5328 N AMESTOY AVE 91316
Certificate Information: 5328 N AMESTOY AVE 91316
- Application / Permit
- 17010-20002-00998
- Plan Check / Job No.
- B21VN08028
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- SUPPLLEMENTAL TO 17010-20000-00998 TO REVISE SCOPE OF WORK TO NEW 36' X 32'10" ACCESSORY DWELLING UNIT AS PER GCS 65852.2(E)(1)(B) , NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT , ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 12/10/2021
- Issuing Office
- Current Status
- Permit Finaled on 10/12/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/15/2021 | RARES BODEA |
| Corrections Issued | 7/22/2021 | RARES BODEA |
| Quality Review Completed | 7/30/2021 | STEVEN KIM |
| Building Plans Picked Up | 8/3/2021 | APPLICANT |
| Plan Check Approved | 12/9/2021 | RARES BODEA |
| Issued | 12/10/2021 | APPLICANT |
| Permit Finaled | 10/12/2022 | SEAN HAUPT |
Permit Application Clearance Information
| Address approval | Cleared | 8/26/2021 | CARLOS AGUILERA |
| Tract Map conditions | Cleared | 8/27/2021 | LAUREN PADICK |
| Eng Process Fee Ord 176,300 | Cleared | 8/30/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 8/30/2021 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 10/21/2021 | KURT CORRAL |
| Low Impact Development | Cleared | 11/17/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 11/17/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 1/20/2022 | Approved | SEAN HAUPT |
| Underground Mechanical | 1/20/2022 | Partial Approval | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 2/1/2022 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 10/12/2022 | Approved | SEAN HAUPT |
| HVAC-Final | 10/12/2022 | Approved | SEAN HAUPT |
| PLUMBING-Final | 10/12/2022 | Approved | SEAN HAUPT |