1614 N TOWER GROVE DR 90210

Certificate Information: 1614 N TOWER GROVE DR 90210

Application / Permit
17010-30000-02230
Plan Check / Job No.
B17WL03101
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Remodel and addition to SFD with deck
Permit Issued
Issued on 9/7/2017
Issuing Office
West Los Angeles
Current Status
Issued on 9/7/2017
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/7/2017 APPLICANT
Assigned to Plan Check Engineer 6/15/2017 SERGIO SILVA
Corrections Issued 6/22/2017 SHANGQIN XIE
Quality Review Completed 6/23/2017 STEVEN KIM
Building Plans Picked Up 6/23/2017 APPLICANT
Green Plans Picked Up 6/23/2017 APPLICANT
Applicant returned to address corrections 7/24/2017 SHANGQIN XIE
Applicant returned to address corrections 8/7/2017 SHANGQIN XIE
Applicant returned to address corrections 9/1/2017 SHANGQIN XIE
Plan Check Approved 9/7/2017 SHANGQIN XIE
Issued 9/7/2017 LADBS

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 7/13/2017 MARKOS PEREZ-BRAN
BHO/Hillside ordinance Cleared 7/13/2017 MARKOS PEREZ-BRAN
BHO/Hillside ordinance Cleared 7/13/2017 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 7/13/2017 MARKOS PEREZ-BRAN
Low Impact Development Cleared 8/21/2017 RYAN HUDSON
Roof/Waste drainage to street Cleared 8/21/2017 RAVIL MANAPOV
Green Code Cleared 8/22/2017 RICHARD GARCIA
CPC Cleared 9/7/2017 JOHN DACEY
ZA Case Cleared 9/7/2017 JOHN DACEY
ZA Case Cleared 9/7/2017 JOHN DACEY
ZA Case Cleared 9/7/2017 JOHN DACEY

Contact Information

Architect Bangham, Robert C; Lic. No.: C26009 833 PALMS BLVD      VENICE, CA 90291
Contractor Owner-Builder       ,
Engineer Daugherty, Daniel Thomas; Lic. No.: C76588 31129 VIA COLINAS STE 707      WESTLAKE VILLAGE, CA 91362
Engineer Mirzadeh, Amir; Lic. No.: C58119 P O BOX 572110      TARZANA, CA 91357
Engineer Uhles, Scott Delane; Lic. No.: C72391 2909 ARIZONA AVE 5      SANTA MONICA, CA 90404

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/15/2019 Partial Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 4/18/2019 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 4/19/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 5/1/2019 Conditional Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 5/2/2019 Conditional Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 5/3/2019 Conditional Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 5/6/2019 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 5/8/2019 Conditional Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 6/11/2019 Conditional Approval CARLOS MATAMOROS
Deputy Drilled-In Anchors 9/6/2019 No Access for Inspection DAVID FEILER
Footing/Foundation/Slab 9/9/2019 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 9/10/2019 Conditional Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 9/11/2019 Conditional Approval CARLOS MATAMOROS
PLUMBING-Rough 9/13/2019 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Rough 10/7/2019 Partial Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 11/18/2019 Corrections Issued MATT KELLERMAN
Excavation/Setback/Form/Re-Bar 11/20/2019 Not Ready for Inspection CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 12/2/2019 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 12/2/2019 Corrections Issued CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 12/3/2019 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 12/4/2019 Partial Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 12/5/2019 Partial Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 3/18/2020 Partial Approval ANTHONY MCDOWALL
Footing/Foundation/Slab 3/18/2020 Partial Approval ANTHONY MCDOWALL
Excavation/Setback/Form/Re-Bar 3/20/2020 Partial Approval ANTHONY MCDOWALL
Floor/Roof Diaphrgm/Shear Wall 4/23/2020 Partial Approval ANTHONY MCDOWALL
Green Building Rough 4/23/2020 Not Ready for Inspection ANTHONY MCDOWALL
Floor/Roof Diaphrgm/Shear Wall 5/13/2020 Partial Approval ANTHONY MCDOWALL
Deputy Drilled-In Anchors 5/21/2020 Conditional Approval ANTHONY MCDOWALL
Floor/Roof Diaphrgm/Shear Wall 6/25/2020 Not Ready for Inspection ANTHONY MCDOWALL
Floor/Roof Diaphrgm/Shear Wall 7/6/2020 Corrections Issued ANTHONY MCDOWALL
Floor/Roof Diaphrgm/Shear Wall 7/15/2020 Not Ready for Inspection ANTHONY MCDOWALL
Green Building Rough 7/15/2020 Not Ready for Inspection ANTHONY MCDOWALL
Floor/Roof Diaphrgm/Shear Wall 7/20/2020 Partial Approval ANTHONY MCDOWALL
ELECTRICAL-Rough 7/21/2020 Partial Approval ANTHONY MCDOWALL
Floor/Roof Diaphrgm/Shear Wall 7/31/2020 Partial Approval ANTHONY MCDOWALL
Green Building Rough 7/31/2020 Not Ready for Inspection ANTHONY MCDOWALL
HVAC-Rough 8/6/2020 Partial Approval ANTHONY MCDOWALL
PLUMBING-Rough 8/11/2020 Approved ANTHONY MCDOWALL
Special/Order Compliance 9/4/2020 Corrections Issued ANTHONY MCDOWALL
ELECTRICAL-Rough 10/15/2020 Approved ANTHONY MCDOWALL
HVAC-Rough 10/16/2020 Approved ANTHONY MCDOWALL
Floor/Roof Diaphrgm/Shear Wall 10/19/2020 Approved ANTHONY MCDOWALL
Green Building Rough 10/19/2020 Not Ready for Inspection ANTHONY MCDOWALL
BUILDING-Rough-Frame 10/23/2020 Partial Approval ANTHONY MCDOWALL
Green Building Rough 10/23/2020 Approved ANTHONY MCDOWALL
Interior/Exterior Lathing 11/6/2020 Not Ready for Inspection JOHNNY MIRANDA
BUILDING-Rough-Frame 11/9/2020 Approved ANTHONY MCDOWALL
Insulation 11/16/2020 Approved ANTHONY MCDOWALL
Drywall Nailing 11/25/2020 Approved ANTHONY MCDOWALL
Interior/Exterior Lathing 12/1/2020 Partial Approval ANTHONY MCDOWALL
Shower Pan 12/1/2020 Approved ANTHONY MCDOWALL
Interior/Exterior Lathing 12/22/2020 Approved KEVIN SARGSYAN
Final 4/29/2021 Corrections Issued ANTHONY MCDOWALL
Footing/Foundation/Slab 4/29/2021 Approved ANTHONY MCDOWALL
Green Building Final 4/29/2021 Not Ready for Inspection ANTHONY MCDOWALL
SGSOV-Seismic Gas S/O Valve 4/29/2021 SGSOV Not Ready ANTHONY MCDOWALL
Smoke Detectors 4/29/2021 Not Ready for Inspection ANTHONY MCDOWALL
Final 5/18/2021 Not Ready for Inspection ANTHONY MCDOWALL
Green Building Final 5/18/2021 Not Ready for Inspection ANTHONY MCDOWALL
SGSOV-Seismic Gas S/O Valve 5/18/2021 SGSOV Not Ready ANTHONY MCDOWALL
Smoke Detectors 5/18/2021 Not Ready for Inspection ANTHONY MCDOWALL
ELECTRICAL-Final 7/28/2021 Corrections Issued ANTHONY MCDOWALL
HVAC-Final 7/28/2021 Corrections Issued ANTHONY MCDOWALL
PLUMBING-Final 7/28/2021 Corrections Issued ANTHONY MCDOWALL
Gas Test 8/6/2021 Approved JUAN VALENZUELA
ELECTRICAL-Final 8/11/2021 Approved ANTHONY MCDOWALL
HVAC-Final 8/11/2021 Not Ready for Inspection ANTHONY MCDOWALL
PLUMBING-Final 8/11/2021 Approved ANTHONY MCDOWALL
HVAC-Final 8/13/2021 Not Ready for Inspection ANTHONY MCDOWALL
HVAC-Final 7/11/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
HVAC-Final 7/13/2022 Approved MICHAEL PELHAM
Final 8/9/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Green Building Final 8/9/2022 Approved GERMAN RODRIGUEZ MENDOZA
SGSOV-Seismic Gas S/O Valve 8/9/2022 SGSOV Approved GERMAN RODRIGUEZ MENDOZA
Smoke Detectors 8/9/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA