11801 W WESTMINSTER AVE 90066

Certificate Information: 11801 W WESTMINSTER AVE 90066

Application / Permit
17010-30000-03699
Plan Check / Job No.
B17WL05565
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2-STORY ACCESSORY DWELLING UNIT PER AB 2299 AND SB 1069.
Permit Issued
Issued on 3/26/2019
Issuing Office
West Los Angeles
Current Status
Issued on 3/26/2019
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/26/2017 APPLICANT
Assigned to Plan Check Engineer 10/19/2017 JAHANSHAH POURHASSAN
Green Plans Picked Up 10/20/2017 APPLICANT
Corrections Issued 11/13/2017 BRYAN OSORIO
Quality Review Completed 11/20/2017 JOSE RODRIGUEZ
Building Plans Picked Up 11/21/2017 APPLICANT
Applicant returned to address corrections 1/10/2018 BRYAN OSORIO
Applicant returned to address corrections 3/22/2018 BRYAN OSORIO
Applicant returned to address corrections 3/7/2019 JAHANSHAH POURHASSAN
Applicant returned to address corrections 3/21/2019 JAHANSHAH POURHASSAN
Plan Check Approved 3/26/2019 JAHANSHAH POURHASSAN
Issued 3/26/2019 LADBS

Permit Application Clearance Information

Grading Pre-Inspection Cleared 11/13/2017 GRANT WOODS
Address approval Cleared 1/10/2018 DENNIS BRAGIN
CPC Cleared 1/10/2018 TREVOR MARTIN
CPC Cleared 1/10/2018 TREVOR MARTIN
Hydrant and Access approval Cleared 2/28/2019 PEJMAN NOORI
Eng Process Fee Ord 176,300 Cleared 3/6/2019 ELAINE LEI
Low Impact Development Cleared 3/6/2019 RYAN HUDSON
Roof/Waste drainage to street Cleared 3/6/2019 ELAINE LEI
Green Code Cleared 3/13/2019 RICHARD GARCIA
GPI Written Notices Cleared 3/21/2019 BRYAN OSORIO
Sewer availability Cleared 3/22/2019 KATHLEEN HUGHEY

Contact Information

Architect Rees, Robert S; Lic. No.: C26934 3483 BARRY AVENUE      LOS ANGELES, CA 90066
Contractor Owner-Builder       ,
Engineer Messiha, Hany Gamil; Lic. No.: C56766 10834 ROSE AVE 9      LOS ANGELES, CA 90034

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 10/29/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Underground Mechanical 11/5/2020 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 11/30/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Footing/Foundation/Slab 12/8/2020 Approved RICHARD ROBLES
Wood Frame 4/21/2021 Partial Approval KENNETH NAGLE
BUILDING-Rough-Frame 10/13/2021 Corrections Issued JOHNNY MIRANDA
ELECTRICAL-Rough 10/13/2021 Corrections Issued JOHNNY MIRANDA
Green Building Rough 10/13/2021 Not Ready for Inspection JOHNNY MIRANDA
HVAC-Rough 10/13/2021 Corrections Issued JOHNNY MIRANDA
PLUMBING-Rough 10/13/2021 Corrections Issued JOHNNY MIRANDA
Verify Sprinkler Sign Off 10/13/2021 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 10/20/2021 Partial Approval JOHNNY MIRANDA
Green Building Rough 10/20/2021 Not Ready for Inspection JOHNNY MIRANDA
BUILDING-Rough-Frame 11/19/2021 Approved JOHNNY MIRANDA
Green Building Rough 11/19/2021 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 11/19/2021 Partial Approval JOHNNY MIRANDA
ELECTRICAL-Rough 1/27/2022 Approved EVAN COOPER
Green Building Rough 1/27/2022 Approved EVAN COOPER
HVAC-Rough 1/27/2022 Approved EVAN COOPER
PLUMBING-Rough 1/27/2022 Approved EVAN COOPER
Shower Pan 1/27/2022 Approved EVAN COOPER
Insulation 2/8/2022 Conditional Approval JOHNNY MIRANDA
Drywall Nailing 3/17/2022 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 4/8/2022 Corrections Issued JOHNNY MIRANDA
Interior/Exterior Lathing 4/11/2022 Approved JOHNNY MIRANDA
Underground Mechanical 8/15/2022 Approved JOHNNY MIRANDA
Final 9/1/2022 Not Ready for Inspection JOHNNY MIRANDA
Green Building Final 9/1/2022 Not Ready for Inspection JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 9/1/2022 SGSOV Not Ready JOHNNY MIRANDA
Service/Power Release 9/1/2022 Not Ready for Inspection JOHNNY MIRANDA
Smoke Detectors 9/1/2022 Not Ready for Inspection JOHNNY MIRANDA
ELECTRICAL-Final 9/28/2022 Corrections Issued ANDREW NAVE
ELECTRICAL-Final 10/12/2022 Approved JOHNNY MIRANDA
PLUMBING-Final 10/12/2022 Corrections Issued JOHNNY MIRANDA
Final 11/15/2022 Corrections Issued JOHNNY MIRANDA
Green Building Final 11/15/2022 Approved JOHNNY MIRANDA
HVAC-Final 11/15/2022 Corrections Issued JOHNNY MIRANDA
PLUMBING-Final 11/15/2022 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 11/15/2022 SGSOV Not Required JOHNNY MIRANDA
Service/Power Release 11/15/2022 Not Ready for Inspection JOHNNY MIRANDA
Smoke Detectors 11/15/2022 Approved JOHNNY MIRANDA
Final 11/30/2022 Not Ready for Inspection JESUS RODRIGUEZ
HVAC-Rough 11/30/2022 Not Ready for Inspection JESUS RODRIGUEZ
Service/Power Release 11/30/2022 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Final 12/5/2022 Approved JOHNNY MIRANDA
HVAC-Final 12/5/2022 Approved JOHNNY MIRANDA
MERV13>=Final 12/5/2022 Approved JOHNNY MIRANDA