443 W AVENUE 37 90065

Certificate Information: 443 W AVENUE 37 90065

Application / Permit
17010-20000-05198
Plan Check / Job No.
B17VN20030
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 1-STORY W/ BASEMENT ACCESSORY DWELLING UNIT W/ ATTACHED 1-CAR GARAGE (IN BASEMENT) & PATIO. FIRE SPRINKLERS REQ'D THROUGH-OUT. [PER DIR-2018-6459-SPP; SEE COMMENTS]
Permit Issued
Issued on 12/31/2020
Issuing Office
Current Status
CofO Issued on 11/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/29/2017 APPLICANT
Green Plans Picked Up 1/31/2018 APPLICANT
Assigned to Plan Check Engineer 2/1/2018 ALEXANDER SBARDELLATI
Corrections Issued 2/7/2018 ALEXANDER SBARDELLATI
Re-Submittal Required 2/7/2018 DOUGLAS NAKATANI
Building Plans Picked Up 2/9/2018 APPLICANT
Re-Submitted 1/11/2019 ALEXANDER SBARDELLATI
Review in Progress 2 1/11/2019 ALEXANDER SBARDELLATI
Review in Progress 2 1/25/2019 ALEXANDER SBARDELLATI
Review in Progress 2 2/7/2019 ALEXANDER SBARDELLATI
Corrections Issued 2 2/20/2019 ALEXANDER SBARDELLATI
Submitted for Second Quality Review 2/20/2019 ALEXANDER SBARDELLATI
Quality Review Completed 2/20/2019 STEVEN KIM
Applicant returned to address corrections 6/25/2020 RODNEY SAMIIAN
Applicant returned to address corrections 6/30/2020 RODNEY SAMIIAN
Applicant returned to address corrections 8/12/2020 RODNEY SAMIIAN
Plan Check Approved 8/24/2020 RODNEY SAMIIAN
Issued 12/31/2020 APPLICANT
CofO in Progress 10/24/2024 OSVALDO PARAMO
CofO Issued 11/1/2024 DEROLD HAUFF
Permit Finaled 11/1/2024 DEROLD HAUFF

Permit Application Clearance Information

GPI Written Notices Cleared 2/5/2018 ALEXANDER SBARDELLATI
Grading Pre-Inspection Cleared 2/5/2018 ALEXANDER SBARDELLATI
Address approval Cleared 7/26/2018 KENNETH PHAM
BHO/Hillside ordinance Cleared 7/26/2018 KENNETH PHAM
BHO/Hillside ordinance Cleared 7/26/2018 KENNETH PHAM
Eng Process Fee Ord 176,300 Cleared 7/26/2018 KENNETH PHAM
Permit Cleared 7/26/2018 KENNETH PHAM
Sewer availability Cleared 7/26/2018 KENNETH PHAM
BHO/Hillside ordinance Cleared 9/13/2018 KARAN PATEL
Miscellaneous Cleared 10/25/2018 ALEXANDER SBARDELLATI
Low Impact Development Cleared 2/27/2019 MITESH PATEL
Specific Plan Cleared 3/12/2020 NASHYA JENSEN
Green Code Cleared 7/15/2020 ALEXANDER SBARDELLATI
Roof/Waste drainage to street Cleared 7/23/2020 JEANIE LAM
Distance to fire station Cleared 8/3/2020 MATTHEW CRAIG
Hydrant and Access approval Cleared 8/3/2020 MATTHEW CRAIG
Excavation more than 5-ft deep Cleared 8/13/2020 CALOSHA APPROVED
Miscellaneous Cleared 8/20/2020 SARAHI ORTEGA

Contact Information

Contractor Owner-Builder       ,
Engineer Koh, Timothy Wei-Mann; Lic. No.: L8669 18024 MARTHA PL      CERRITOS, CA 90703
Engineer Minas, Shant; Lic. No.: CEG2607       GLENDALE, CA 91204
Engineer Rahman, Moksudur; Lic. No.: C69263 6939 SCHAEFER AVE   #D-170    CHINO, CA 91710
Geologist Minas, Caro Jolfaie; Lic. No.: GEO601       GLENDALE, CA 91204

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 7/19/2021 Not Ready for Inspection OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 7/21/2021 Corrections Issued OSVALDO PARAMO
Piling/Pier/Caisson 7/21/2021 Not Ready for Inspection OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 7/23/2021 Partial Approval COREY HUPP
Piling/Pier/Caisson 7/23/2021 Partial Approval COREY HUPP
Piling/Pier/Caisson 9/3/2021 Approved OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 11/12/2021 Partial Approval OSVALDO PARAMO
Deputy Reinf. Concrete 11/16/2021 Conditional Approval LILIANA PORTILLO
Footing/Foundation/Slab 11/17/2021 Partial Approval OSVALDO PARAMO
Deputy Reinf. Concrete 11/19/2021 Conditional Approval OSVALDO PARAMO
Footing/Foundation/Slab 11/29/2021 Partial Approval OSVALDO PARAMO
Deputy Reinf. Concrete 11/30/2021 Conditional Approval OSVALDO PARAMO
Footing/Foundation/Slab 12/3/2021 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 12/15/2021 Not Ready for Inspection OSVALDO PARAMO
Footing/Foundation/Slab 12/20/2021 Partial Approval OSVALDO PARAMO
Deputy Reinf. Concrete 12/22/2021 Conditional Approval OSVALDO PARAMO
Piling/Pier/Caisson 1/4/2022 Not Ready for Inspection SHAVONNE ESPINOZA
Deputy Drilled-In Anchors 1/10/2022 Conditional Approval OSVALDO PARAMO
PLUMBING-Rough 1/11/2022 Partial Approval OSVALDO PARAMO
Deputy Drilled-In Anchors 1/13/2022 Conditional Approval OSVALDO PARAMO
Deputy Drilled-In Anchors 1/14/2022 Conditional Approval OSVALDO PARAMO
Footing/Foundation/Slab 1/18/2022 Partial Approval OSVALDO PARAMO
Deputy Reinf. Concrete 1/19/2022 Conditional Approval OSVALDO PARAMO
Footing/Foundation/Slab 1/25/2022 Partial Approval OSVALDO PARAMO
Underground Mechanical 3/7/2022 Not Ready for Inspection OSVALDO PARAMO
Footing/Foundation/Slab 3/11/2022 Partial Inspection OSVALDO PARAMO
Deputy Reinf. Concrete 3/17/2022 Conditional Approval OSVALDO PARAMO
Pre-Inspection 3/30/2022 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 4/19/2022 Partial Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 6/29/2022 Approved OSVALDO PARAMO
Footing/Foundation/Slab 6/29/2022 Partial Approval OSVALDO PARAMO
Deputy Reinf. Concrete 6/30/2022 Conditional Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 7/21/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 7/29/2022 Approved OSVALDO PARAMO
Reinforced Concrete Frame 7/29/2022 Approved OSVALDO PARAMO
Footing/Foundation/Slab 8/18/2022 Partial Approval OSVALDO PARAMO
PLUMBING-Rough 8/18/2022 Not Ready for Inspection OSVALDO PARAMO
Sewer 8/18/2022 Approved OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 8/29/2022 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 8/29/2022 Partial Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 9/16/2022 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 9/16/2022 Partial Approval OSVALDO PARAMO
ELECTRICAL-Rough 9/21/2022 Corrections Issued OSVALDO PARAMO
HVAC-Rough 9/21/2022 Approved OSVALDO PARAMO
Deputy Wood Construction 11/1/2022 Conditional Approval OSVALDO PARAMO
ELECTRICAL-Rough 11/4/2022 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 11/4/2022 Approved OSVALDO PARAMO
PLUMBING-Rough 11/4/2022 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 11/14/2022 Corrections Issued ALIZAH MAYAGOITIA
Green Building Rough 11/14/2022 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 11/14/2022 Partial Approval ALIZAH MAYAGOITIA
Shower Pan 11/14/2022 Approved ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 11/14/2022 Approved ALIZAH MAYAGOITIA
Insulation 11/21/2022 Approved OSVALDO PARAMO
Drywall Nailing 11/30/2022 Approved OSVALDO PARAMO
Interior/Exterior Lathing 12/7/2022 Approved OSVALDO PARAMO
ELECTRICAL-Final 4/10/2024 Corrections Issued OSVALDO PARAMO
Service/Power Release 4/10/2024 Not Ready for Inspection OSVALDO PARAMO
Verify Rec and Parks Fee Memo 4/12/2024 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 9/16/2024 Approved OSVALDO PARAMO
Final 9/16/2024 Corrections Issued OSVALDO PARAMO
Footing/Foundation/Slab 9/16/2024 Approved OSVALDO PARAMO
Green Building Final 9/16/2024 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 9/16/2024 SGSOV Not Ready OSVALDO PARAMO
Service/Power Release 9/16/2024 Approved OSVALDO PARAMO
Smoke Detectors 9/16/2024 Approved OSVALDO PARAMO
Final 10/23/2024 OK to Issue CofO OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 10/23/2024 SGSOV Approved OSVALDO PARAMO