3238 S MOUNTAIN VIEW AVE 90066
Certificate Information: 3238 S MOUNTAIN VIEW AVE 90066
- Application / Permit
- 17010-30000-00613
- Plan Check / Job No.
- B17WL00756
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New irregualr shaped 72'0" x 38'0" 2-story SFD with uncovered roof deck and attached garage. Fully sprinklered per NFPA 13D. (See comments).
- Permit Issued
- Issued on 1/6/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/15/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 3/16/2017 | CRYSTEL MAALOUF |
| Corrections Issued | 3/30/2017 | JOSE RODRIGUEZ |
| Quality Review Completed | 4/3/2017 | STEVEN KIM |
| Building Plans Picked Up | 4/4/2017 | APPLICANT |
| Green Plans Picked Up | 4/4/2017 | APPLICANT |
| Applicant returned to address corrections | 11/15/2018 | JOSE RODRIGUEZ |
| Applicant returned to address corrections | 11/29/2018 | JOSE RODRIGUEZ |
| Plan Check Approved | 4/3/2019 | JOSE RODRIGUEZ |
| Plan Check Approved | 1/6/2020 | JOSE RODRIGUEZ |
| Issued | 1/6/2020 | LADBS |
| CofO in Progress | 1/17/2023 | DAVID FEILER |
| Permit Finaled | 1/18/2023 | DANIEL ORRANTE |
| CofO Issued | 1/18/2023 | DANIEL ORRANTE |
| Permit Finaled | 1/18/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/8/2018 | STEVEN JIN |
| Grading Pre-Inspection | Cleared | 11/29/2018 | PATRICK MISCHLICH |
| Address approval | Cleared | 12/12/2018 | ADRIAN SANCHEZ |
| Green Code | Cleared | 12/12/2018 | RICHARD GARCIA |
| Hydrant and Access approval | Cleared | 12/12/2018 | PEJMAN NOORI |
| Permit | Cleared | 12/12/2018 | ADRIAN SANCHEZ |
| Permit | Cleared | 12/12/2018 | ADRIAN SANCHEZ |
| Roof/Waste drainage to street | Cleared | 12/12/2018 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 12/12/2018 | ADRIAN SANCHEZ |
| Trees in Parkway | Cleared | 12/14/2018 | ADRIAN SANCHEZ |
| Low Impact Development | Cleared | 1/17/2019 | JORGE MEJIA LEMUS |
| GPI Written Notices | Cleared | 3/4/2019 | JOSE RODRIGUEZ |
| Green Code | Cleared | 12/26/2019 | JOSE RODRIGUEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Babayan, Raffi Samuel; Lic. No.: C72168 | 1140 N COLUMBUS AVE 112 GLENDALE, CA 91202 |
| Engineer | Germiyanoglu, Ismail; Lic. No.: S1505 | 144 N STANLEY DR BEVERLY HILLS, CA 90211 |
| Engineer | Miyamoto, Yoshiaki Wayne; Lic. No.: L4825 | 4396 MENTONE AVE CULVER CITY, CA 90230 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/21/2020 | Partial Approval | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 10/7/2020 | Conditional Approval | ANTHONY MCDOWALL |
| Deputy Reinf. Concrete | 10/8/2020 | Conditional Approval | ANTHONY MCDOWALL |
| Deputy Reinf. Concrete | 10/22/2020 | Conditional Approval | ANTHONY MCDOWALL |
| Deputy Wood Construction | 10/26/2020 | Conditional Approval | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2020 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Wood Construction | 11/12/2020 | Conditional Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2020 | Approved | RICHARD ROBLES |
| Deputy Wood Construction | 12/9/2020 | Conditional Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2020 | Approved | RICHARD ROBLES |
| ELECTRICAL-Rough | 1/14/2021 | Approved | EVAN COOPER |
| PLUMBING-Rough | 1/22/2021 | Partial Approval | OGANES TARAKHCHYAN |
| HVAC-Rough | 1/25/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Rough | 1/27/2021 | Corrections Issued | RICHARD ROBLES |
| BUILDING-Rough-Frame | 2/10/2021 | Not Ready for Inspection | RICHARD ROBLES |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2021 | Approved | RICHARD ROBLES |
| Green Building Rough | 2/10/2021 | Not Ready for Inspection | RICHARD ROBLES |
| HVAC-Rough | 2/10/2021 | Not Ready for Inspection | RICHARD ROBLES |
| PLUMBING-Rough | 2/10/2021 | Not Ready for Inspection | RICHARD ROBLES |
| Verify Sprinkler Sign Off | 2/10/2021 | Approved | RICHARD ROBLES |
| BUILDING-Rough-Frame | 3/8/2021 | Not Ready for Inspection | EVAN COOPER |
| Green Building Rough | 3/8/2021 | Not Ready for Inspection | EVAN COOPER |
| BUILDING-Rough-Frame | 3/9/2021 | Conditional Approval | RICHARD ROBLES |
| Green Building Rough | 3/9/2021 | Approved | RICHARD ROBLES |
| Rough-Elec/Plmb/HVAC | 3/9/2021 | Partial Approval | RICHARD ROBLES |
| Insulation | 3/12/2021 | Partial Inspection | OGANES TARAKHCHYAN |
| Deputy Reinf. Concrete | 3/16/2021 | No Access for Inspection | KENNETH NAGLE |
| BUILDING-Rough-Frame | 3/22/2021 | Approved | EVAN COOPER |
| Insulation | 3/22/2021 | Approved | EVAN COOPER |
| PLUMBING-Rough | 3/22/2021 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 3/26/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Drywall Nailing | 5/3/2021 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 5/3/2021 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 10/28/2021 | Corrections Issued | JOHNNY MIRANDA |
| Gas Test | 12/2/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Gas Test | 12/9/2021 | Corrections Issued | JOHNNY MIRANDA |
| ELECTRICAL-Final | 3/24/2022 | Approved | JOHNNY MIRANDA |
| Service/Power Release | 3/24/2022 | Approved | JOHNNY MIRANDA |
| HVAC-Final | 7/7/2022 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 7/7/2022 | Corrections Issued | HERBERT GIRON |
| Special/Order Compliance | 7/7/2022 | Partial Inspection | CLAYTON GRAHAM |
| Gas Test | 7/15/2022 | Approved | JOHNNY MIRANDA |
| HVAC-Final | 9/16/2022 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Final | 9/16/2022 | Approved | JOHNNY MIRANDA |
| HVAC-Final | 9/22/2022 | Approved | JOHN KIDWELL |
| Final | 11/22/2022 | Corrections Issued | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 11/22/2022 | Approved | JOHNNY MIRANDA |
| Green Building Final | 11/22/2022 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 11/22/2022 | SGSOV Approved | JOHNNY MIRANDA |
| Smoke Detectors | 11/22/2022 | Approved | JOHNNY MIRANDA |
| Final | 1/6/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| Final | 1/11/2023 | OK to Issue CofO | JOHNNY MIRANDA |