900 N VISTA ST 90046
Certificate Information: 900 N VISTA ST 90046
- Application / Permit
- 17010-20001-00245
- Plan Check / Job No.
- B18VN08067
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Suppl. permit to revsie work description to read "New irregular shape 73'11" x 30'9" NFPA13-D sprinkle throughout 2-story dwelling with attached garage, trellises and 1 level basement (including shoring on East and West side"
- Permit Issued
- Issued on 8/27/2018
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/20/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/11/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 5/31/2018 | ALDOUS CHIC |
| Corrections Issued | 6/4/2018 | ALDOUS CHIC |
| Quality Review Completed | 6/7/2018 | CHON CHIO KUO |
| Building Plans Picked Up | 6/12/2018 | APPLICANT |
| Green Plans Picked Up | 6/12/2018 | APPLICANT |
| Applicant returned to address corrections | 6/20/2018 | ALDOUS CHIC |
| Applicant returned to address corrections | 7/10/2018 | ALDOUS CHIC |
| Plan Check Approved | 7/17/2018 | ALDOUS CHIC |
| Issued | 8/27/2018 | LADBS |
| CofO in Progress | 5/9/2024 | AMIR NAZARIAN |
| Permit Finaled | 5/20/2024 | DEROLD HAUFF |
| CofO Issued | 5/20/2024 | DEROLD HAUFF |
| Permit Finaled | 5/20/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 7/5/2018 | PARISA ZAHABI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | , ; Lic. No.: C21234 | 22129 BRYANT STREET CANOGA PARK, CA 91304 |
| Engineer | Hollingsworth, Robert Alan; Lic. No.: GE2022 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Grading | 11/16/2018 | Approved | ROBERT MINASSIANS |
| Deputy Grading | 11/19/2018 | Corrections Issued | DANNY TOLENTINO |
| Deputy Grading | 11/20/2018 | Conditional Approval | DANNY TOLENTINO |
| Deputy Grading | 11/21/2018 | Conditional Approval | DANNY TOLENTINO |
| Deputy Grading | 11/27/2018 | No Access for Inspection | DANNY TOLENTINO |
| Deputy Grading | 11/28/2018 | Conditional Approval | DANNY TOLENTINO |
| Footing/Foundation/Slab | 5/28/2019 | No Access for Inspection | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 5/31/2019 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 6/28/2019 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 6/28/2019 | Partial Approval | JOSEPH MCGARRY |
| Reinforced Concrete Frame | 8/5/2019 | Partial Inspection | JOSEPH MCGARRY |
| Reinforced Masonry Frame | 8/5/2019 | Partial Inspection | JOSEPH MCGARRY |
| Reinforced Concrete Frame | 8/12/2019 | Not Ready for Inspection | JOSEPH MCGARRY |
| Reinforced Masonry Frame | 8/12/2019 | Not Ready for Inspection | JOSEPH MCGARRY |
| Reinforced Concrete Frame | 8/20/2019 | Not Ready for Inspection | JOSEPH MCGARRY |
| Reinforced Masonry Frame | 8/20/2019 | Not Ready for Inspection | JOSEPH MCGARRY |
| Reinforced Concrete Frame | 8/26/2019 | Partial Approval | JOSEPH MCGARRY |
| Reinforced Masonry Frame | 8/26/2019 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2019 | Partial Approval | JOSEPH MCGARRY |
| Deputy Steel/Welding | 10/17/2019 | Partial Approval | PIERRE VEGA |
| Deputy Steel/Welding | 10/18/2019 | Partial Approval | PIERRE VEGA |
| Floor/Roof Diaphrgm/Shear Wall | 11/27/2019 | No Access for Inspection | JOSEPH MCGARRY |
| Wood Frame | 1/30/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2020 | No Access for Inspection | RAUL BARAJAS |
| BUILDING-Rough-Frame | 3/20/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Green Building Rough | 3/20/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Special/Order Compliance | 3/20/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 3/20/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2020 | Partial Approval | JOSEPH MCGARRY |
| Pre-Inspection | 4/29/2020 | Partial Inspection | CHRIS CHRISTENSEN |
| Deputy Drilled-In Anchors | 7/8/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| Pre-Inspection | 7/21/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Deputy Drilled-In Anchors | 9/8/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 1/11/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 1/11/2021 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 6/8/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 6/8/2021 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 6/8/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Rough | 6/8/2021 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 6/8/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 6/8/2021 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 9/13/2021 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 9/13/2021 | Approved | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 9/13/2021 | Approved | CHRIS CHRISTENSEN |
| Insulation | 10/28/2021 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 11/16/2021 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 11/16/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Shower Pan | 3/22/2022 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 3/29/2022 | Approved | ALIZAH MAYAGOITIA |
| Gas Test | 6/16/2022 | Approved | ADAM ESCOTO |
| Service/Power Release | 6/16/2022 | Not Ready for Inspection | ADAM ESCOTO |
| Gas Test | 10/4/2022 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 10/27/2022 | Partial Inspection | MICHAEL LEWIS |
| Final | 10/27/2022 | Partial Inspection | MICHAEL LEWIS |
| Footing/Foundation/Slab | 10/27/2022 | Approved | MICHAEL LEWIS |
| Green Building Final | 10/27/2022 | Approved | MICHAEL LEWIS |
| HVAC-Final | 10/27/2022 | Conditional Approval | MICHAEL LEWIS |
| PLUMBING-Final | 10/27/2022 | Conditional Approval | MICHAEL LEWIS |
| Service/Power Release | 10/27/2022 | Partial Inspection | MICHAEL LEWIS |
| Smoke Detectors | 10/27/2022 | Approved | MICHAEL LEWIS |
| PLUMBING-Final | 10/31/2022 | Approved | MICHAEL LEWIS |
| Pre-Inspection | 5/15/2023 | Partial Inspection | LILIANA PORTILLO |
| ELECTRICAL-Final | 5/30/2023 | Approved | LILIANA PORTILLO |
| Service/Power Release | 5/30/2023 | Approved | LILIANA PORTILLO |
| HVAC-Final | 4/4/2024 | Corrections Issued | AMIR NAZARIAN |
| HVAC-Final | 4/17/2024 | Corrections Issued | AMIR NAZARIAN |
| HVAC-Final | 4/24/2024 | Approved | AMIR NAZARIAN |
| Final | 5/1/2024 | Corrections Issued | AMIR NAZARIAN |
| Final | 5/8/2024 | OK to Issue CofO | AMIR NAZARIAN |