306 N CLIFFWOOD AVE 90049
Certificate Information: 306 N CLIFFWOOD AVE 90049
- Application / Permit
- 17010-30000-00479
- Plan Check / Job No.
- B17WL00641
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- new 2 story + basement s.f.d.
- Permit Issued
- Issued on 5/15/2017
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 5/15/2017
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/10/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 3/9/2017 | DEAN RYAN REYES |
| Corrections Issued | 3/14/2017 | DEAN RYAN REYES |
| Quality Review Completed | 3/17/2017 | STEVEN KIM |
| Building Plans Picked Up | 3/17/2017 | APPLICANT |
| Green Plans Picked Up | 3/17/2017 | APPLICANT |
| Applicant returned to address corrections | 4/5/2017 | DEAN RYAN REYES |
| Applicant returned to address corrections | 4/13/2017 | DEAN RYAN REYES |
| Applicant returned to address corrections | 4/18/2017 | DEAN RYAN REYES |
| Applicant returned to address corrections | 4/21/2017 | DEAN RYAN REYES |
| Plan Check Approved | 5/4/2017 | DEAN RYAN REYES |
| Issued | 5/15/2017 | LADBS |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 3/22/2017 | ROBERT DUFF |
| ZI | Cleared | 3/24/2017 | TRACY WILLIAMS |
| Eng Process Fee Ord 176,300 | Cleared | 4/25/2017 | ADRIAN SANCHEZ |
| Low Impact Development | Cleared | 4/25/2017 | RYAN HUDSON |
| Permit | Cleared | 4/25/2017 | ADRIAN SANCHEZ |
| Roof/Waste drainage to street | Cleared | 4/25/2017 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 4/25/2017 | ADRIAN SANCHEZ |
| Excavation more than 5-ft deep | Cleared | 5/4/2017 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 5/4/2017 | DEAN RYAN REYES |
| Green Code | Cleared | 5/4/2017 | BRYAN MEYER |
Contact Information
| Architect | Ungar, Kenneth Joel; Lic. No.: C21777 | 988 COUNTRY VALLEY ROAD WESTLAKE VILLAGE, CA 91362 |
| Contractor | Heltzer Development Group Inc; Lic. No.: 993371-B | 11751 MISSISSIPPI AVENUE SUITE 100 LOS ANGELES, CA 90025 |
| Engineer | Joshua, F Danz; Lic. No.: C84764 | , |
| Engineer | Tani, Jason Yukio; Lic. No.: C58271 | 5296 VIA PATRICIA THOUSAND OAKS, CA 91320 |
| Engineer | Walter, Scott John; Lic. No.: GE2476 | 14428 HAMLIN ST STE 200 VAN NUYS, CA 91401 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/18/2017 | Not Ready for Inspection | JOHN LUMB |
| Footing/Foundation/Slab | 5/18/2017 | Not Ready for Inspection | JOHN LUMB |
| Excavation/Setback/Form/Re-Bar | 5/19/2017 | Not Ready for Inspection | JOHN LUMB |
| Underground Mechanical | 8/10/2017 | Partial Approval | JOHN LUMB |
| Footing/Foundation/Slab | 8/14/2017 | Partial Approval | JOHN LUMB |
| Footing/Foundation/Slab | 8/28/2017 | Partial Approval | JOHN LUMB |
| Deputy Reinf. Concrete | 8/30/2017 | Approved | JOHN LUMB |
| ELECTRICAL-Rough | 8/30/2017 | Partial Approval | JOHN LUMB |
| Excavation/Setback/Form/Re-Bar | 9/11/2017 | Partial Approval | VINCENT SCIPIONI |
| Deputy Reinf. Concrete | 9/13/2017 | Approved | RICHARD STEINBACH |
| Excavation/Setback/Form/Re-Bar | 9/13/2017 | Partial Approval | RICHARD STEINBACH |
| Deputy Reinf. Concrete | 9/25/2017 | Approved | JOHN LUMB |
| Excavation/Setback/Form/Re-Bar | 9/25/2017 | Partial Approval | JOHN LUMB |
| Deputy Reinf. Concrete | 9/28/2017 | Approved | JOHN LUMB |
| Excavation/Setback/Form/Re-Bar | 9/29/2017 | Partial Approval | JOHN LUMB |
| Grading Pre-Inspection | 10/11/2017 | Partial Approval | JOHN LUMB |
| Footing/Foundation/Slab | 11/16/2017 | Partial Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 11/28/2017 | Partial Approval | JOHN LUMB |
| Footing/Foundation/Slab | 11/28/2017 | Partial Approval | JOHN LUMB |
| Green Building Rough | 11/28/2017 | Not Ready for Inspection | JOHN LUMB |
| Verify Sprinkler Sign Off | 11/28/2017 | Not Ready for Inspection | JOHN LUMB |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2017 | Conditional Approval | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 1/17/2018 | Not Ready for Inspection | JOHN LUMB |
| Green Building Rough | 1/17/2018 | Not Ready for Inspection | JOHN LUMB |
| Verify Sprinkler Sign Off | 1/17/2018 | Corrections Issued | JOHN LUMB |
| BUILDING-Rough-Frame | 1/19/2018 | Partial Approval | JOHN LUMB |
| Deputy Reinf. Concrete | 1/19/2018 | Approved | JOHN LUMB |
| Green Building Rough | 1/19/2018 | Not Ready for Inspection | JOHN LUMB |
| Verify Sprinkler Sign Off | 1/19/2018 | Approved | JOHN LUMB |
| Footing/Foundation/Slab | 1/22/2018 | Partial Approval | JOHN LUMB |
| Deputy Drilled-In Anchors | 4/16/2018 | No Access for Inspection | KENNETH NAGLE |
| Footing/Foundation/Slab | 4/18/2018 | Partial Approval | KENNETH NAGLE |
| Deputy Reinf. Concrete | 4/24/2018 | No Access for Inspection | KENNETH NAGLE |
| ELECTRICAL-Rough | 8/29/2018 | Not Ready for Inspection | KENNETH NAGLE |
| HVAC-Rough | 8/29/2018 | Not Ready for Inspection | KENNETH NAGLE |
| ELECTRICAL-Rough | 9/5/2018 | Not Ready for Inspection | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2018 | Partial Approval | KENNETH NAGLE |
| Interior/Exterior Lathing | 9/5/2018 | Partial Approval | KENNETH NAGLE |
| ELECTRICAL-Rough | 9/6/2018 | Corrections Issued | KENNETH NAGLE |
| HVAC-Rough | 9/7/2018 | Corrections Issued | KENNETH NAGLE |
| PLUMBING-Rough | 9/26/2018 | Not Ready for Inspection | KENNETH NAGLE |
| BUILDING-Rough-Frame | 10/9/2018 | Conditional Approval | KENNETH NAGLE |
| Green Building Rough | 10/9/2018 | Approved | KENNETH NAGLE |
| PLUMBING-Rough | 10/9/2018 | Approved | KENNETH NAGLE |
| BUILDING-Rough-Frame | 10/18/2018 | Approved | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2018 | Approved | KENNETH NAGLE |
| Drywall Nailing | 10/24/2018 | Corrections Issued | MICHAEL PELHAM |
| Insulation | 10/24/2018 | Approved | MICHAEL PELHAM |
| Drywall Nailing | 1/14/2019 | Approved | KENNETH NAGLE |
| ELECTRICAL-Rough | 1/14/2019 | Approved | KENNETH NAGLE |
| HVAC-Rough | 1/14/2019 | Approved | KENNETH NAGLE |
| Interior/Exterior Lathing | 1/14/2019 | Approved | KENNETH NAGLE |
| Sewer | 3/1/2019 | Partial Approval | KENNETH NAGLE |
| Underground Mechanical | 6/2/2020 | Partial Approval | TIM CHRISTENSEN |
| Underground Mechanical | 7/7/2020 | Partial Approval | TIM CHRISTENSEN |
| Gas Test | 9/14/2020 | Corrections Issued | TIM CHRISTENSEN |
| Gas Test | 9/16/2020 | Approved | TIM CHRISTENSEN |
| Footing/Foundation/Slab | 12/9/2020 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 1/4/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Pre-Inspection | 5/19/2021 | Partial Inspection | KENNETH NAGLE |
| PLUMBING-Final | 9/1/2021 | Corrections Issued | JUAN VALENZUELA |
| ELECTRICAL-Final | 12/13/2022 | Not Ready for Inspection | ASHLEY THOMPSON |
| Special/Order Compliance | 5/30/2023 | Corrections Issued | KENNETH NAGLE |