17454 W CHATSWORTH ST #1-54 91344
Certificate Information: 17454 W CHATSWORTH ST #1-54 91344
- Application / Permit
- 17010-20003-01261
- Plan Check / Job No.
- B22VN09602
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (5) Apartment
- Work Description
- SUPPLEMENTAL PERMIT FOR 17010-20000-01261 TO REVISE FLOOR PLANS, REDUCE NUMBER OF PARKING SPACES, REDUCE OPEN SPACE & CHANGE EXITING (NO CHANGE TO REQ'D PKG SPACES)
- Permit Issued
- Issued on 2/10/2023
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 11/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/7/2022 | NILOOFAR MEHRAIN |
| Disabled Access Plans Picked Up | 7/7/2022 | APPLICANT |
| Plans on Hold | 7/8/2022 | OMID HEDAYAT |
| Green Plans Picked Up | 7/14/2022 | APPLICANT |
| Hold Released | 7/18/2022 | NILOOFAR MEHRAIN |
| Corrections Issued | 7/19/2022 | NILOOFAR MEHRAIN |
| Quality Review Completed | 7/25/2022 | STEVEN KIM |
| Building Plans Picked Up | 7/27/2022 | APPLICANT |
| Plan Check Approved | 1/26/2023 | NILOOFAR MEHRAIN |
| Issued | 2/10/2023 | APPLICANT |
| Permit Finaled | 11/13/2023 | JEFFREY FULTON |
Permit Application Clearance Information
| DAS Clearance | Cleared | 8/31/2022 | NORLITO MEDRANO |
| Green Code | Cleared | 9/1/2022 | MICHAEL AYERS |
| Fire Marshal Fire Life Safety | Cleared | 10/11/2022 | VIDAL GARCIA |
| Miscellaneous | Cleared | 11/28/2022 | NELSON RODRIGUEZ |
| Opn space landscape/Water mgmt | Cleared | 11/28/2022 | NELSON RODRIGUEZ |
| Specific Plan | Cleared | 12/22/2022 | NELSON RODRIGUEZ |
| ZI | Cleared | 12/22/2022 | NELSON RODRIGUEZ |
Contact Information
| Contractor | Jasco Enterprise Inc; Lic. No.: 871467-B | 12439 MAGNOLIA BL 185 VALLEY VILLAGE, CA 91607 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 11/13/2023 | Permit Finaled | JEFFREY FULTON |
| Green Building Final | 11/13/2023 | Approved | JEFFREY FULTON |
| Green Building Rough | 11/13/2023 | Approved | JEFFREY FULTON |
| Reinforced Concrete Frame | 11/13/2023 | Approved | JEFFREY FULTON |
| Reinforced Masonry Frame | 11/13/2023 | Approved | JEFFREY FULTON |