411 N ROSENELL TER 1-35 90026

Certificate Information: 411 N ROSENELL TER 1-35 90026

Application / Permit
17010-20003-00068
Plan Check / Job No.
B22VN02151
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SUPPLEMENTAL TO 17010-20000-00068 TO CHANGE THE ADDRESS & REVISE FLOOR PLAN AT ALL FLOORS TO REVISE GARAGE PLANS AND REVISE FLOOR PLANS ON 1ST, 2ND , 3RD & 4TH FLOORS TO SHOW 7 NEW RECREATION ROOMS PER DIR-2018-2887-TOC, ALL WORK PE ENGINEERING
Permit Issued
Issued on 5/16/2023
Issuing Office
Valley
Current Status
Permit Finaled on 4/6/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/11/2022 APPLICANT
Assigned to Plan Check Engineer 2/24/2022 RARES BODEA
Corrections Issued 2/28/2022 RARES BODEA
Quality Review Completed 3/3/2022 STEVEN KIM
Building Plans Picked Up 4/18/2022 APPLICANT
Disabled Access Plans Picked Up 4/18/2022 APPLICANT
Applicant returned to address corrections 8/29/2022 RARES BODEA
Plan Check Approved 4/14/2023 RARES BODEA
Issued 5/16/2023 APPLICANT
Permit Finaled 4/6/2026 RONALD JIMENEZ

Permit Application Clearance Information

"Q" conditions Cleared 9/13/2022 LOUIS ORTEGA
"T" removal Cleared 9/13/2022 LOUIS ORTEGA
Miscellaneous Cleared 9/13/2022 LOUIS ORTEGA
Miscellaneous Cleared 9/13/2022 LOUIS ORTEGA
Miscellaneous Cleared 9/13/2022 LOUIS ORTEGA
Miscellaneous Cleared 9/13/2022 LOUIS ORTEGA
ZA Case Cleared 9/13/2022 LOUIS ORTEGA
ZA Case Cleared 9/13/2022 LOUIS ORTEGA
ZA Case Cleared 9/13/2022 LOUIS ORTEGA
ZA Case Cleared 9/13/2022 LOUIS ORTEGA
Address approval Cleared 10/14/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 10/14/2022 CINDY QI
Hydrant and Access approval Cleared 11/8/2022 KURT CORRAL
DAS Clearance Cleared 12/1/2022 RARES BODEA
Fire Marshal Fire Life Safety Cleared 3/24/2023 ANDREW KO

Contact Information

Architect Hefner,, Charles David; Lic. No.: C23963 6320 VAN NUYS BOULEVARD #225      VAN NUYS, CA 91401
Contractor Owner-Builder       ,
Engineer Babayan,, Raffi Samuel; Lic. No.: C72168 7718 DAY STREET      LOS ANGELES, CA 91042
Engineer Dejban,, Masoud; Lic. No.: S2521 17200 VENTURA BLVD STE 213A      ENCINO, CA 91316

Inspector Information

RONALD JIMENEZ, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
LARRY ARNICK, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
JOEY BUCHANAN, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
ERNESTO CORRAL, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL ESPINOZA, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Drywall Nailing 6/27/2023 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 6/27/2023 Not Ready for Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 7/7/2023 Partial Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 7/20/2023 Partial Approval RAFAEL ESPINOZA
Piling/Pier/Caisson 7/20/2023 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 7/21/2023 Partial Approval RAFAEL ESPINOZA
Wood Frame 7/26/2023 Partial Approval LARRY ARNICK
Insulation 8/4/2023 Partial Approval LARRY ARNICK
Wood Frame 8/14/2023 Partial Approval RAFAEL ESPINOZA
Wood Frame 8/15/2023 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 8/16/2023 Partial Approval RAFAEL ESPINOZA
Wood Frame 8/18/2023 Not Ready for Inspection LARRY ARNICK
Wood Frame 8/24/2023 Partial Approval LARRY ARNICK
Insulation 8/30/2023 Partial Approval LARRY ARNICK
Insulation 8/31/2023 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 9/14/2023 Partial Approval RAFAEL ESPINOZA
Deputy Grading 10/12/2023 Conditional Approval LARRY ARNICK
Insulation 10/31/2023 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 11/6/2023 Partial Approval RAFAEL ESPINOZA
Deputy Shotcrete 11/17/2023 Conditional Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 11/17/2023 Partial Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 11/17/2023 Not Ready for Inspection RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 11/20/2023 Partial Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 11/20/2023 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 11/28/2023 Partial Approval RAFAEL ESPINOZA
Insulation 12/11/2023 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 12/13/2023 Approved RAFAEL ESPINOZA
Drywall Nailing 12/26/2023 Partial Approval LARRY ARNICK
Drywall Nailing 1/5/2024 Partial Approval RAFAEL ESPINOZA
Wall Anchors 1/5/2024 Approved RAFAEL ESPINOZA
Pre-Inspection 2/5/2025 Partial Inspection JEFFREY FULTON
Pre-Inspection 12/10/2025 Partial Approval LARRY ARNICK
Final 12/11/2025 Partial Inspection LARRY ARNICK
Smoke Detectors 12/11/2025 Partial Approval LARRY ARNICK
Pre-Inspection 12/12/2025 Partial Approval LARRY ARNICK
Final 12/16/2025 Partial Inspection JEFFREY FULTON
Smoke Detectors 12/16/2025 Partial Inspection JEFFREY FULTON
Special/Order Compliance 12/17/2025 Corrections Issued JEFFREY FULTON
Pre-Inspection 1/8/2026 Not Ready for Inspection JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 1/8/2026 SGSOV Approved JEFFREY FULTON
Pre-Inspection 1/9/2026 Corrections Issued JEFFREY FULTON
Final 2/5/2026 Corrections Issued RONALD JIMENEZ
Smoke Detectors 2/5/2026 Approved RONALD JIMENEZ
Pre-Inspection 2/11/2026 Not Ready for Inspection RONALD JIMENEZ
Special/Order Compliance 3/12/2026 Not Ready for Inspection RONALD JIMENEZ
Final 4/6/2026 Permit Finaled RONALD JIMENEZ