4712 N VANTAGE AVE Lot 6 91607
Certificate Information: 4712 N VANTAGE AVE Lot 6 91607
- Application / Permit
- 17010-20000-05086
- Plan Check / Job No.
- B17VN19686
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- "Small lot subdivision pursuant to Tentative Tract No./Preliminary Parcel Map No. VTT-74012-SL. A certificate of occupancy (temporary or final) shall not be issued until after the final map has been recorded. NEW 19'-9" x 46'-8" THREE STORY SFD WITH ATTACHED 3 CAR GARAGE. (FIRE SPRINKLER REQUIRED)
- Permit Issued
- Issued on 2/22/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/26/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/26/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 1/25/2018 | ARTIN ZARUKIAN |
| Green Plans Picked Up | 1/30/2018 | APPLICANT |
| Corrections Issued | 2/16/2018 | ARTIN ZARUKIAN |
| Quality Review Completed | 2/23/2018 | CHON CHIO KUO |
| Building Plans Picked Up | 2/27/2018 | APPLICANT |
| Applicant returned to address corrections | 4/23/2018 | ARTIN ZARUKIAN |
| Applicant returned to address corrections | 5/3/2018 | ARTIN ZARUKIAN |
| Applicant returned to address corrections | 6/25/2018 | ARTIN ZARUKIAN |
| Plan Check Approved | 9/3/2018 | ARTIN ZARUKIAN |
| Issued | 2/22/2019 | LADBS |
| CofO in Progress | 8/24/2021 | JOSEPH SAGEN |
| CofO Issued | 8/26/2021 | MICHAEL SMITH |
| Permit Finaled | 8/26/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 3/16/2018 | JOHN DALLAS |
| Green Code | Cleared | 4/24/2018 | ARTIN ZARUKIAN |
| Miscellaneous | Cleared | 5/11/2018 | STEVEN WECHSLER |
| Specific Plan | Cleared | 5/11/2018 | STEVEN WECHSLER |
| Tract Map conditions | Cleared | 5/11/2018 | STEVEN WECHSLER |
| ZI | Cleared | 5/11/2018 | STEVEN WECHSLER |
| Low Impact Development | Cleared | 7/13/2018 | RYAN HUDSON |
| Address approval | Cleared | 8/14/2018 | RUDY TERRIQUEZ. |
| Eng Process Fee Ord 176,300 | Cleared | 8/14/2018 | RUDY TERRIQUEZ. |
| Miscellaneous | Cleared | 8/14/2018 | RUDY TERRIQUEZ. |
| Permit | Cleared | 8/14/2018 | RUDY TERRIQUEZ. |
| Roof/Waste drainage to street | Cleared | 8/14/2018 | RUDY TERRIQUEZ. |
| Sewer availability | Cleared | 8/14/2018 | RUDY TERRIQUEZ. |
Contact Information
| Contractor | Sma Builders Inc; Lic. No.: 457725-B | 16134 LEADWELL ST VAN NUYS, CA 91406 |
| Engineer | Fischer, Kurt Mark; Lic. No.: S5432 | PO BOX 809 POWAY, CA 92074 |
| Engineer | Smith, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
Inspector Information
| JOSEPH SAGEN, (818) 774-4353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 5/22/2019 | Approved | DONALD SUNSERI |
| Footing/Foundation/Slab | 5/22/2019 | Partial Approval | DONALD SUNSERI |
| Footing/Foundation/Slab | 6/3/2019 | Not Ready for Inspection | DONALD SUNSERI |
| Footing/Foundation/Slab | 6/10/2019 | Partial Approval | JOHN KIDWELL |
| Underground Mechanical | 6/26/2019 | Approved | DONALD SUNSERI |
| Footing/Foundation/Slab | 9/4/2019 | Partial Approval | JOSEPH SAGEN |
| Footing/Foundation/Slab | 9/20/2019 | Approved | JOSEPH SAGEN |
| Underground Mechanical | 12/2/2019 | Approved | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2020 | Partial Approval | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2020 | Partial Approval | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 2/21/2020 | Partial Approval | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2020 | Partial Approval | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 3/23/2020 | Partial Approval | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2020 | Partial Approval | JOSEPH SAGEN |
| Structural Steel Frame | 5/5/2020 | Approved | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 5/18/2020 | Partial Approval | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2020 | Partial Approval | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 6/8/2020 | Partial Approval | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2020 | Partial Approval | JOSEPH SAGEN |
| PLUMBING-Rough | 7/22/2020 | Not Ready for Inspection | JOSEPH SAGEN |
| HVAC-Rough | 7/28/2020 | Not Ready for Inspection | JOSEPH SAGEN |
| PLUMBING-Rough | 7/28/2020 | Partial Approval | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 8/3/2020 | Partial Approval | JOSEPH SAGEN |
| Insulation | 8/6/2020 | Partial Approval | JOSEPH SAGEN |
| Shower Pan | 8/20/2020 | Approved | JOSEPH SAGEN |
| ELECTRICAL-Rough | 8/25/2020 | Approved | JOSEPH SAGEN |
| HVAC-Rough | 8/25/2020 | Approved | JOSEPH SAGEN |
| PLUMBING-Rough | 8/25/2020 | Approved | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2020 | Partial Approval | JOSEPH SAGEN |
| BUILDING-Rough-Frame | 9/8/2020 | Not Ready for Inspection | DONALD SUNSERI |
| Green Building Rough | 9/8/2020 | Approved | DONALD SUNSERI |
| MERV13>=Rough | 9/8/2020 | Approved | DONALD SUNSERI |
| Verify Sprinkler Sign Off | 9/8/2020 | Not Ready for Inspection | DONALD SUNSERI |
| BUILDING-Rough-Frame | 9/10/2020 | Approved | SEAN WIRCH |
| Verify Sprinkler Sign Off | 9/10/2020 | Approved | SEAN WIRCH |
| Drywall Nailing | 9/22/2020 | Approved | JOSEPH SAGEN |
| Interior/Exterior Lathing | 10/2/2020 | Partial Approval | JOSEPH SAGEN |
| Interior/Exterior Lathing | 11/13/2020 | Approved | JOSEPH SAGEN |
| Gas Test | 3/3/2021 | Approved | JOSEPH SAGEN |
| Underground Mechanical | 3/4/2021 | Partial Approval | JOSEPH SAGEN |
| Service/Power Release | 5/7/2021 | Approved | JOSEPH SAGEN |
| SGSOV-Seismic Gas S/O Valve | 5/12/2021 | SGSOV Approved | JOSEPH SAGEN |
| Pre-Inspection | 6/21/2021 | Approved | JOSEPH SAGEN |
| ELECTRICAL-Final | 7/15/2021 | Approved | JOSEPH SAGEN |
| HVAC-Final | 7/15/2021 | Approved | JOSEPH SAGEN |
| PLUMBING-Final | 7/15/2021 | Approved | JOSEPH SAGEN |
| Final | 8/23/2021 | OK to Issue CofO | JOSEPH SAGEN |
| Green Building Final | 8/23/2021 | Approved | JOSEPH SAGEN |
| MERV13>=Final | 8/23/2021 | Approved | JOSEPH SAGEN |
| Smoke Detectors | 8/23/2021 | Approved | JOSEPH SAGEN |