2332 W BAXTER ST 90039
Certificate Information: 2332 W BAXTER ST 90039
- Application / Permit
- 17010-30000-00833
- Plan Check / Job No.
- B17WL01063
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED 3-CAR GARAGE *** 1 of 3 ***
- Permit Issued
- Issued on 10/20/2017
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/2/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 3/16/2017 | ERWIN PASCUA |
| Corrections Issued | 3/20/2017 | ERWIN PASCUA |
| Quality Review Completed | 3/20/2017 | STEVEN KIM |
| Building Plans Picked Up | 3/20/2017 | APPLICANT |
| Green Plans Picked Up | 3/28/2017 | APPLICANT |
| Applicant returned to address corrections | 8/25/2017 | ERWIN PASCUA |
| Applicant returned to address corrections | 9/13/2017 | ERWIN PASCUA |
| Plan Check Approved | 10/13/2017 | ERWIN PASCUA |
| Issued | 10/20/2017 | LADBS |
| CofO in Progress | 6/1/2023 | STUART CHAPMAN |
| Permit Finaled | 6/27/2023 | DEROLD HAUFF |
| CofO Issued | 6/27/2023 | DEROLD HAUFF |
| Permit Finaled | 6/27/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/20/2017 | MAHELET GEBEYHU |
| BHO/Hillside ordinance | Cleared | 3/20/2017 | MAHELET GEBEYHU |
| BHO/Hillside ordinance | Cleared | 3/20/2017 | MAHELET GEBEYHU |
| BHO/Hillside ordinance | Cleared | 3/20/2017 | MAHELET GEBEYHU |
| Eng Process Fee Ord 176,300 | Cleared | 3/20/2017 | MAHELET GEBEYHU |
| Roof/Waste drainage to street | Cleared | 3/20/2017 | MAHELET GEBEYHU |
| Sewer availability | Cleared | 3/20/2017 | MAHELET GEBEYHU |
| Permit | Cleared | 9/29/2017 | NAZILA NOORIFAR |
| Hydrant and Access approval | Cleared | 10/4/2017 | ROBERT DUFF |
| Landscape for retaining wall | Cleared | 10/10/2017 | IVORY CHAMBESHI |
| Low Impact Development | Cleared | 10/10/2017 | MITESH PATEL |
| Excavation more than 5-ft deep | Cleared | 10/13/2017 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 10/13/2017 | ERWIN PASCUA |
| Grading Pre-Inspection | Cleared | 10/13/2017 | ERWIN PASCUA |
| Green Code | Cleared | 10/13/2017 | BRYAN MEYER |
Contact Information
| Architect | Ehrlich, Steven David; Lic. No.: C10142 | 10865 WASHINGTON BLVD CULVER CITY, CA 90232 |
| Contractor | D T K Builders Inc; Lic. No.: 813974-B | 2927 GILROY STREET LOS ANGELES, CA 90039 |
| Engineer | Lau, David Harkwong; Lic. No.: C34961 | 12467 W WASHINGTON BLVD LOS ANGELES, CA 90066 |
| Engineer | Liu, Haiyan; Lic. No.: C81463 | 1566 KINGS ROAD PALMDALE, CA 93551 |
| Engineer | Tran, Quang Tai; Lic. No.: C70929 | 3889 FOUNTAIN ST CAMARILLO, CA 93012 |
| Geologist | Swiatek, Mark A; Lic. No.: EG1781 | 24203 VALLEY ST NEWHALL, CA 91321 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/3/2018 | Partial Approval | DAVID CHAN |
| Masonry Wall/Backfill | 10/5/2018 | Partial Approval | DAVID CHAN |
| Sewer | 10/5/2018 | Partial Approval | DAVID CHAN |
| Deputy Reinf. Concrete | 12/21/2018 | Approved | DANNY TOLENTINO |
| Excavation/Setback/Form/Re-Bar | 4/9/2019 | Partial Approval | DAVID CHAN |
| Deputy Reinf. Masonry | 4/24/2019 | Conditional Approval | DAVID CHAN |
| Excavation/Setback/Form/Re-Bar | 4/25/2019 | Partial Approval | DAVID CHAN |
| Deputy Reinf. Masonry | 5/1/2019 | Conditional Approval | DAVID CHAN |
| Reinforced Masonry Frame | 5/8/2019 | Partial Approval | DAVID CHAN |
| Deputy Reinf. Masonry | 5/15/2019 | Conditional Approval | DAVID CHAN |
| Deputy Reinf. Masonry | 5/23/2019 | Conditional Approval | DAVID CHAN |
| Reinforced Masonry Frame | 5/28/2019 | Partial Approval | DAVID CHAN |
| Deputy Reinf. Masonry | 5/29/2019 | Conditional Approval | DAVID CHAN |
| Underground Mechanical | 6/28/2019 | Partial Approval | DAVID CHAN |
| Deputy Steel/Welding | 9/9/2019 | No Access for Inspection | DAVID CHAN |
| Deputy Steel/Welding | 10/7/2019 | Conditional Approval | DAVID CHAN |
| Deputy Steel/Welding | 10/15/2019 | Conditional Approval | DAVID CHAN |
| Structural Steel Frame | 11/4/2019 | Approved | DAVID CHAN |
| Deputy Drilled-In Anchors | 12/9/2019 | Conditional Approval | AJA COLLAY |
| Deputy Steel/Welding | 12/9/2019 | Conditional Approval | AJA COLLAY |
| Deputy Reinf. Concrete | 1/10/2020 | Conditional Approval | AJA COLLAY |
| BUILDING-Rough-Frame | 2/3/2020 | Not Ready for Inspection | AJA COLLAY |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2020 | Partial Approval | AJA COLLAY |
| Green Building Rough | 2/3/2020 | Not Ready for Inspection | AJA COLLAY |
| Verify Sprinkler Sign Off | 2/3/2020 | Not Ready for Inspection | AJA COLLAY |
| Underground Mechanical | 3/9/2020 | Partial Approval | DANNY TOLENTINO |
| Underground Mechanical | 3/24/2020 | Partial Approval | HAMIK HARTOUNIAN |
| Underground Mechanical | 4/14/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 4/20/2020 | Conditional Approval | STUART CHAPMAN |
| Deputy Drilled-In Anchors | 4/22/2020 | Conditional Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 4/28/2020 | No Access for Inspection | SCOTT FINNILA |
| Underground Mechanical | 4/28/2020 | No Access for Inspection | SCOTT FINNILA |
| Footing/Foundation/Slab | 4/29/2020 | Partial Approval | SCOTT FINNILA |
| HVAC-Rough | 4/29/2020 | Partial Approval | SCOTT FINNILA |
| Masonry Wall/Backfill | 4/29/2020 | Partial Approval | SCOTT FINNILA |
| Deputy Drilled-In Anchors | 6/9/2020 | Conditional Approval | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 6/12/2020 | Partial Approval | MATTHEW NUCKOLLS |
| Footing/Foundation/Slab | 6/29/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| Underground Mechanical | 7/1/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| Underground Mechanical | 10/6/2020 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Rough | 11/6/2020 | No Access for Inspection | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 12/9/2020 | Approved | SCOTT FINNILA |
| ELECTRICAL-Rough | 3/31/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2021 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 4/5/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| HVAC-Final | 4/26/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| HVAC-Rough | 4/26/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 4/27/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 4/27/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 5/6/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Green Building Rough | 5/6/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Verify Sprinkler Sign Off | 5/6/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 5/11/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| HVAC-Rough | 5/11/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Shower Pan | 5/11/2021 | Approved | KATHRYN BUTTERWORTH |
| Wood Frame | 5/11/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 6/22/2021 | Approved | SCOTT FINNILA |
| BUILDING-Rough-Frame | 6/28/2021 | Not Ready for Inspection | RUBEN SALAS |
| Green Building Rough | 6/28/2021 | Not Ready for Inspection | RUBEN SALAS |
| HVAC-Rough | 6/28/2021 | Approved | RUBEN SALAS |
| Verify Sprinkler Sign Off | 6/28/2021 | Not Ready for Inspection | RUBEN SALAS |
| BUILDING-Rough-Frame | 7/6/2021 | Corrections Issued | SCOTT FINNILA |
| Green Building Rough | 7/6/2021 | Approved | SCOTT FINNILA |
| Insulation | 8/11/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Wood Frame | 8/11/2021 | Partial Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 9/15/2021 | Corrections Issued | THOMAS LOGRASSO |
| Insulation | 9/15/2021 | Conditional Approval | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 9/15/2021 | Conditional Approval | THOMAS LOGRASSO |
| Special/Order Compliance | 9/15/2021 | Approved | RUBEN SALAS |
| Drywall Nailing | 10/25/2021 | Conditional Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 11/3/2021 | Approved | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 11/3/2021 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 12/8/2021 | Partial Approval | THOMAS LOGRASSO |
| Shower Pan | 12/28/2021 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 1/13/2022 | Approved | THOMAS LOGRASSO |
| Gas Test | 6/9/2022 | Partial Inspection | THOMAS LOGRASSO |
| Gas Test | 9/20/2022 | Approved | THOMAS LOGRASSO |
| Smoke Detectors | 9/20/2022 | Corrections Issued | THOMAS LOGRASSO |
| ELECTRICAL-Final | 9/27/2022 | Partial Approval | THOMAS LOGRASSO |
| Smoke Detectors | 9/27/2022 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Final | 10/4/2022 | Corrections Issued | THOMAS LOGRASSO |
| HVAC-Final | 10/4/2022 | Corrections Issued | THOMAS LOGRASSO |
| Service/Power Release | 10/4/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Final | 10/6/2022 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Final | 10/20/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| HVAC-Final | 10/20/2022 | Approved | THOMAS LOGRASSO |
| Service/Power Release | 10/20/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Final | 11/10/2022 | Partial Approval | THOMAS LOGRASSO |
| Service/Power Release | 11/10/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Final | 12/2/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Drywall Nailing | 4/12/2023 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Final | 4/12/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 4/12/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 4/12/2023 | Approved | THOMAS LOGRASSO |
| Green Building Final | 4/12/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| HVAC-Final | 4/12/2023 | Approved | THOMAS LOGRASSO |
| Reinforced Masonry Frame | 4/12/2023 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 4/12/2023 | SGSOV Approved | THOMAS LOGRASSO |
| Service/Power Release | 4/12/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Final | 5/17/2023 | Approved | STUART CHAPMAN |
| Final | 5/17/2023 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 5/17/2023 | Approved | STUART CHAPMAN |
| Service/Power Release | 5/17/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 5/31/2023 | OK to Issue CofO | STUART CHAPMAN |
| Service/Power Release | 5/31/2023 | Approved | STUART CHAPMAN |