Excavation/Setback/Form/Re-Bar
|
7/23/2018
|
Partial Inspection
|
TED RIES
|
|
Pre-Inspection
|
7/23/2018
|
Approved
|
TED RIES
|
|
Pre-Inspection
|
12/12/2018
|
Approved
|
TED RIES
|
|
Piling/Pier/Caisson
|
12/28/2018
|
Partial Approval
|
TED RIES
|
|
Footing/Foundation/Slab
|
5/9/2019
|
Partial Approval
|
TED RIES
|
|
METHANE-Barrier
|
5/9/2019
|
Partial Approval
|
TED RIES
|
|
METHANE-Subgrade
|
5/9/2019
|
Partial Approval
|
TED RIES
|
|
Deputy Reinf. Concrete
|
5/13/2019
|
Approved
|
TED RIES
|
|
Footing/Foundation/Slab
|
5/13/2019
|
Partial Approval
|
TED RIES
|
|
METHANE-Barrier
|
5/13/2019
|
Not Ready for Inspection
|
TED RIES
|
|
METHANE-Subgrade
|
5/13/2019
|
Not Ready for Inspection
|
TED RIES
|
|
Deputy Reinf. Concrete
|
5/14/2019
|
Approved
|
TED RIES
|
|
Deputy Reinf. Concrete
|
5/17/2019
|
Approved
|
TED RIES
|
|
Footing/Foundation/Slab
|
5/17/2019
|
Partial Approval
|
TED RIES
|
|
METHANE-Barrier
|
5/17/2019
|
Approved
|
TED RIES
|
|
METHANE-Subgrade
|
5/17/2019
|
Approved
|
TED RIES
|
|
Deputy Reinf. Concrete
|
5/24/2019
|
Approved
|
TED RIES
|
|
Footing/Foundation/Slab
|
5/24/2019
|
Partial Approval
|
TED RIES
|
|
Deputy Reinf. Concrete
|
5/29/2019
|
Approved
|
JEFF BYTHEWAY
|
|
Deputy Reinf. Concrete
|
5/30/2019
|
Approved
|
TED RIES
|
|
Deputy Reinf. Concrete
|
5/31/2019
|
Approved
|
TED RIES
|
|
Deputy Reinf. Concrete
|
6/3/2019
|
Approved
|
TED RIES
|
|
Deputy Reinf. Concrete
|
6/4/2019
|
Approved
|
TED RIES
|
|
Footing/Foundation/Slab
|
6/4/2019
|
Partial Approval
|
TED RIES
|
|
Deputy Reinf. Concrete
|
6/5/2019
|
Approved
|
TED RIES
|
|
Deputy Reinf. Concrete
|
6/6/2019
|
Approved
|
JEFF BYTHEWAY
|
|
Deputy Reinf. Concrete
|
6/7/2019
|
Partial Approval
|
JAMES POWERS
|
|
Footing/Foundation/Slab
|
6/7/2019
|
Partial Approval
|
JAMES POWERS
|
|
Green Building Rough
|
6/7/2019
|
Not Ready for Inspection
|
JAMES POWERS
|
|
METHANE-Rough
|
6/7/2019
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Reinforced Concrete Frame
|
6/7/2019
|
Partial Approval
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
6/7/2019
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
6/10/2019
|
Approved
|
TED RIES
|
|
Deputy Shotcrete
|
6/10/2019
|
Approved
|
TED RIES
|
|
Deputy Reinf. Masonry
|
6/11/2019
|
Approved
|
TED RIES
|
|
Deputy Shotcrete
|
6/11/2019
|
Approved
|
TED RIES
|
|
Footing/Foundation/Slab
|
6/11/2019
|
Partial Approval
|
TED RIES
|
|
Deputy Reinf. Masonry
|
6/12/2019
|
Approved
|
TED RIES
|
|
Deputy Shotcrete
|
6/12/2019
|
Approved
|
TED RIES
|
|
Deputy Reinf. Concrete
|
6/13/2019
|
Approved
|
TED RIES
|
|
Deputy Reinf. Masonry
|
6/13/2019
|
Approved
|
TED RIES
|
|
Green Building Rough
|
6/13/2019
|
Not Ready for Inspection
|
TED RIES
|
|
METHANE-Rough
|
6/13/2019
|
Approved
|
TED RIES
|
|
Reinforced Concrete Frame
|
6/13/2019
|
Partial Approval
|
TED RIES
|
|
Verify Sprinkler Sign Off
|
6/13/2019
|
Not Ready for Inspection
|
TED RIES
|
|
Deputy Shotcrete
|
6/14/2019
|
Approved
|
TED RIES
|
|
Deputy Reinf. Concrete
|
6/18/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
6/18/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Footing/Foundation/Slab
|
6/18/2019
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Concrete
|
6/20/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
6/20/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Green Building Rough
|
6/20/2019
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Reinforced Concrete Frame
|
6/20/2019
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Verify Sprinkler Sign Off
|
6/20/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Concrete
|
6/25/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
6/25/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Pre-Inspection
|
7/12/2019
|
Not Ready for Inspection
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Concrete
|
7/25/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Footing/Foundation/Slab
|
7/25/2019
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Concrete
|
8/28/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Excavation/Setback/Form/Re-Bar
|
8/28/2019
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Concrete
|
8/29/2019
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Excavation/Setback/Form/Re-Bar
|
8/30/2019
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Excavation/Setback/Form/Re-Bar
|
9/9/2019
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Concrete
|
9/11/2019
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Concrete
|
9/13/2019
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
9/16/2019
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
9/18/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Shotcrete
|
9/18/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Excavation/Setback/Form/Re-Bar
|
9/18/2019
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Concrete
|
9/19/2019
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
9/19/2019
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Shotcrete
|
9/19/2019
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Concrete
|
9/20/2019
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Shotcrete
|
9/20/2019
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
9/23/2019
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Concrete
|
9/24/2019
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
9/24/2019
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
9/25/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Excavation/Setback/Form/Re-Bar
|
9/25/2019
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
9/30/2019
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
10/1/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Excavation/Setback/Form/Re-Bar
|
10/1/2019
|
Not Ready for Inspection
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Concrete
|
10/2/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
10/2/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Pre-Inspection
|
10/2/2019
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
10/3/2019
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
10/4/2019
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Masonry Wall/Backfill
|
10/7/2019
|
Not Ready for Inspection
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
10/8/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Reinforced Masonry Frame
|
10/8/2019
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Green Building Rough
|
11/4/2019
|
Not Ready for Inspection
|
DANIEL MC AULIFFE
|
|
Reinforced Concrete Frame
|
11/4/2019
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Concrete
|
11/14/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Excavation/Setback/Form/Re-Bar
|
11/14/2019
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Reinforced Concrete Frame
|
11/14/2019
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Excavation/Setback/Form/Re-Bar
|
11/15/2019
|
Not Ready for Inspection
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Concrete
|
11/19/2019
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
11/20/2019
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Concrete
|
11/25/2019
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Excavation/Setback/Form/Re-Bar
|
11/26/2019
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Concrete
|
11/27/2019
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
12/3/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Masonry Wall/Backfill
|
12/3/2019
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
12/5/2019
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Pre-Inspection
|
12/9/2019
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Green Building Rough
|
12/12/2019
|
Not Ready for Inspection
|
DANIEL MC AULIFFE
|
|
Pre-Inspection
|
12/12/2019
|
Not Ready for Inspection
|
DANIEL MC AULIFFE
|
|
Wood Frame
|
12/12/2019
|
Not Ready for Inspection
|
DANIEL MC AULIFFE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/13/2019
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Deputy Steel/Welding
|
12/17/2019
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Steel/Welding
|
12/19/2019
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Wood Construction
|
12/19/2019
|
Approved
|
DANIEL MC AULIFFE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/19/2019
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Deputy Steel/Welding
|
12/20/2019
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/2/2020
|
Partial Inspection
|
DAVID BURKHEAD
|
|
Deputy Steel/Welding
|
1/3/2020
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/6/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/13/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Deputy Wood Construction
|
1/24/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/24/2020
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/27/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/28/2020
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/29/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Deputy Wood Construction
|
3/3/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/3/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Deputy Wood Construction
|
3/5/2020
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/6/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/6/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/25/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/14/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Insulation
|
4/14/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Deputy Wood Construction
|
4/20/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/20/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/21/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Deputy Wood Construction
|
4/23/2020
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Insulation
|
4/24/2020
|
Not Ready for Inspection
|
DANIEL MC AULIFFE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/27/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Insulation
|
4/27/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/28/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/29/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Insulation
|
4/29/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/4/2020
|
Not Ready for Inspection
|
DANIEL MC AULIFFE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/5/2020
|
Not Ready for Inspection
|
DANIEL MC AULIFFE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/6/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/8/2020
|
Not Ready for Inspection
|
DANIEL MC AULIFFE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/11/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/27/2020
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/29/2020
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Green Building Rough
|
6/4/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Insulation
|
6/4/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Wood Frame
|
6/4/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
6/18/2020
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
6/19/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Insulation
|
6/19/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
6/24/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
6/26/2020
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
6/29/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Masonry Wall/Backfill
|
6/29/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
6/30/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Drywall Nailing
|
6/30/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
7/1/2020
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Insulation
|
7/14/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Pre-Inspection
|
9/10/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Pre-Inspection
|
9/18/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Interior/Exterior Lathing
|
9/28/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Interior/Exterior Lathing
|
10/8/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Interior/Exterior Lathing
|
10/16/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/19/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Drywall Nailing
|
11/24/2020
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Light Gage Steel Frame
|
12/17/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Drywall Nailing
|
1/26/2021
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Deputy Drilled-In Anchors
|
4/6/2021
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
5/4/2021
|
Approved
|
DANIEL MC AULIFFE
|
|
Posting Pre-Inspection
|
5/4/2021
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Pre-Inspection
|
5/4/2021
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
5/5/2021
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
5/6/2021
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
5/7/2021
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
5/10/2021
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
5/12/2021
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
5/13/2021
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Masonry Wall/Backfill
|
5/13/2021
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
5/14/2021
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
5/17/2021
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Reinf. Masonry
|
5/26/2021
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Reinforced Concrete Frame
|
5/26/2021
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Masonry Wall/Backfill
|
7/13/2021
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Final
|
7/27/2021
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Footing/Foundation/Slab
|
7/27/2021
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Green Building Final
|
7/27/2021
|
Approved
|
DANIEL MC AULIFFE
|
|
Reinforced Concrete Frame
|
7/27/2021
|
Approved
|
DANIEL MC AULIFFE
|
|
SGSOV-Seismic Gas S/O Valve
|
7/27/2021
|
SGSOV Approved
|
DANIEL MC AULIFFE
|
|
Smoke Detectors
|
7/27/2021
|
Approved
|
DANIEL MC AULIFFE
|
|
Wood Frame
|
7/27/2021
|
Not Ready for Inspection
|
DANIEL MC AULIFFE
|
|
Interior/Exterior Lathing
|
8/31/2021
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Pre-Inspection
|
9/15/2021
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Footing/Foundation/Slab
|
9/20/2021
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Final
|
1/19/2022
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Footing/Foundation/Slab
|
1/19/2022
|
Approved
|
DANIEL MC AULIFFE
|
|
Pre-Inspection
|
1/19/2022
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Wood Frame
|
1/19/2022
|
Approved
|
DANIEL MC AULIFFE
|
|
Pre-Inspection
|
3/4/2022
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Final
|
4/15/2022
|
Not Ready for Inspection
|
DANIEL MC AULIFFE
|
|
Special/Order Compliance
|
4/15/2022
|
Not Ready for Inspection
|
DANIEL MC AULIFFE
|
|
Posting Pre-Inspection
|
4/18/2022
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
T-Bar Ceiling
|
4/20/2022
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Final
|
5/4/2022
|
Partial Inspection
|
DAVID BURKHEAD
|
|
Special/Order Compliance
|
5/5/2022
|
Approved
|
DAVID BURKHEAD
|
|
Final
|
5/6/2022
|
OK to Issue CofO
|
DAVID BURKHEAD
|