1395 N DOHENY DR 90069

Certificate Information: 1395 N DOHENY DR 90069

Application / Permit
17010-20000-05039
Plan Check / Job No.
B17VN19653
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW (58' X 115'-8") IRREGULAR SHAPED 2-STORY OVER BASEMENT SFD W/ 3-CAR ATTACHED GARAGE AND TRELLIS PATIO COVER PER ENGINEERING. NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 3/10/2022
Issuing Office
Current Status
CofO Issued on 3/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/22/2017 APPLICANT
Assigned to Plan Check Engineer 1/25/2018 RAPHAEL ROSAS
Green Plans Picked Up 1/25/2018 APPLICANT
Corrections Issued 1/31/2018 RAPHAEL ROSAS
Quality Review Completed 2/5/2018 STEVEN KIM
Applicant returned to address corrections 4/3/2018 RAPHAEL ROSAS
Applicant returned to address corrections 6/20/2018 RAPHAEL ROSAS
Applicant returned to address corrections 9/4/2018 RAPHAEL ROSAS
Applicant returned to address corrections 11/18/2019 RAPHAEL ROSAS
Applicant returned to address corrections 2/11/2020 RAPHAEL ROSAS
Plan Check Approved 2/17/2022 RAPHAEL ROSAS
Building Plans Picked Up 2/18/2022 APPLICANT
Issued 3/10/2022 APPLICANT
CofO in Progress 3/27/2025 RAUL BARAJAS
Permit Finaled 3/29/2025 DEROLD HAUFF
Permit Finaled 3/29/2025 DEROLD HAUFF
CofO Issued 3/29/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/15/2018 KAYLA PEJI
BHO/Hillside ordinance Cleared 3/15/2018 KAYLA PEJI
Permit Cleared 3/15/2018 KAYLA PEJI
CPC Cleared 3/20/2018 STEVEN WECHSLER
Eng Process Fee Ord 176,300 Cleared 3/28/2018 NAZILA NOORIFAR
Sewer availability Cleared 3/28/2018 NAZILA NOORIFAR
Distance to fire station Cleared 4/3/2018 JOHN DALLAS
Hydrant and Access approval Cleared 4/3/2018 JOHN DALLAS
BHO/Hillside ordinance Cleared 4/4/2018 ADRIAN SANCHEZ
BHO/Hillside ordinance Cleared 4/4/2018 ADRIAN SANCHEZ
Green Code Cleared 5/18/2018 MICHAEL AYERS
Excavation more than 5-ft deep Cleared 6/1/2018 CALOSHA APPROVED
Low Impact Development Cleared 6/6/2018 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 6/6/2018 STEVE MELGAR
Landscape for retaining wall Cleared 9/4/2018 DENNIS CHEW
Green Code Cleared 1/17/2020 MICHAEL AYERS
GPI Written Notices Cleared 2/19/2020 RAPHAEL ROSAS
Grading Pre-Inspection Cleared 2/19/2020 RAPHAEL ROSAS

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 21757 DEVONSHIRE ST.   SUITE 3    CANOGA PARK, CA 91311
Engineer Irvine, Jon Alan; Lic. No.: GE2891 145 N SIERRA MADRE BLVD      PASADENA, CA 91107
Geologist Irvine, Jon A; Lic. No.: EG1691 1150 ENCANTO DR      ARCADIA, CA 91007

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/15/2022 Partial Inspection RAUL BARAJAS
Deputy Reinf. Concrete 4/12/2022 Conditional Approval RAUL BARAJAS
Deputy Reinf. Concrete 5/11/2022 Conditional Approval RAUL BARAJAS
Piling/Pier/Caisson 6/13/2022 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 6/14/2022 Conditional Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 7/14/2022 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 7/14/2022 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 8/18/2022 Not Ready for Inspection RAUL BARAJAS
Deputy Reinf. Concrete 8/25/2022 Conditional Approval RUBEN SALAS
Excavation/Setback/Form/Re-Bar 8/29/2022 Conditional Approval RAUL BARAJAS
Footing/Foundation/Slab 8/29/2022 Partial Approval RAUL BARAJAS
Deputy Shotcrete 9/20/2022 Conditional Approval ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 9/20/2022 Partial Approval ALIZAH MAYAGOITIA
Deputy Shotcrete 9/22/2022 Conditional Approval ALIZAH MAYAGOITIA
PLUMBING-Rough 11/7/2022 Not Ready for Inspection RAUL BARAJAS
Underground Mechanical 11/7/2022 Not Ready for Inspection RAUL BARAJAS
Underground Mechanical 11/18/2022 No Access for Inspection RAUL BARAJAS
Underground Mechanical 11/21/2022 Approved RAUL BARAJAS
Deputy Reinf. Concrete 12/20/2022 Conditional Approval RAUL BARAJAS
Footing/Foundation/Slab 12/21/2022 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 12/22/2022 Approved RAUL BARAJAS
Deputy Steel/Welding 1/18/2023 Conditional Approval RAUL BARAJAS
Deputy Steel/Welding 1/23/2023 Conditional Approval RUBEN SALAS
Deputy Steel/Welding 1/26/2023 Conditional Approval RAUL BARAJAS
Deputy Steel/Welding 1/31/2023 Conditional Approval RAUL BARAJAS
Deputy Wood Construction 2/22/2023 Conditional Approval RAUL BARAJAS
Deputy Wood Construction 2/28/2023 Conditional Approval STUART CHAPMAN
Deputy Wood Construction 3/28/2023 Conditional Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 4/6/2023 Partial Approval RAUL BARAJAS
Deputy Wood Construction 5/17/2023 Conditional Approval RAUL BARAJAS
Shower Pan 6/20/2023 Approved STUART CHAPMAN
Gas Test 6/27/2023 Partial Approval RAUL BARAJAS
PLUMBING-Rough 6/27/2023 Approved RAUL BARAJAS
Underground Mechanical 6/27/2023 Approved RAUL BARAJAS
ELECTRICAL-Rough 6/28/2023 Partial Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 6/28/2023 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Rough 6/28/2023 Approved RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 7/3/2023 Partial Inspection RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 7/6/2023 Partial Inspection RAUL BARAJAS
HVAC-Rough 7/26/2023 Partial Approval RAUL BARAJAS
Interior/Exterior Lathing 8/2/2023 Approved RAUL BARAJAS
Interior/Exterior Lathing 8/2/2023 Off-Hour Fees Due
Excavation/Setback/Form/Re-Bar 8/4/2023 Partial Inspection RAUL BARAJAS
Interior/Exterior Lathing 8/4/2023 Approved RAUL BARAJAS
Insulation 8/17/2023 Conditional Approval RAUL BARAJAS
BUILDING-Rough-Frame 8/22/2023 Partial Inspection RAUL BARAJAS
Green Building Rough 8/22/2023 Approved RAUL BARAJAS
Verify Sprinkler Sign Off 8/22/2023 Approved RAUL BARAJAS
Drywall Nailing 9/10/2023 Off-Hour Fees Due
Interior/Exterior Lathing 9/11/2023 Off-Hour Fees Due
Drywall Nailing 9/12/2023 Approved RAUL BARAJAS
ELECTRICAL-Final 9/16/2024 Corrections Issued RAUL BARAJAS
Final 9/16/2024 Corrections Issued RAUL BARAJAS
PLUMBING-Final 9/16/2024 Not Ready for Inspection RAUL BARAJAS
Service/Power Release 10/1/2024 Corrections Issued CRAIG VAUGHAN
PLUMBING-Final 10/8/2024 Not Ready for Inspection BRENDAN MORELLI
Service/Power Release 10/16/2024 Not Ready for Inspection RAUL BARAJAS
Service/Power Release 10/17/2024 Off-Hour Fees Due
Service/Power Release 10/17/2024 Partial Inspection RAUL BARAJAS
PLUMBING-Final 10/28/2024 Not Ready for Inspection RAUL BARAJAS
Service/Power Release 10/28/2024 Approved RAUL BARAJAS
PLUMBING-Final 11/20/2024 Corrections Issued RAUL BARAJAS
PLUMBING-Final 11/26/2024 Approved RAUL BARAJAS
BUILDING-Rough-Frame 2/5/2025 Approved ROY SPAULDING
Final 2/5/2025 Corrections Issued ROY SPAULDING
Green Building Final 2/5/2025 Not Ready for Inspection ROY SPAULDING
Reinforced Masonry Frame 2/5/2025 Not Ready for Inspection ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 2/5/2025 SGSOV Not Ready ROY SPAULDING
Smoke Detectors 2/5/2025 Not Ready for Inspection ROY SPAULDING
Final 2/13/2025 Not Ready for Inspection ROY SPAULDING
Green Building Final 2/13/2025 Not Ready for Inspection ROY SPAULDING
Reinforced Masonry Frame 2/13/2025 Not Ready for Inspection ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 2/13/2025 SGSOV Not Ready ROY SPAULDING
Smoke Detectors 2/13/2025 Not Ready for Inspection ROY SPAULDING
Reinforced Masonry Frame 2/19/2025 Not Ready for Inspection ROY SPAULDING
Enclosure/Fence 3/13/2025 Partial Inspection RAUL BARAJAS
Reinforced Masonry Frame 3/13/2025 Approved RAUL BARAJAS
Final 3/25/2025 OK to Issue CofO RAUL BARAJAS
Green Building Final 3/25/2025 Approved RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 3/25/2025 SGSOV Approved RAUL BARAJAS
Smoke Detectors 3/25/2025 Approved RAUL BARAJAS