Excavation/Setback/Form/Re-Bar
|
4/7/2021
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
4/7/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Excavation/Setback/Form/Re-Bar
|
4/22/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
4/22/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Excavation/Setback/Form/Re-Bar
|
4/27/2021
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
4/27/2021
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Pre-Stress Concrete
|
5/3/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/13/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
5/13/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Verify Sprinkler Sign Off
|
5/13/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/18/2021
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
5/18/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Verify Sprinkler Sign Off
|
5/18/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/28/2021
|
Partial Inspection
|
DAVID BURKHEAD
|
|
Green Building Rough
|
5/28/2021
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Verify Sprinkler Sign Off
|
5/28/2021
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/17/2021
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Green Building Rough
|
8/17/2021
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Insulation
|
8/17/2021
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Verify Sprinkler Sign Off
|
8/17/2021
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Wood Frame
|
8/17/2021
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/23/2021
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
8/23/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Insulation
|
8/23/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Verify Sprinkler Sign Off
|
8/23/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Wood Frame
|
8/23/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/3/2021
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
9/3/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Insulation
|
9/3/2021
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Verify Sprinkler Sign Off
|
9/3/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Wood Frame
|
9/3/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Interior/Exterior Lathing
|
9/22/2021
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
9/23/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Verify Sprinkler Sign Off
|
9/23/2021
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Wood Frame
|
9/23/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
1/3/2022
|
Approved
|
DANNY RODRIGUEZ
|
|
Verify Sprinkler Sign Off
|
1/3/2022
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Wood Frame
|
1/3/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Insulation
|
1/11/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Verify Sprinkler Sign Off
|
1/11/2022
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Wood Frame
|
1/11/2022
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Insulation
|
2/1/2022
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Drywall Nailing
|
2/3/2022
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Insulation
|
2/4/2022
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Drywall Nailing
|
2/8/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Drywall Nailing
|
2/17/2022
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Verify Sprinkler Sign Off
|
2/25/2022
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Drywall Nailing
|
3/29/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Drywall Nailing
|
3/30/2022
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Drywall Nailing
|
4/1/2022
|
Approved
|
DANNY RODRIGUEZ
|
|
Special/Order Compliance
|
6/16/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Pre-Inspection
|
10/5/2022
|
Approved
|
DANNY RODRIGUEZ
|
|
Final
|
10/25/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
10/25/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Green Building Final
|
10/25/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
SGSOV-Seismic Gas S/O Valve
|
10/25/2022
|
SGSOV Not Ready
|
DANNY RODRIGUEZ
|
|
Smoke Detectors
|
10/25/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Verify Sprinkler Sign Off
|
10/25/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Wood Frame
|
10/25/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Pre-Inspection
|
10/28/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Pre-Inspection
|
10/31/2022
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Final
|
12/16/2022
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
12/16/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Green Building Final
|
12/16/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
SGSOV-Seismic Gas S/O Valve
|
12/16/2022
|
SGSOV Approved
|
DANNY RODRIGUEZ
|
|
Smoke Detectors
|
12/16/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Verify Sprinkler Sign Off
|
12/16/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Wood Frame
|
12/16/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Final
|
12/23/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
12/23/2022
|
Approved
|
DANNY RODRIGUEZ
|
|
Green Building Final
|
12/23/2022
|
Approved
|
DANNY RODRIGUEZ
|
|
Smoke Detectors
|
12/23/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Verify Sprinkler Sign Off
|
12/23/2022
|
Approved
|
DANNY RODRIGUEZ
|
|
Wood Frame
|
12/23/2022
|
Approved
|
DANNY RODRIGUEZ
|
|
Pre-Inspection
|
12/28/2022
|
Partial Inspection
|
ANDREW DORSO
|
|
Final
|
12/29/2022
|
OK to Issue CofO
|
ANDREW DORSO
|
|
Smoke Detectors
|
12/29/2022
|
Approved
|
ANDREW DORSO
|