3030 N COOLIDGE AVE 90039

Certificate Information: 3030 N COOLIDGE AVE 90039

Application / Permit
17010-30000-00400
Plan Check / Job No.
B17WL00512
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Lot unit 15: New Unit of a 30 small lot subdivision s.f.d. homes where 2 units are to very low income household occupancy. Small lot subdivision pursuant to tentative tract map no 74109-sl. A certificate of occupancy (temporary or final) shall not be issued until after the final map has been recorded. ********************15 of 30 **************************
Permit Issued
Issued on 5/25/2018
Issuing Office
Metro
Current Status
CofO Issued on 6/23/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/3/2017 APPLICANT
Building Plans Picked Up 2/27/2017 APPLICANT
Green Plans Picked Up 2/27/2017 APPLICANT
Assigned to Plan Check Engineer 3/2/2017 RICARDO RAMIREZ
Corrections Issued 3/13/2017 RICARDO RAMIREZ
Quality Review Completed 3/24/2017 STEVEN KIM
Applicant returned to address corrections 4/27/2017 RICARDO RAMIREZ
Applicant returned to address corrections 5/19/2017 RICARDO RAMIREZ
Plan Check Approved 1/19/2018 RICARDO RAMIREZ
Issued 5/25/2018 LADBS
CofO in Progress 6/17/2020 SCOTT FINNILA
Permit Finaled 6/23/2020 DEROLD HAUFF
CofO Issued 6/23/2020 DEROLD HAUFF
Permit Finaled 6/23/2020 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/3/2017 ALFREDO JARA
Eng Process Fee Ord 176,300 Cleared 5/3/2017 ALFREDO JARA
Low Impact Development Cleared 5/25/2017 AMMAR ELTAWIL
Highway dedication Cleared 5/26/2017 SEVAK ISAKHAYAN
Hydrant and Access approval Cleared 6/1/2017 JOHN CONNEALLY
Sewer availability Cleared 6/20/2017 IRENE CHIA
Miscellaneous Cleared 7/31/2017 DAVID PEREZ
Roof/Waste drainage to street Cleared 7/31/2017 DAVID PEREZ
"Q" conditions Cleared 8/16/2017 DANALYNN DOMINGUEZ
CPC Cleared 8/16/2017 DANALYNN DOMINGUEZ
Tract Map conditions Cleared 8/16/2017 DANALYNN DOMINGUEZ
ZI Cleared 8/16/2017 DANALYNN DOMINGUEZ
ZI Cleared 8/16/2017 DANALYNN DOMINGUEZ
Housing density bonus Cleared 9/27/2017 NICHOLAS KAWAZOE
Miscellaneous Cleared 10/23/2017 AIDA KARAPETIAN
Construction near power lines Cleared 3/8/2018 RIDWAN HARDY
Green Code Cleared 4/10/2018 RICHARD GARCIA

Contact Information

Architect Leavitt, Derek Chase; Lic. No.: C31212 425 MARINE STREET # 6      SANTA MONICA, CA 90405
Contractor Owner-Builder       ,
Engineer Krief, Dan Dov; Lic. No.: C76041 1450 S BEVERLY DR 305      LOS ANGELES, CA 90035
Engineer Nguyen, Huan Ngoc; Lic. No.: C64238 7015 PINNACLE POINTE      ORANGE, CA 92869

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/7/2018 Partial Approval SCOTT FINNILA
Underground Mechanical 11/7/2018 Partial Approval SCOTT FINNILA
METHANE-Subgrade 11/28/2018 Partial Approval SCOTT FINNILA
Pre-Inspection 11/28/2018 Partial Approval SCOTT FINNILA
Underground Mechanical 11/28/2018 Partial Approval SCOTT FINNILA
METHANE-Barrier 12/4/2018 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 12/12/2018 Approved SCOTT FINNILA
Deputy Reinf. Concrete 12/13/2018 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 2/20/2019 Partial Approval SCOTT FINNILA
Deputy Wood Construction 2/25/2019 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 2/25/2019 Corrections Issued MICHAEL FAUNCE
Floor/Roof Diaphrgm/Shear Wall 2/28/2019 Partial Approval MICHAEL FAUNCE
Drywall Nailing 3/6/2019 No Access for Inspection MICHAEL FAUNCE
Floor/Roof Diaphrgm/Shear Wall 3/6/2019 No Access for Inspection MICHAEL FAUNCE
Floor/Roof Diaphrgm/Shear Wall 3/8/2019 Partial Approval SCOTT FINNILA
Special/Order Compliance 3/8/2019 Corrections Issued SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 3/19/2019 Partial Approval SCOTT FINNILA
Deputy Wood Construction 3/20/2019 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 4/4/2019 Partial Approval SCOTT FINNILA
Drywall Nailing 4/5/2019 Corrections Issued SCOTT FINNILA
Drywall Nailing 4/8/2019 Not Ready for Inspection SCOTT FINNILA
Drywall Nailing 4/9/2019 Corrections Issued SCOTT FINNILA
Drywall Nailing 4/10/2019 Partial Approval SCOTT FINNILA
Insulation 4/29/2019 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 4/30/2019 Partial Approval SCOTT FINNILA
Drywall Nailing 5/7/2019 Partial Approval SCOTT FINNILA
HVAC-Rough 7/2/2019 Partial Inspection SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 7/12/2019 Corrections Issued SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 7/23/2019 Not Ready for Inspection SCOTT FINNILA
PLUMBING-Rough 7/23/2019 Not Ready for Inspection SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 7/25/2019 Partial Approval SCOTT FINNILA
PLUMBING-Rough 7/26/2019 Corrections Issued MICHAEL FAUNCE
METHANE-Rough 7/30/2019 Approved SCOTT FINNILA
PLUMBING-Rough 7/30/2019 Approved SCOTT FINNILA
ELECTRICAL-Rough 8/1/2019 Partial Approval SCOTT FINNILA
ELECTRICAL-Rough 8/2/2019 Corrections Issued SCOTT FINNILA
HVAC-Rough 8/12/2019 Approved SCOTT FINNILA
ELECTRICAL-Rough 8/15/2019 Corrections Issued SCOTT FINNILA
HVAC-Rough 8/15/2019 Approved SCOTT FINNILA
BUILDING-Rough-Frame 8/21/2019 Not Ready for Inspection SCOTT FINNILA
ELECTRICAL-Rough 8/21/2019 Approved SCOTT FINNILA
Green Building Rough 8/21/2019 Not Ready for Inspection SCOTT FINNILA
Verify Sprinkler Sign Off 8/21/2019 Approved SCOTT FINNILA
BUILDING-Rough-Frame 9/4/2019 Corrections Issued MICHAEL FAUNCE
Green Building Rough 9/4/2019 Conditional Approval MICHAEL FAUNCE
BUILDING-Rough-Frame 9/10/2019 Partial Inspection SCOTT FINNILA
Green Building Rough 9/10/2019 Approved SCOTT FINNILA
BUILDING-Rough-Frame 9/12/2019 Approved SCOTT FINNILA
Insulation 9/19/2019 Approved SCOTT FINNILA
Interior/Exterior Lathing 9/19/2019 Not Ready for Inspection SCOTT FINNILA
Drywall Nailing 9/20/2019 Not Ready for Inspection SCOTT FINNILA
Drywall Nailing 9/27/2019 Conditional Approval MICHAEL FAUNCE
Drywall Nailing 10/4/2019 Approved MICHAEL FAUNCE
Underground Mechanical 11/19/2019 Partial Approval SCOTT FINNILA
Gas Test 12/9/2019 Partial Approval SCOTT FINNILA
Underground Mechanical 12/9/2019 Partial Approval SCOTT FINNILA
Interior/Exterior Lathing 1/7/2020 Conditional Approval SCOTT FINNILA
Service/Power Release 3/4/2020 Partial Inspection SCOTT FINNILA
Service/Power Release 4/3/2020 Not Ready for Inspection SCOTT FINNILA
Service/Power Release 4/27/2020 No Access for Inspection SCOTT FINNILA
ELECTRICAL-Final 5/12/2020 Approved SCOTT FINNILA
HVAC-Final 5/12/2020 Approved SCOTT FINNILA
Gas Test 5/14/2020 Approved SCOTT FINNILA
Final 5/28/2020 Partial Inspection SCOTT FINNILA
Green Building Final 5/28/2020 Approved SCOTT FINNILA
PLUMBING-Final 5/28/2020 Approved SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 5/28/2020 SGSOV Approved SCOTT FINNILA
Service/Power Release 5/28/2020 Approved SCOTT FINNILA
Final 6/16/2020 OK to Issue CofO SCOTT FINNILA