2352 W RIVERSIDE DR 90039
Certificate Information: 2352 W RIVERSIDE DR 90039
- Application / Permit
- 17010-30000-00641
- Plan Check / Job No.
- B17WL00808
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- new 2-story s.f.d w/ attached garage
- Permit Issued
- Issued on 8/8/2017
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/30/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/17/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 3/9/2017 | DIEGO BAUTISTA |
| Corrections Issued | 3/13/2017 | DIEGO BAUTISTA |
| Quality Review Completed | 3/14/2017 | STEVEN KIM |
| Building Plans Picked Up | 3/15/2017 | APPLICANT |
| Green Plans Picked Up | 3/17/2017 | APPLICANT |
| Applicant returned to address corrections | 3/23/2017 | DIEGO BAUTISTA |
| Applicant returned to address corrections | 4/6/2017 | DIEGO BAUTISTA |
| Applicant returned to address corrections | 4/19/2017 | DIEGO BAUTISTA |
| Applicant returned to address corrections | 4/27/2017 | DIEGO BAUTISTA |
| Applicant returned to address corrections | 6/7/2017 | DIEGO BAUTISTA |
| Plan Check Approved | 7/31/2017 | DIEGO BAUTISTA |
| Issued | 8/8/2017 | LADBS |
| CofO in Progress | 1/21/2023 | THOMAS LOGRASSO |
| CofO Issued | 1/30/2023 | DEROLD HAUFF |
| Permit Finaled | 1/30/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Permit | Cleared | 3/20/2017 | CHEN ZHANG |
| Address approval | Cleared | 3/23/2017 | CARLA VALLADARES |
| Eng Process Fee Ord 176,300 | Cleared | 3/23/2017 | CARLA VALLADARES |
| Sewer availability | Cleared | 3/23/2017 | CARLA VALLADARES |
| Hydrant and Access approval | Cleared | 4/6/2017 | ROBERT DUFF |
| GPI Written Notices | Cleared | 4/12/2017 | DIEGO BAUTISTA |
| Grading Pre-Inspection | Cleared | 4/12/2017 | DIEGO BAUTISTA |
| Low Impact Development | Cleared | 4/13/2017 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 4/13/2017 | ROCHELLE DUNGCA |
| Green Code | Cleared | 4/19/2017 | RICHARD GARCIA |
| Excavation more than 5-ft deep | Cleared | 5/17/2017 | CALOSHA APPROVED |
Contact Information
| Architect | Murnane, R Mcshane; Lic. No.: C34176 | 2898 ROWENA AVENUE UNIT 102 LOS ANGELES, CA 90039 |
| Contractor | Line Electric Inc; Lic. No.: 910172-B | 4055 WILSHIRE BLVD #500 LOS ANGELES, CA 90010 |
| Engineer | Khoury, Nader Bulos; Lic. No.: C61402 | 3406 LINDA VISTA TER FALLBROOK, CA 92028 |
| Engineer | Salehipour, Sassan A; Lic. No.: GE2579 | 1290 N LAKE AVENUE #204 PASADENA, CA 91104 |
| Geologist | Hill, Thomas George; Lic. No.: EG1100 | 3210 VAL VERDE LONG BEACH, CA 90808 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/11/2020 | Not Ready for Inspection | COREY HUPP |
| PLUMBING-Rough | 6/11/2020 | Not Ready for Inspection | COREY HUPP |
| ELECTRICAL-Rough | 6/16/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 6/16/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 6/16/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 6/24/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 6/24/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Underground Mechanical | 6/24/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| Underground Mechanical | 6/25/2020 | Partial Approval | MATTHEW NUCKOLLS |
| Underground Mechanical | 9/1/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 9/28/2020 | Partial Approval | DONALD CRICHLOW |
| Structural Steel Frame | 9/28/2020 | Partial Approval | DONALD CRICHLOW |
| Underground Mechanical | 9/28/2020 | Partial Approval | DONALD CRICHLOW |
| Wood Frame | 11/10/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Sewer | 12/15/2020 | Approved | KATHRYN BUTTERWORTH |
| Wood Frame | 12/15/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| Wood Frame | 12/18/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Deputy Wood Construction | 12/23/2020 | No Access for Inspection | ELMER BLAND |
| ELECTRICAL-Rough | 4/22/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 4/22/2021 | Approved | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 4/23/2021 | Approved | KATHRYN BUTTERWORTH |
| HVAC-Rough | 4/23/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 5/4/2021 | Conditional Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 5/4/2021 | Approved | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 5/4/2021 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 5/4/2021 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 5/4/2021 | Approved | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 5/4/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Wood Frame | 5/4/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Wood Frame | 5/13/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Insulation | 6/15/2021 | Partial Approval | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 8/10/2021 | Approved | THOMAS LOGRASSO |
| Verify Sprinkler Sign Off | 8/10/2021 | Approved | THOMAS LOGRASSO |
| Insulation | 8/11/2021 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 8/11/2021 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 2/24/2022 | Approved | KATHRYN BUTTERWORTH |
| Shower Pan | 6/1/2022 | Approved | THOMAS LOGRASSO |
| Final | 11/28/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Final | 11/28/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Reinforced Concrete Frame | 11/28/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 11/28/2022 | SGSOV Not Ready | THOMAS LOGRASSO |
| Service/Power Release | 11/28/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Smoke Detectors | 11/28/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 1/13/2023 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Final | 1/13/2023 | Approved | THOMAS LOGRASSO |
| Reinforced Concrete Frame | 1/13/2023 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 1/13/2023 | SGSOV Approved | THOMAS LOGRASSO |
| Service/Power Release | 1/13/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Smoke Detectors | 1/13/2023 | Approved | THOMAS LOGRASSO |
| Final | 1/20/2023 | OK to Issue CofO | THOMAS LOGRASSO |
| Service/Power Release | 1/20/2023 | Approved | THOMAS LOGRASSO |