Excavation/Setback/Form/Re-Bar
|
8/11/2020
|
Partial Inspection
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
9/1/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
9/9/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
9/15/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
9/22/2020
|
Partial Inspection
|
JOHN KITCKO
|
|
Drywall Nailing
|
9/23/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Final
|
9/23/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Footing/Foundation/Slab
|
9/23/2020
|
Conditional Approval
|
JOHN KITCKO
|
|
Green Building Final
|
9/23/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Green Building Rough
|
9/23/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Reinforced Concrete Frame
|
9/23/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Reinforced Masonry Frame
|
9/23/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
SGSOV-Seismic Gas S/O Valve
|
9/23/2020
|
SGSOV Not Ready
|
JOHN KITCKO
|
|
Smoke Detectors
|
9/23/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Structural Steel Frame
|
9/23/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
9/23/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
9/23/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Deputy Reinf. Concrete
|
9/24/2020
|
Approved
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
9/24/2020
|
Partial Approval
|
JOHN KITCKO
|
|
Green Building Rough
|
10/9/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Reinforced Masonry Frame
|
10/9/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
10/9/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Deputy Drilled-In Anchors
|
10/14/2020
|
Approved
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
10/20/2020
|
Approved
|
JOHN KITCKO
|
|
Deputy Reinf. Concrete
|
10/23/2020
|
Approved
|
JOHN KITCKO
|
|
Deputy Reinf. Masonry
|
10/23/2020
|
Approved
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
10/29/2020
|
Partial Approval
|
JOHN KITCKO
|
|
Green Building Rough
|
10/29/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Masonry Wall/Backfill
|
10/29/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Reinforced Concrete Frame
|
10/29/2020
|
Partial Inspection
|
JOHN KITCKO
|
|
Masonry Wall/Backfill
|
10/30/2020
|
Partial Approval
|
JOHN KITCKO
|
|
Footing/Foundation/Slab
|
11/17/2020
|
Partial Approval
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
1/15/2021
|
Partial Inspection
|
JOHN KITCKO
|
|
Footing/Foundation/Slab
|
1/19/2021
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Deputy Reinf. Concrete
|
1/20/2021
|
Approved
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
1/20/2021
|
Partial Approval
|
JOHN KITCKO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/4/2021
|
Partial Approval
|
JOHN KITCKO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/12/2021
|
Corrections Issued
|
JOHN KITCKO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/16/2021
|
Partial Approval
|
JOHN KITCKO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/23/2021
|
Partial Approval
|
JOHN KITCKO
|
|
Green Building Rough
|
3/10/2021
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Drywall Nailing
|
3/18/2021
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Green Building Rough
|
3/18/2021
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/31/2021
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Pre-Inspection
|
3/31/2021
|
No Access for Inspection
|
JOHN KITCKO
|
|
Drywall Nailing
|
4/1/2021
|
Partial Approval
|
JOHN KITCKO
|
|
Green Building Rough
|
4/1/2021
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Insulation
|
4/12/2021
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Insulation
|
4/13/2021
|
Conditional Approval
|
JOHN KITCKO
|
|
Drywall Nailing
|
5/4/2021
|
Partial Approval
|
JOHN KITCKO
|
|
Green Building Rough
|
5/4/2021
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Drywall Nailing
|
5/20/2021
|
Partial Approval
|
JOHN KITCKO
|
|
Green Building Rough
|
5/20/2021
|
Partial Approval
|
JOHN KITCKO
|
|
Drywall Nailing
|
5/25/2021
|
Partial Approval
|
JOHN KITCKO
|
|
Green Building Rough
|
5/25/2021
|
Partial Inspection
|
JOHN KITCKO
|
|
Drywall Nailing
|
5/27/2021
|
Partial Approval
|
JOHN KITCKO
|
|
Green Building Rough
|
5/27/2021
|
Partial Approval
|
JOHN KITCKO
|
|
Insulation
|
5/27/2021
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/15/2021
|
Partial Approval
|
ROBERT DAVIS
|
|
Insulation
|
7/15/2021
|
Partial Approval
|
ROBERT DAVIS
|
|
Drywall Nailing
|
7/23/2021
|
Partial Approval
|
ROBERT DAVIS
|
|
Green Building Rough
|
7/23/2021
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
T-Bar Ceiling
|
7/23/2021
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
Interior/Exterior Lathing
|
8/9/2021
|
Partial Approval
|
DANIEL VARNUM
|
|
Green Building Rough
|
8/19/2021
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
8/19/2021
|
Partial Inspection
|
JOHN KITCKO
|
|
Insulation
|
8/26/2021
|
Partial Approval
|
JOHN KITCKO
|
|
Insulation
|
8/30/2021
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Special/Order Compliance
|
8/30/2021
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Drywall Nailing
|
9/2/2021
|
Partial Approval
|
JOHN KITCKO
|
|
Green Building Rough
|
9/2/2021
|
Approved
|
JOHN KITCKO
|
|
Drywall Nailing
|
10/1/2021
|
Partial Approval
|
JOHN KITCKO
|
|
Interior/Exterior Lathing
|
10/21/2021
|
Partial Approval
|
JOHN KITCKO
|
|
T-Bar Ceiling
|
12/3/2021
|
Partial Approval
|
JOHN KITCKO
|
|
T-Bar Ceiling
|
3/30/2022
|
Corrections Issued
|
JOHN KITCKO
|
|
T-Bar Ceiling
|
4/7/2022
|
Partial Approval
|
ROBERT DAVIS
|
|
Pre-Inspection
|
6/9/2022
|
Partial Inspection
|
JOHN KITCKO
|
|
Special/Order Compliance
|
9/9/2022
|
Partial Inspection
|
JOHN KITCKO
|
|
Pre-Inspection
|
11/28/2022
|
Partial Inspection
|
JOHN KITCKO
|
|
Drywall Nailing
|
2/10/2023
|
Approved
|
JOHN KITCKO
|
|
Final
|
2/10/2023
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Footing/Foundation/Slab
|
2/10/2023
|
Approved
|
JOHN KITCKO
|
|
Green Building Final
|
2/10/2023
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Reinforced Concrete Frame
|
2/10/2023
|
Approved
|
JOHN KITCKO
|
|
Reinforced Masonry Frame
|
2/10/2023
|
Approved
|
JOHN KITCKO
|
|
SGSOV-Seismic Gas S/O Valve
|
2/10/2023
|
SGSOV Approved
|
JOHN KITCKO
|
|
Smoke Detectors
|
2/10/2023
|
Approved
|
JOHN KITCKO
|
|
Structural Steel Frame
|
2/10/2023
|
Approved
|
JOHN KITCKO
|
|
Wood Frame
|
2/10/2023
|
Approved
|
JOHN KITCKO
|
|
Special/Order Compliance
|
3/27/2024
|
Partial Inspection
|
JOHN KITCKO
|
|
Final
|
9/4/2024
|
OK to Issue CofO
|
JOHN KITCKO
|
|
Green Building Final
|
9/4/2024
|
Approved
|
JOHN KITCKO
|