2208 S DUXBURY CIR 90034

Certificate Information: 2208 S DUXBURY CIR 90034

Application / Permit
17010-30000-00838
Plan Check / Job No.
B17WL01068
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE & HABITABLE BASEMENT.
Permit Issued
Issued on 3/23/2018
Issuing Office
West Los Angeles
Current Status
CofO Issued on 3/4/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/2/2017 APPLICANT
Assigned to Plan Check Engineer 4/6/2017 ERWIN PASCUA
Corrections Issued 4/18/2017 ERWIN PASCUA
Quality Review Completed 4/27/2017 STEVEN KIM
Building Plans Picked Up 5/8/2017 APPLICANT
Green Plans Picked Up 5/8/2017 APPLICANT
Applicant returned to address corrections 1/19/2018 ERWIN PASCUA
Applicant returned to address corrections 1/26/2018 ERWIN PASCUA
Plan Check Approved 3/23/2018 ERWIN PASCUA
Plan Check Approved 3/23/2018 ERWIN PASCUA
Plan Check Approved 3/23/2018 ERWIN PASCUA
Issued 3/23/2018 LADBS
CofO in Progress 1/26/2021 KEVIN SARGSYAN
Permit Finaled 3/4/2021 KENNETH NAGLE
CofO Issued 3/4/2021 KENNETH NAGLE
Permit Finaled 3/4/2021 KENNETH NAGLE

Permit Application Clearance Information

Address approval Cleared 10/27/2017 JAMES MORALEZ
CPC Cleared 10/27/2017 EDBER MACEDO
CPC Cleared 10/27/2017 EDBER MACEDO
Eng Process Fee Ord 176,300 Cleared 10/27/2017 JAMES MORALEZ
Permit Cleared 10/27/2017 JAMES MORALEZ
Hydrant and Access approval Cleared 12/22/2017 VIDAL GARCIA
Sewer availability Cleared 12/22/2017 FATIMA GUERRA
Low Impact Development Cleared 1/19/2018 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 1/19/2018 ADRIAN SANCHEZ
Excavation more than 5-ft deep Cleared 1/26/2018 CALOSHA APPROVED
Green Code Cleared 2/5/2018 RICHARD GARCIA
GPI Written Notices Cleared 3/23/2018 ERWIN PASCUA
Grading Pre-Inspection Cleared 3/23/2018 ERWIN PASCUA

Contact Information

Architect Langer-Voss, Naomi; Lic. No.: C32512 9305 DUXBURY ROAD      LOS ANGELES, CA 90034
Contractor Plax Inc; Lic. No.: 682281-B 2048 MAYVIEW DRIVE      LOS ANGELES, CA 90027
Engineer Lotfi, Fariborz Frank; Lic. No.: C49359 1547 PALISADES DR      PACIFIC PALISADES, CA 90272
Engineer Mahn, Jonathan Edward; Lic. No.: C60293 12848 FOOTHILL BLVD      SYLMAR, CA 91381
Engineer Nester, Melvin Russell Jr; Lic. No.: C26324 2902 TYLER CT      SIMI VALLEY, CA 93063

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/5/2018 Approved DAVID HEINE
Deputy Grading 5/9/2018 Partial Approval DAVID HEINE
PLUMBING-Rough 5/29/2018 Partial Approval DAVID HEINE
Underground Mechanical 5/29/2018 Partial Approval DAVID HEINE
Deputy Methane Barrier 6/11/2018 Partial Approval DAVID HEINE
Deputy Methane Barrier 6/12/2018 No Access for Inspection DAVID HEINE
Footing/Foundation/Slab 6/21/2018 Partial Approval DAVID HEINE
METHANE-Barrier 6/21/2018 Not Ready for Inspection DAVID HEINE
METHANE-Subgrade 6/21/2018 Not Ready for Inspection DAVID HEINE
Excavation/Setback/Form/Re-Bar 7/20/2018 Partial Approval DAVID HEINE
Deputy Shotcrete 7/23/2018 Partial Approval DAVID HEINE
Reinforced Concrete Frame 7/23/2018 Partial Approval DAVID HEINE
METHANE-Subgrade 8/15/2018 Approved DAVID HEINE
Deputy Methane Barrier 8/17/2018 Partial Approval DAVID HEINE
Deputy Methane Barrier 8/20/2018 Partial Approval DAVID HEINE
Excavation/Setback/Form/Re-Bar 8/23/2018 Partial Approval DAVID HEINE
METHANE-Barrier 8/23/2018 Approved DAVID HEINE
Deputy Steel/Welding 8/31/2018 Partial Approval DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 10/1/2018 Partial Approval DAVID HEINE
Footing/Foundation/Slab 10/22/2018 Approved DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 12/3/2018 Partial Approval DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 3/1/2019 Approved RONALD WEBER
PLUMBING-Rough 4/1/2019 Approved RONALD WEBER
Sewer 4/16/2019 Approved RONALD WEBER
Excavation/Setback/Form/Re-Bar 9/4/2019 Approved RONALD WEBER
Reinforced Concrete Frame 9/12/2019 Approved RONALD WEBER
Deputy Reinf. Concrete 9/16/2019 Conditional Approval RONALD WEBER
METHANE-Rough 9/23/2019 Approved RONALD WEBER
Footing/Foundation/Slab 9/25/2019 Partial Approval EVAN COOPER
Deputy Reinf. Concrete 10/18/2019 Approved RONALD WEBER
Footing/Foundation/Slab 10/18/2019 Partial Approval RONALD WEBER
BUILDING-Rough-Frame 12/10/2019 Not Ready for Inspection RONALD WEBER
Floor/Roof Diaphrgm/Shear Wall 12/10/2019 Approved RONALD WEBER
Green Building Rough 12/10/2019 Approved RONALD WEBER
HVAC-Rough 12/10/2019 Approved RONALD WEBER
Deputy Wood Construction 12/16/2019 Conditional Approval RONALD WEBER
BUILDING-Rough-Frame 1/7/2020 Approved RONALD WEBER
ELECTRICAL-Rough 1/7/2020 Approved RONALD WEBER
Interior/Exterior Lathing 1/7/2020 Approved RONALD WEBER
Shower Pan 1/7/2020 Approved RONALD WEBER
Insulation 1/27/2020 Approved RONALD WEBER
Drywall Nailing 2/10/2020 Approved RONALD WEBER
Interior/Exterior Lathing 4/1/2020 Partial Approval CARLOS MATAMOROS
Interior/Exterior Lathing 4/9/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
Special/Order Compliance 9/3/2020 Corrections Issued KEVIN SARGSYAN
Special/Order Compliance 9/8/2020 Approved KEVIN SARGSYAN
Gas Test 10/21/2020 Approved KEVIN SARGSYAN
PLUMBING-Final 11/23/2020 Corrections Issued KEVIN SARGSYAN
PLUMBING-Final 11/30/2020 Not Ready for Inspection KENNETH NAGLE
ELECTRICAL-Final 12/22/2020 Corrections Issued KEVIN SARGSYAN
HVAC-Final 12/22/2020 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Final 12/28/2020 Not Ready for Inspection KEVIN SARGSYAN
HVAC-Final 12/28/2020 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Final 12/30/2020 Corrections Issued KEVIN SARGSYAN
HVAC-Final 12/30/2020 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Final 1/4/2021 Approved KEVIN SARGSYAN
HVAC-Final 1/4/2021 Approved KEVIN SARGSYAN
Service/Power Release 1/4/2021 Approved KEVIN SARGSYAN
PLUMBING-Final 1/15/2021 Approved KEVIN SARGSYAN
Final 1/21/2021 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 1/21/2021 Approved KEVIN SARGSYAN
Green Building Final 1/21/2021 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 1/21/2021 SGSOV Approved KEVIN SARGSYAN
Smoke Detectors 1/21/2021 Approved KEVIN SARGSYAN
Final 1/26/2021 OK to Issue CofO KEVIN SARGSYAN
Special/Order Compliance 2/11/2021 Corrections Issued KENNETH NAGLE
Special/Order Compliance 2/11/2021 Partial Inspection KEVIN SARGSYAN
Special/Order Compliance 2/22/2021 Partial Inspection KEVIN SARGSYAN