Piling/Pier/Caisson
|
7/30/2018
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
7/31/2018
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Piling/Pier/Caisson
|
8/2/2018
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
8/3/2018
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
9/13/2018
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Piling/Pier/Caisson
|
9/13/2018
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
9/17/2018
|
Corrections Issued
|
JOEL LAUNCHBAUGH
|
|
Footing/Foundation/Slab
|
9/19/2018
|
Partial Inspection
|
JOEL LAUNCHBAUGH
|
|
Excavation/Setback/Form/Re-Bar
|
9/24/2018
|
Partial Approval
|
JOEL LAUNCHBAUGH
|
|
Footing/Foundation/Slab
|
9/24/2018
|
Partial Approval
|
JOEL LAUNCHBAUGH
|
|
Pre-Inspection
|
10/11/2018
|
Partial Approval
|
JOEL LAUNCHBAUGH
|
|
Deputy Drilled-In Anchors
|
10/23/2018
|
Conditional Approval
|
JOEL LAUNCHBAUGH
|
|
Footing/Foundation/Slab
|
10/24/2018
|
Approved
|
JOEL LAUNCHBAUGH
|
|
BUILDING-Rough-Frame
|
11/27/2018
|
Partial Approval
|
JOEL LAUNCHBAUGH
|
|
PLUMBING-Rough
|
11/27/2018
|
Partial Approval
|
JOEL LAUNCHBAUGH
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/6/2018
|
No Access for Inspection
|
JOEL LAUNCHBAUGH
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/11/2018
|
Partial Approval
|
JOEL LAUNCHBAUGH
|
|
Special/Order Compliance
|
3/16/2019
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Special/Order Compliance
|
3/23/2019
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Special/Order Compliance
|
3/30/2019
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
4/2/2019
|
Corrections Issued
|
ANTHONY MCDOWALL
|
|
Pool Piping
|
4/2/2019
|
Corrections Issued
|
ANTHONY MCDOWALL
|
|
PLUMBING-Rough
|
4/5/2019
|
Corrections Issued
|
ANTHONY MCDOWALL
|
|
HVAC-Rough
|
4/8/2019
|
Corrections Issued
|
ANTHONY MCDOWALL
|
|
ELECTRICAL-Rough
|
4/9/2019
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/9/2019
|
Corrections Issued
|
ANTHONY MCDOWALL
|
|
BUILDING-Rough-Frame
|
4/12/2019
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/12/2019
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
Green Building Rough
|
4/12/2019
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
PLUMBING-Rough
|
4/12/2019
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
Structural Steel Frame
|
4/12/2019
|
Partial Approval
|
ANTHONY MCDOWALL
|
|
Verify Sprinkler Sign Off
|
4/12/2019
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
Wood Frame
|
4/12/2019
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
Special/Order Compliance
|
4/13/2019
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
4/15/2019
|
Approved
|
ANTHONY MCDOWALL
|
|
Rough-Elec/Plmb/HVAC
|
4/15/2019
|
Approved
|
ANTHONY MCDOWALL
|
|
BUILDING-Rough-Frame
|
4/18/2019
|
Corrections Issued
|
ANTHONY MCDOWALL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/18/2019
|
Partial Approval
|
ANTHONY MCDOWALL
|
|
Green Building Rough
|
4/18/2019
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
Verify Sprinkler Sign Off
|
4/18/2019
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
BUILDING-Rough-Frame
|
4/26/2019
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
Green Building Rough
|
4/26/2019
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
Masonry Wall/Backfill
|
4/26/2019
|
Partial Inspection
|
ANTHONY MCDOWALL
|
|
Verify Sprinkler Sign Off
|
4/26/2019
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
Special/Order Compliance
|
4/27/2019
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Pool Piping
|
5/1/2019
|
Partial Approval
|
ANTHONY MCDOWALL
|
|
Grounding or Bonding
|
5/8/2019
|
Partial Approval
|
ANTHONY MCDOWALL
|
|
Pool Piping
|
5/8/2019
|
Approved
|
ANTHONY MCDOWALL
|
|
Pre-Gunite
|
5/8/2019
|
Approved
|
ANTHONY MCDOWALL
|
|
Verify Sprinkler Sign Off
|
5/8/2019
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
BUILDING-Rough-Frame
|
6/17/2019
|
No Access for Inspection
|
ANTHONY MCDOWALL
|
|
Green Building Rough
|
6/17/2019
|
No Access for Inspection
|
ANTHONY MCDOWALL
|
|
Interior/Exterior Lathing
|
6/17/2019
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
Verify Sprinkler Sign Off
|
6/17/2019
|
No Access for Inspection
|
ANTHONY MCDOWALL
|
|
BUILDING-Rough-Frame
|
7/5/2019
|
Partial Approval
|
ANTHONY MCDOWALL
|
|
Green Building Rough
|
7/5/2019
|
Approved
|
ANTHONY MCDOWALL
|
|
Interior/Exterior Lathing
|
7/5/2019
|
Approved
|
ANTHONY MCDOWALL
|
|
Verify Sprinkler Sign Off
|
7/5/2019
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
Insulation
|
7/9/2019
|
Approved
|
ANTHONY MCDOWALL
|
|
Interior/Exterior Lathing
|
7/17/2019
|
Partial Approval
|
ANTHONY MCDOWALL
|
|
Drywall Nailing
|
8/2/2019
|
Approved
|
ANTHONY MCDOWALL
|
|
Interior/Exterior Lathing
|
9/10/2019
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Interior/Exterior Lathing
|
12/5/2019
|
Approved
|
ANTHONY MCDOWALL
|
|
ELECTRICAL-Final
|
3/31/2020
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Piling/Pier/Caisson
|
7/10/2020
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Piling/Pier/Caisson
|
7/15/2020
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Deputy Reinf. Concrete
|
7/20/2020
|
Conditional Approval
|
CARLOS MATAMOROS
|
|
Service/Power Release
|
7/24/2020
|
Approved
|
CARLOS MATAMOROS
|
|
Piling/Pier/Caisson
|
8/14/2020
|
Corrections Issued
|
CARLOS MATAMOROS
|
|
Piling/Pier/Caisson
|
8/18/2020
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
8/20/2020
|
Conditional Approval
|
CARLOS MATAMOROS
|
|
Piling/Pier/Caisson
|
8/21/2020
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Deck
|
9/10/2020
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
9/10/2020
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Deck
|
9/15/2020
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
9/15/2020
|
Corrections Issued
|
CARLOS MATAMOROS
|
|
Special/Order Compliance
|
9/19/2020
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Final
|
9/21/2020
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Final
|
9/21/2020
|
Corrections Issued
|
CARLOS MATAMOROS
|
|
HVAC-Final
|
9/21/2020
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
PLUMBING-Final
|
9/21/2020
|
Corrections Issued
|
CARLOS MATAMOROS
|
|
Deck
|
10/21/2020
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
10/21/2020
|
Corrections Issued
|
CARLOS MATAMOROS
|
|
Piling/Pier/Caisson
|
10/21/2020
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
10/23/2020
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Pre-Gunite
|
10/27/2020
|
Corrections Issued
|
CARLOS MATAMOROS
|
|
Pre-Gunite
|
11/2/2020
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Special/Order Compliance
|
11/7/2020
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Final
|
1/5/2021
|
Corrections Issued
|
CARLOS MATAMOROS
|
|
HVAC-Final
|
1/5/2021
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
PLUMBING-Final
|
1/5/2021
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
ELECTRICAL-Final
|
1/6/2021
|
Corrections Issued
|
CARLOS MATAMOROS
|
|
ELECTRICAL-Final
|
1/21/2021
|
Not Ready for Inspection
|
MATT KELLERMAN
|
|
Final
|
1/21/2021
|
Corrections Issued
|
CARLOS MATAMOROS
|
|
HVAC-Final
|
1/21/2021
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
PLUMBING-Final
|
1/21/2021
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
BUILDING-Rough-Frame
|
1/26/2021
|
Approved
|
CARLOS MATAMOROS
|
|
Final
|
1/26/2021
|
Corrections Issued
|
CARLOS MATAMOROS
|
|
Green Building Final
|
1/26/2021
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
SGSOV-Seismic Gas S/O Valve
|
1/26/2021
|
SGSOV Not Ready
|
CARLOS MATAMOROS
|
|
Smoke Detectors
|
1/26/2021
|
Approved
|
CARLOS MATAMOROS
|
|
Structural Steel Frame
|
1/26/2021
|
Approved
|
CARLOS MATAMOROS
|
|
Verify Sprinkler Sign Off
|
1/26/2021
|
Approved
|
CARLOS MATAMOROS
|
|
Final
|
1/27/2021
|
Corrections Issued
|
CARLOS MATAMOROS
|
|
Green Building Final
|
1/27/2021
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
SGSOV-Seismic Gas S/O Valve
|
1/27/2021
|
SGSOV Not Ready
|
CARLOS MATAMOROS
|
|
ELECTRICAL-Final
|
2/2/2021
|
Corrections Issued
|
CARLOS MATAMOROS
|
|
Gas Test
|
2/2/2021
|
Approved
|
CARLOS MATAMOROS
|
|
Green Building Final
|
2/2/2021
|
Corrections Issued
|
CARLOS MATAMOROS
|
|
HVAC-Final
|
2/2/2021
|
Corrections Issued
|
CARLOS MATAMOROS
|
|
PLUMBING-Final
|
2/2/2021
|
Corrections Issued
|
CARLOS MATAMOROS
|
|
ELECTRICAL-Final
|
2/9/2021
|
Approved
|
CARLOS MATAMOROS
|
|
HVAC-Final
|
2/9/2021
|
Approved
|
CARLOS MATAMOROS
|
|
Final
|
2/16/2021
|
Corrections Issued
|
CARLOS MATAMOROS
|
|
Green Building Final
|
2/16/2021
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
PLUMBING-Final
|
2/16/2021
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
SGSOV-Seismic Gas S/O Valve
|
2/16/2021
|
SGSOV Not Ready
|
CARLOS MATAMOROS
|
|
Sewer
|
2/17/2021
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Special/Order Compliance
|
2/20/2021
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
PLUMBING-Final
|
2/24/2021
|
Approved
|
CARLOS MATAMOROS
|
|
Sewer
|
2/24/2021
|
Approved
|
CARLOS MATAMOROS
|
|
Final
|
3/16/2021
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Green Building Final
|
3/16/2021
|
Approved
|
CARLOS MATAMOROS
|
|
SGSOV-Seismic Gas S/O Valve
|
3/16/2021
|
SGSOV Approved
|
CARLOS MATAMOROS
|
|
Final
|
3/24/2021
|
Corrections Issued
|
CARLOS MATAMOROS
|
|
Gas Test
|
3/24/2021
|
Not Ready for Inspection
|
MATT KELLERMAN
|
|
Final
|
3/26/2021
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Final
|
3/31/2021
|
Partial Approval
|
CARLOS MATAMOROS
|