1901 N ECHO PARK AVE 1-13 90026

Certificate Information: 1901 N ECHO PARK AVE 1-13 90026

Application / Permit
17010-30000-03242
Plan Check / Job No.
B17WL04851
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
New fully sprinklered 4 story 13 unit apartment with on grade parking garage
Permit Issued
Issued on 4/19/2018
Issuing Office
Valley
Current Status
CofO Issued on 1/7/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/23/2017 APPLICANT
Assigned to Plan Check Engineer 8/24/2017 STEVEN KIM
Corrections Issued 8/29/2017 STEVEN KIM
Quality Review Completed 9/6/2017 FELIX FIGUEROA
Building Plans Picked Up 9/14/2017 APPLICANT
Green Plans Picked Up 11/1/2017 APPLICANT
Applicant returned to address corrections 1/12/2018 STEVEN KIM
Plan Check Approved 4/18/2018 STEVEN KIM
Issued 4/19/2018 LADBS
CofO in Progress 1/7/2021 ERNESTO CORRAL
Permit Finaled 1/7/2021 ERNESTO CORRAL
CofO Issued 1/7/2021 ERNESTO CORRAL
Permit Finaled 1/7/2021 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 9/8/2017 ADRIAN SANCHEZ
Encroachment in public way Cleared 9/8/2017 JAMES KHO
"Q" conditions Cleared 9/15/2017 TREVOR MARTIN
Eng Process Fee Ord 176,300 Cleared 9/15/2017 FATIMA GUERRA
Permit Cleared 9/15/2017 FATIMA GUERRA
Opn space landscape/Water mgmt Cleared 9/18/2017 TREVOR MARTIN
Hydrant and Access approval Cleared 9/28/2017 JOHN CONNEALLY
Sewer availability Cleared 9/28/2017 FATIMA GUERRA
Highway dedication Cleared 10/3/2017 RAVIL MANAPOV
Housing density bonus Cleared 1/12/2018 AGHAVNI SIMONYAN
Low Impact Development Cleared 3/29/2018 MATTHEW JIMENEZ
Roof/Waste drainage to street Cleared 3/29/2018 MICHAEL CASTILLO
Fire Marshall Fire Life Safety Cleared 4/11/2018 ANDREW KO
Building over 3-story or 36-ft Cleared 4/13/2018 CALOSHA APPROVED
Green Code Cleared 4/16/2018 RICHARD GARCIA
DAS Clearance Cleared 4/17/2018 WAI LAU
Work Adjacent to Public Way Cleared 4/18/2018 KAYLA PEJI

Contact Information

Architect Sun,, Peter M; Lic. No.: C33608       ,
Contractor Owner-Builder       ,
Engineer Ekwueme, Chukwuma Ganiru; Lic. No.: S4416 4551 GLENCOE AVE STE 350      MARINA DEL REY, CA 90292
Engineer Haro, Ruben Jr; Lic. No.: C72213 1554 CIPRES CT      CAMARILLO, CA 93010
Geologist Bovenizer, Ernest; Lic. No.: EG2515 7622 GODDARD AVENUE      LOS ANGELES, CA 90045

Inspector Information

LARRY ARNICK, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
ERNESTO CORRAL, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
JEFFREY FULTON, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL ESPINOZA, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 11/15/2018 Partial Inspection ERNESTO CORRAL
Pre-Inspection 11/15/2018 Approved ERNESTO CORRAL
Green Building Rough 11/26/2018 Not Ready for Inspection ERNESTO CORRAL
Piling/Pier/Caisson 11/26/2018 Corrections Issued ERNESTO CORRAL
Verify Sprinkler Sign Off 11/26/2018 Not Ready for Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 11/27/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 11/28/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 12/3/2018 Conditional Approval ERNESTO CORRAL
Piling/Pier/Caisson 12/3/2018 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 12/4/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 12/5/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 12/6/2018 No Access for Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 12/7/2018 No Access for Inspection JEFFREY FULTON
Deputy Reinf. Concrete 12/10/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 12/11/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 12/12/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 1/29/2019 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 1/29/2019 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 1/30/2019 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 1/30/2019 Partial Inspection ERNESTO CORRAL
Deputy Shotcrete 2/21/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 2/26/2019 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 2/27/2019 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 2/28/2019 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 3/1/2019 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 3/1/2019 Approved ERNESTO CORRAL
Deputy Reinf. Concrete 3/5/2019 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 3/5/2019 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 3/8/2019 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 3/8/2019 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 3/14/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 3/29/2019 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 4/11/2019 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 4/16/2019 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 4/16/2019 Partial Inspection ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 5/3/2019 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 5/6/2019 Conditional Approval ERNESTO CORRAL
Deputy Pre-Stress Concrete 7/16/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 7/16/2019 Conditional Approval ERNESTO CORRAL
Reinforced Masonry Frame 7/19/2019 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 7/22/2019 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 7/25/2019 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 9/18/2019 Partial Inspection ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 10/15/2019 Partial Inspection ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 11/14/2019 Approved ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 12/10/2019 Partial Inspection ERNESTO CORRAL
Green Building Rough 1/9/2020 Approved ERNESTO CORRAL
Verify Sprinkler Sign Off 1/9/2020 Approved ERNESTO CORRAL
Wood Frame 1/9/2020 Partial Inspection ERNESTO CORRAL
Wood Frame 1/13/2020 Partial Approval DANIEL COLLINS
Insulation 2/6/2020 Corrections Issued RAFAEL ESPINOZA
Wood Frame 2/10/2020 Partial Inspection ERNESTO CORRAL
Drywall Nailing 2/20/2020 Partial Inspection ERNESTO CORRAL
Wood Frame 2/27/2020 Partial Inspection ERNESTO CORRAL
T-Bar Ceiling 3/19/2020 Not Ready for Inspection JONATHAN QUACH
Drywall Nailing 3/26/2020 Partial Inspection ERNESTO CORRAL
Insulation 3/31/2020 Approved ERNESTO CORRAL
Drywall Nailing 4/6/2020 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 4/6/2020 Approved RAFAEL ESPINOZA
Drywall Nailing 4/9/2020 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 4/14/2020 Partial Inspection LESLIE TRUJILLO
Interior/Exterior Lathing 4/29/2020 Not Ready for Inspection JONATHAN QUACH
Interior/Exterior Lathing 5/1/2020 Approved TIMOTHY BUXTON
Pre-Inspection 8/11/2020 Partial Approval NICK DANERI
Pre-Inspection 8/13/2020 Partial Approval NICK DANERI
Special/Order Compliance 8/28/2020 Partial Approval NICK DANERI
Drywall Nailing 9/29/2020 Approved NICK DANERI
Final 9/29/2020 Corrections Issued NICK DANERI
Green Building Final 9/29/2020 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 9/29/2020 Approved NICK DANERI
Reinforced Masonry Frame 9/29/2020 Approved NICK DANERI
SGSOV-Seismic Gas S/O Valve 9/29/2020 SGSOV Not Ready NICK DANERI
Smoke Detectors 9/29/2020 Approved NICK DANERI
Structural Steel Frame 9/29/2020 Approved NICK DANERI
Wood Frame 9/29/2020 Approved NICK DANERI
Final 11/9/2020 Not Ready for Inspection RAFAEL ESPINOZA
Green Building Final 11/9/2020 Not Ready for Inspection RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 11/9/2020 SGSOV Not Ready RAFAEL ESPINOZA
Final 11/24/2020 Conditional Approval NICK DANERI
Green Building Final 11/24/2020 Approved NICK DANERI
SGSOV-Seismic Gas S/O Valve 11/24/2020 SGSOV Approved NICK DANERI