100 S ALTA VISTA BLVD 90036
Certificate Information: 100 S ALTA VISTA BLVD 90036
- Application / Permit
- 17010-20002-00075
- Plan Check / Job No.
- B17VN00341
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- NEW 20'-0"X20'-0" DETACHED GARAGE PER ENGINEERING.
- Permit Issued
- Issued on 7/6/2018
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 3/10/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/10/2017 | APPLICANT |
| Green Plans Picked Up | 2/28/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 3/2/2017 | JOHNNY WU |
| Corrections Issued | 3/10/2017 | JOHNNY WU |
| Quality Review Completed | 3/16/2017 | GUANG MIN TUNG |
| Building Plans Picked Up | 3/16/2017 | APPLICANT |
| Applicant returned to address corrections | 4/6/2018 | JOHNNY WU |
| Applicant returned to address corrections | 6/19/2018 | JOHNNY WU |
| Applicant returned to address corrections | 6/22/2018 | JOHNNY WU |
| Plan Check Approved | 7/6/2018 | JOHNNY WU |
| Issued | 7/6/2018 | LADBS |
| Permit Finaled | 3/9/2021 | CHRIS CHRISTENSEN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/19/2018 | EDUARDO PEDROZA |
| Permit | Cleared | 6/19/2018 | EDUARDO PEDROZA |
| Roof/Waste drainage to street | Cleared | 6/19/2018 | EDUARDO PEDROZA |
| ZA Case | Cleared | 6/19/2018 | DAISY BENICIA |
| Construction near power lines | Cleared | 6/20/2018 | WALTER RAMIREZ |
| Construction within easement | Cleared | 6/20/2018 | WALTER RAMIREZ |
| HPOZ | Cleared | 7/2/2018 | MICAELA TORRES-GIL |
| Miscellaneous | Cleared | 7/2/2018 | MICAELA TORRES-GIL |
Contact Information
| Architect | Woodcraft, Lawrence Albert; Lic. No.: C23651 | 20242 ELKWOOD STREET WINNETKA, CA 91306 |
| Contractor | Mirage Construction Inc; Lic. No.: 771100-B | 7162 BEVERLY BLVD # 102 LOS ANGELES, CA 90036 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/25/2019 | Approved | JOSEPH MCGARRY |
| METHANE-Barrier | 9/25/2019 | Approved | JOSEPH MCGARRY |
| METHANE-Subgrade | 9/25/2019 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 3/9/2021 | Approved | CHRIS CHRISTENSEN |
| Final | 3/9/2021 | Permit Finaled | CHRIS CHRISTENSEN |
| Green Building Final | 3/9/2021 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 3/9/2021 | Approved | CHRIS CHRISTENSEN |
| METHANE-Final | 3/9/2021 | Approved | CHRIS CHRISTENSEN |
| METHANE-Rough | 3/9/2021 | Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 3/9/2021 | Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 3/9/2021 | Approved | CHRIS CHRISTENSEN |