8116 W LAUREL VIEW DR 90069
Certificate Information: 8116 W LAUREL VIEW DR 90069
- Application / Permit
- 17010-20002-00383
- Plan Check / Job No.
- B20VN05649
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SUPPLEMENTAL PERMIT FOR 17010-20000-00383 TO RENEW AT 0% COMPLETE
- Permit Issued
- Issued on 5/28/2020
- Issuing Office
- Current Status
- Permit Finaled on 7/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Plan Check Approved | 4/16/2020 | NILOOFAR MEHRAIN |
| Issued | 5/28/2020 | APPLICANT |
| Permit Finaled | 7/27/2023 | RAUL BARAJAS |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lieurance, Martin Ellis; Lic. No.: C54323 | 31129 VIA COLINAS 707 WESTLAKE VILLAGE, CA 91362 |
| Engineer | Nazari, Arthur; Lic. No.: C53497 | PO BOX 7112 NORTHRIDGE, CA 91327 |
| Geologist | Lieurance, Martin Ellis; Lic. No.: EG1810 | GROVER-HOLLINGSWORTH & ASSOCIATE 31129 VIA COLINAS STE 707 WESTLAKE VILLAGE, CA 91362 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/31/2020 | Corrections Issued | RAUL BARAJAS |
| Footing/Foundation/Slab | 9/11/2020 | Partial Approval | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 9/25/2020 | Partial Approval | RAUL BARAJAS |
| Reinforced Concrete Frame | 10/13/2020 | Partial Approval | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 11/2/2020 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 11/2/2020 | Partial Approval | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 11/13/2020 | Partial Approval | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 11/16/2020 | Partial Approval | RAUL BARAJAS |
| ELECTRICAL-Rough | 12/24/2020 | Partial Approval | RAUL BARAJAS |
| PLUMBING-Rough | 12/24/2020 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 12/29/2020 | Partial Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 12/30/2020 | Conditional Approval | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 1/8/2021 | Partial Approval | RAUL BARAJAS |
| Reinforced Masonry Frame | 1/8/2021 | Partial Approval | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 1/15/2021 | Partial Approval | RAUL BARAJAS |
| Masonry Wall/Backfill | 1/15/2021 | Approved | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 1/27/2021 | Partial Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 2/2/2021 | Partial Approval | RAUL BARAJAS |
| Grounding or Bonding | 2/2/2021 | Approved | RAUL BARAJAS |
| Wood Frame | 3/23/2021 | Partial Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 4/27/2021 | Corrections Issued | RAUL BARAJAS |
| Structural Steel Frame | 4/27/2021 | Partial Inspection | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 5/18/2021 | Corrections Issued | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2021 | Conditional Approval | RAUL BARAJAS |
| ELECTRICAL-Rough | 7/29/2021 | Partial Inspection | RAUL BARAJAS |
| HVAC-Rough | 7/29/2021 | Partial Inspection | RAUL BARAJAS |
| PLUMBING-Rough | 7/29/2021 | Not Ready for Inspection | RAUL BARAJAS |
| BUILDING-Rough-Frame | 9/24/2021 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Rough | 9/24/2021 | Partial Approval | SCOTT FINNILA |
| HVAC-Rough | 9/24/2021 | Corrections Issued | SCOTT FINNILA |
| PLUMBING-Rough | 9/24/2021 | Corrections Issued | SCOTT FINNILA |
| Rough-Elec/Plmb/HVAC | 9/24/2021 | Corrections Issued | SCOTT FINNILA |
| ELECTRICAL-Rough | 9/27/2021 | Corrections Issued | RAUL BARAJAS |
| HVAC-Rough | 9/27/2021 | Partial Approval | RAUL BARAJAS |
| PLUMBING-Rough | 9/27/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Deputy Wood Construction | 12/16/2021 | Conditional Approval | RAUL BARAJAS |
| Deputy Wood Construction | 12/20/2021 | Conditional Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2021 | Partial Approval | RAUL BARAJAS |
| Deputy Wood Construction | 12/27/2021 | Conditional Approval | RAUL BARAJAS |