218 N MABERY ROAD 90402

Certificate Information: 218 N MABERY ROAD 90402

Application / Permit
17010-30000-00627
Plan Check / Job No.
B17WL00782
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW 1-STORY RECREATION ROOM AT REAR YARD.
Permit Issued
Issued on 8/27/2021
Issuing Office
Current Status
CofO Issued on 4/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/16/2017 APPLICANT
Assigned to Plan Check Engineer 3/16/2017 ERWIN PASCUA
Corrections Issued 3/24/2017 ERWIN PASCUA
Quality Review Completed 3/30/2017 STEVEN KIM
Building Plans Picked Up 3/31/2017 APPLICANT
Applicant returned to address corrections 5/9/2017 ERWIN PASCUA
Green Plans Picked Up 12/26/2017 APPLICANT
Applicant returned to address corrections 4/18/2018 ERWIN PASCUA
Plan Check Approved 8/17/2021 ERWIN PASCUA
Issued 8/27/2021 APPLICANT
CofO in Progress 4/1/2022 JOHN KIDWELL
Permit Finaled 4/11/2022 DANIEL ORRANTE
CofO Issued 4/11/2022 DANIEL ORRANTE
Permit Finaled 4/11/2022 DANIEL ORRANTE

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 4/4/2017 ERIK MUNOZ
BHO/Hillside ordinance Cleared 4/4/2017 ERIK MUNOZ
BHO/Hillside ordinance Cleared 4/4/2017 ERIK MUNOZ
Eng Process Fee Ord 176,300 Cleared 4/4/2017 ERIK MUNOZ
Permit Cleared 4/4/2017 ERIK MUNOZ
Sewer availability Cleared 4/4/2017 ERIK MUNOZ
ZA Case Cleared 4/6/2017 JUSTIN BILOW
Roof/Waste drainage to street Cleared 1/23/2018 JAMES MORALEZ
GPI Written Notices Cleared 1/28/2020 ERWIN PASCUA
Grading Pre-Inspection Cleared 1/28/2020 ERWIN PASCUA
Coastal Zone Cleared 11/18/2020 RUBEN VASQUEZ
Miscellaneous Cleared 11/18/2020 RUBEN VASQUEZ
ZI Cleared 11/18/2020 RUBEN VASQUEZ
Low Impact Development Cleared 7/20/2021 ORVAL HERNANDEZ-MARCI
Construction near power lines Cleared 7/24/2021 RIDWAN HARDY
Green Code Cleared 8/17/2021 ERWIN PASCUA

Contact Information

Contractor Owner-Builder       ,
Engineer Hollingsworth,, Robert Alan; Lic. No.: GE2022 31129 VIA COLINAS SUITE 707      WESTLAKE VILLAGE, CA 91362
Engineer Tuchscher, James Todd; Lic. No.: C77649 5503 E 2ND ST      LONG BEACH, CA 90803
Geologist Hollingsworth,, Robert Alan; Lic. No.: EG1265 31129 VIA COLINAS SUITE 707      WESTLAKE VILLAGE, CA 91362

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 9/7/2021 Not Ready for Inspection JUAN VALENZUELA
Drywall Nailing 9/7/2021 Partial Inspection JUAN VALENZUELA
Final 9/7/2021 Not Ready for Inspection JUAN VALENZUELA
Footing/Foundation/Slab 9/7/2021 Not Ready for Inspection JUAN VALENZUELA
Green Building Final 9/7/2021 Partial Inspection JUAN VALENZUELA
Green Building Rough 9/7/2021 Not Ready for Inspection JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 9/7/2021 SGSOV Not Ready JUAN VALENZUELA
Service/Power Release 9/7/2021 Not Ready for Inspection JUAN VALENZUELA
Smoke Detectors 9/7/2021 Not Ready for Inspection JUAN VALENZUELA
Structural Steel Frame 9/7/2021 Not Ready for Inspection JUAN VALENZUELA
Verify Sprinkler Sign Off 9/7/2021 Not Ready for Inspection JUAN VALENZUELA
ELECTRICAL-Final 9/29/2021 Not Ready for Inspection JOHN KIDWELL
HVAC-Rough 9/29/2021 Approved JOHN KIDWELL
PLUMBING-Final 9/29/2021 Not Ready for Inspection JOHN KIDWELL
BUILDING-Rough-Frame 10/12/2021 Approved JOHN KIDWELL
ELECTRICAL-Rough 10/12/2021 Approved JOHN KIDWELL
Green Building Rough 10/12/2021 Approved JOHN KIDWELL
PLUMBING-Rough 10/12/2021 Approved JOHN KIDWELL
Verify Sprinkler Sign Off 10/12/2021 Approved JOHN KIDWELL
Drywall Nailing 10/19/2021 Approved JOHN KIDWELL
Final 3/4/2022 Corrections Issued ANDREW NAVE
Footing/Foundation/Slab 3/4/2022 Approved ANDREW NAVE
Green Building Final 3/4/2022 Corrections Issued ANDREW NAVE
SGSOV-Seismic Gas S/O Valve 3/4/2022 SGSOV Approved ANDREW NAVE
Service/Power Release 3/4/2022 Approved ANDREW NAVE
Smoke Detectors 3/4/2022 Approved ANDREW NAVE
Structural Steel Frame 3/4/2022 Approved ANDREW NAVE
ELECTRICAL-Final 3/15/2022 Approved ANDREW NAVE
Final 3/15/2022 Corrections Issued ANDREW NAVE
Green Building Final 3/15/2022 Approved ANDREW NAVE
HVAC-Final 3/15/2022 Approved ANDREW NAVE
PLUMBING-Final 3/15/2022 Approved ANDREW NAVE
Special/Order Compliance 3/15/2022 Partial Inspection PATRICK QUALEY
Final 3/31/2022 OK to Issue CofO JOHN KIDWELL