | APPLICANT |
| Quality Review Completed | 10/30/2017 | FELIX FIGUEROA |
| Building Plans Picked Up | 10/31/2017 | APPLICANT |
| Applicant returned to address corrections | 11/29/2017 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 12/27/2017 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 1/8/2018 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 2/28/2018 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 3/14/2018 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 4/3/2018 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 4/27/2018 | KAMRAN GHOTBI RAVANDI |
| Issued | 4/27/2018 | LADBS |
Permit Application Clearance Information
| "Q" conditions | Cleared | 10/25/2017 | SARAH GOLDMAN |
| Eng Process Fee Ord 176,300 | Cleared | 10/26/2017 | OSCAR GUTIERREZ |
| Hydrant and Access approval | Cleared | 11/8/2017 | ROBERT DUFF |
| Address approval | Cleared | 11/14/2017 | STEVE MELGAR |
| Comm Cor/Mini-Mall | Cleared | 11/17/2017 | NOAH MCCOY |
| Highway dedication | Cleared | 11/17/2017 | STEVE MELGAR |
| Driveway location | Cleared | 11/21/2017 | EDUARDO HERMOSO |
| Internal circulation | Cleared | 11/21/2017 | EDUARDO HERMOSO |
| Project located in CRA area | Cleared | 11/21/2017 | JIM URQUHART |
| Sewer availability | Cleared | 11/29/2017 | OSCAR GUTIERREZ |
| Comm Cor/Mini-Mall | Cleared | 12/12/2017 | NOAH MCCOY |
| Low Impact Development | Cleared | 12/14/2017 | SAM NAVID |
| Permit | Cleared | 1/9/2018 | JAMES MORALEZ |
| DAS Clearance | Cleared | 3/9/2018 | KAMRAN GHOTBI RAVANDI |
| Green Code | Cleared | 3/9/2018 | BRYAN MEYER |
| Roof/Waste drainage to street | Cleared | 3/9/2018 | MAHELET GEBEYHU |
| Excavation more than 5-ft deep | Cleared | 4/3/2018 | CALOSHA APPROVED |
| Work Adjacent to Public Way | Cleared | 4/17/2018 | CARLA VALLADARES |
Contact Information
| Architect | Shokoufandeh, Shahram; Lic. No.: C32681 | 4628 CERRILLOS DRIVE WOODLAND HILLS, CA 91364 |
| Contractor | Owner-Builder | , |
| Engineer | Javadi-Koma, Shahram; Lic. No.: C69497 | 10349 MONTGOMERY AVE GRANADA HILLS, CA 91403 |
| Engineer | Smith, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
Inspector Information
| NICK DANERI, (213) 202-5615 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 9/14/2020 | Corrections Issued | NICK DANERI |