1336 E APPLETON WAY 90291

Certificate Information: 1336 E APPLETON WAY 90291

Application / Permit
17010-30000-00722
Plan Check / Job No.
B17WL00955
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE, ATTACHED RECREATION ROOM AND BASEMENT.
Permit Issued
Issued on 2/23/2018
Issuing Office
West Los Angeles
Current Status
CofO Issued on 11/17/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/24/2017 APPLICANT
Assigned to Plan Check Engineer 3/9/2017 ERWIN PASCUA
Corrections Issued 3/14/2017 ERWIN PASCUA
Quality Review Completed 3/17/2017 STEVEN KIM
Building Plans Picked Up 4/20/2017 APPLICANT
Green Plans Picked Up 10/31/2017 APPLICANT
Applicant returned to address corrections 12/20/2017 ERWIN PASCUA
Applicant returned to address corrections 2/8/2018 ERWIN PASCUA
Plan Check Approved 2/23/2018 ERWIN PASCUA
No Progress 2/23/2018 ERWIN PASCUA
Plan Check Approved 2/23/2018 ERWIN PASCUA
Issued 2/23/2018 LADBS
CofO in Progress 11/1/2021 DAVID FEILER
Permit Finaled 11/17/2021 DANIEL ORRANTE
CofO Issued 11/17/2021 DANIEL ORRANTE
Permit Finaled 11/17/2021 DANIEL ORRANTE

Permit Application Clearance Information

Hydrant and Access approval Cleared 8/22/2017 JOHN CONNEALLY
Address approval Cleared 8/23/2017 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 8/23/2017 CELINA MORENO
Permit Cleared 8/23/2017 CELINA MORENO
Low Impact Development Cleared 10/10/2017 MITESH PATEL
Roof/Waste drainage to street Cleared 10/10/2017 RAVIL MANAPOV
Sewer availability Cleared 12/1/2017 NAZILA NOORIFAR
Excavation more than 5-ft deep Cleared 2/8/2018 CALOSHA APPROVED
GPI Written Notices Cleared 2/8/2018 ERWIN PASCUA
Grading Pre-Inspection Cleared 2/8/2018 ERWIN PASCUA
Green Code Cleared 2/16/2018 ERWIN PASCUA

Contact Information

Architect Holz, Michael B; Lic. No.: C28082 12548 EVERGLADE STREET      LOS ANGELES, CA 90066
Contractor Owner-Builder       ,
Engineer De, Leon Cynthia Aguilar; Lic. No.: C31604 8061 SAN MATEO CIR      BUENA PARK, CA 90620
Engineer Mercado, Lizandro; Lic. No.: S4331 25583 AVENUE STANFORD      VALENCIA, CA 91355
Engineer Salehipour, Sassan A; Lic. No.: GE2579 1290 N LAKE AVENUE #204      PASADENA, CA 91104
Engineer Salehipour, Sassan Abolghasem; Lic. No.: C44172 1290 NORTH LAKE AVENUE STE 204      PASADENA, CA 91104

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/21/2018 Partial Approval THOMAS FINNILA
Underground Mechanical 8/21/2018 Partial Approval THOMAS FINNILA
Footing/Foundation/Slab 9/14/2018 Partial Approval THOMAS FINNILA
Underground Mechanical 9/14/2018 Partial Approval THOMAS FINNILA
Footing/Foundation/Slab 9/25/2018 Partial Approval CRAIG DAVIS
Footing/Foundation/Slab 10/16/2018 Conditional Approval THOMAS FINNILA
Footing/Foundation/Slab 4/25/2019 Partial Approval DAVID HEINE
Excavation/Setback/Form/Re-Bar 4/26/2019 Partial Approval DAVID HEINE
Deputy Drilled-In Anchors 5/3/2019 Approved ROBERT SHELLY
Footing/Foundation/Slab 5/17/2019 Corrections Issued KENNETH NAGLE
Footing/Foundation/Slab 6/5/2019 Partial Approval CRAIG DAVIS
Deputy Reinf. Concrete 6/6/2019 Conditional Approval CRAIG DAVIS
BUILDING-Rough-Frame 7/12/2019 Partial Approval DAVID HEINE
Wood Frame 7/26/2019 Partial Approval DAVID HEINE
Footing/Foundation/Slab 8/13/2019 Partial Approval DAVID HEINE
BUILDING-Rough-Frame 9/11/2019 Partial Approval DAVID HEINE
Green Building Rough 9/11/2019 Not Ready for Inspection DAVID HEINE
Verify Sprinkler Sign Off 9/11/2019 Not Ready for Inspection DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 10/22/2019 Partial Approval DAVID HEINE
Wood Frame 4/29/2020 Corrections Issued DAVID HEINE
Deputy Wood Construction 5/7/2020 Partial Approval DAVID HEINE
Wood Frame 5/18/2020 Partial Approval DAVID HEINE
ELECTRICAL-Rough 9/3/2020 Approved DAVID HEINE
HVAC-Rough 9/3/2020 Approved DAVID HEINE
PLUMBING-Rough 9/15/2020 Approved DAVID HEINE
BUILDING-Rough-Frame 9/22/2020 Partial Approval DAVID HEINE
Green Building Rough 9/22/2020 Not Ready for Inspection DAVID HEINE
Verify Sprinkler Sign Off 9/22/2020 Not Ready for Inspection DAVID HEINE
Interior/Exterior Lathing 10/26/2020 Partial Approval DAVID HEINE
BUILDING-Rough-Frame 10/28/2020 Approved DAVID HEINE
Green Building Rough 10/28/2020 Approved DAVID HEINE
Verify Sprinkler Sign Off 10/28/2020 Approved DAVID HEINE
Insulation 11/13/2020 Approved DAVID HEINE
Shower Pan 11/13/2020 Approved DAVID HEINE
Drywall Nailing 11/30/2020 Approved DAVID HEINE
Sewer 1/6/2021 Approved DAVID HEINE
Gas Test 7/9/2021 Partial Approval JOHNNY MIRANDA
Deck 8/3/2021 Partial Approval MATT KELLERMAN
Footing/Foundation/Slab 8/3/2021 Partial Approval MATT KELLERMAN
Masonry Wall/Backfill 8/10/2021 Partial Approval JOHNNY MIRANDA
Deck 8/16/2021 Partial Approval WILLIAM MICHALAK
HVAC-Final 9/14/2021 Corrections Issued JOHNNY MIRANDA
PLUMBING-Final 9/14/2021 Corrections Issued JOHNNY MIRANDA
ELECTRICAL-Final 9/15/2021 Approved JOHNNY MIRANDA
Green Building Final 9/15/2021 Corrections Issued JOHNNY MIRANDA
Green Building Final 9/23/2021 Approved JOHNNY MIRANDA
HVAC-Final 9/23/2021 Approved JOHNNY MIRANDA
PLUMBING-Final 9/23/2021 Approved JOHNNY MIRANDA
Final 9/24/2021 Corrections Issued JOHNNY MIRANDA
Footing/Foundation/Slab 9/24/2021 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 9/24/2021 SGSOV Approved JOHNNY MIRANDA
Service/Power Release 9/24/2021 Not Ready for Inspection JOHNNY MIRANDA
Smoke Detectors 9/24/2021 Approved JOHNNY MIRANDA
Final 10/20/2021 Not Ready for Inspection DAVID FEILER
Service/Power Release 10/20/2021 Not Ready for Inspection DAVID FEILER
Final 11/1/2021 OK to Issue CofO DAVID FEILER
Service/Power Release 11/1/2021 Approved DAVID FEILER