1809 S STEARNS DR 90035

Certificate Information: 1809 S STEARNS DR 90035

Application / Permit
17010-20000-05152
Plan Check / Job No.
B17VN19900
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
(N) 2 CAR GARAGE.
Permit Issued
Issued on 7/3/2018
Issuing Office
Valley
Current Status
CofO Issued on 5/19/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/28/2017 APPLICANT
Green Plans Picked Up 1/23/2018 APPLICANT
Assigned to Plan Check Engineer 1/25/2018 RODNEY SAMIIAN
Corrections Issued 2/8/2018 RODNEY SAMIIAN
Quality Review Completed 2/8/2018 ABDUL CHEGENI
Building Plans Picked Up 2/12/2018 APPLICANT
Applicant returned to address corrections 5/17/2018 RODNEY SAMIIAN
Applicant returned to address corrections 5/30/2018 RODNEY SAMIIAN
Plan Check Approved 6/20/2018 RODNEY SAMIIAN
Issued 7/3/2018 LADBS
CofO in Progress 5/12/2021 MICHAEL FAUNCE
Permit Finaled 5/19/2021 DEROLD HAUFF
CofO Issued 5/19/2021 DEROLD HAUFF
Permit Finaled 5/19/2021 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development Cleared 6/14/2018 MARTIN FRAGOSO
Eng Process Fee Ord 176,300 Cleared 6/21/2018 JOSEPH RHYU
Roof/Waste drainage to street Cleared 6/21/2018 JOSEPH RHYU

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/29/2019 Approved KATHRYN BUTTERWORTH
Footing/Foundation/Slab 3/29/2019 Approved KATHRYN BUTTERWORTH
Wood Frame 4/16/2019 Not Ready for Inspection KATHRYN BUTTERWORTH
ELECTRICAL-Rough 12/7/2020 Approved DAVID CHAN
Underground Mechanical 12/7/2020 Approved DAVID CHAN
BUILDING-Rough-Frame 12/15/2020 Corrections Issued DAVID CHAN
ELECTRICAL-Rough 12/15/2020 Approved DAVID CHAN
Green Building Rough 12/15/2020 Approved DAVID CHAN
BUILDING-Rough-Frame 2/9/2021 Corrections Issued STUART CHAPMAN
ELECTRICAL-Rough 2/9/2021 Approved STUART CHAPMAN
Insulation 2/17/2021 Not Ready for Inspection DAVID FEILER
BUILDING-Rough-Frame 3/1/2021 Approved STUART CHAPMAN
Insulation 3/1/2021 Approved STUART CHAPMAN
Interior/Exterior Lathing 3/1/2021 Approved STUART CHAPMAN
Drywall Nailing 3/11/2021 Approved JOSEPH MCGARRY
ELECTRICAL-Final 3/30/2021 Not Ready for Inspection STUART CHAPMAN
Final 3/30/2021 Corrections Issued STUART CHAPMAN
Green Building Final 3/30/2021 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 3/30/2021 SGSOV Approved STUART CHAPMAN
Service/Power Release 3/30/2021 Not Ready for Inspection STUART CHAPMAN
Smoke Detectors 3/30/2021 Not Ready for Inspection STUART CHAPMAN
Final 5/3/2021 Partial Inspection SCOTT FINNILA
Gas Test 5/3/2021 Approved SCOTT FINNILA
Service/Power Release 5/3/2021 Partial Inspection SCOTT FINNILA
Smoke Detectors 5/3/2021 Approved SCOTT FINNILA
ELECTRICAL-Final 5/12/2021 Approved SCOTT FINNILA
Final 5/12/2021 OK to Issue CofO MICHAEL FAUNCE
Service/Power Release 5/12/2021 Approved MICHAEL FAUNCE