5050 N HASKELL AVE 91436

Certificate Information: 5050 N HASKELL AVE 91436

Application / Permit
17010-20000-05035
Plan Check / Job No.
B17VN19642
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 46'-0''x 77'-5'' 2-story single family dwelling with attached 2-car garage and patio. Building equipped with automatic fire sprinkler system NFPA13D.
Permit Issued
Issued on 5/15/2019
Issuing Office
Valley
Current Status
CofO Issued on 5/9/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/21/2017 APPLICANT
Assigned to Plan Check Engineer 1/4/2018 DANNY MORALES
Corrections Issued 1/7/2018 DANNY MORALES
Quality Review Completed 1/9/2018 STEVEN KIM
Building Plans Picked Up 1/18/2018 APPLICANT
Green Plans Picked Up 1/18/2018 APPLICANT
Plan Check Approved 3/9/2018 DANNY MORALES
No Progress 4/23/2019 ALYSSA N NARCISO
Issued 5/15/2019 LADBS
CofO in Progress 5/7/2024 VINCENT HANLEY
Permit Finaled 5/9/2024 JOHN JANSON
CofO Issued 5/9/2024 JOHN JANSON
Permit Finaled 5/9/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 1/25/2018 HOWARD COOPER
Eng Process Fee Ord 176,300 Cleared 1/25/2018 KAYLA PEJI
Permit Cleared 1/25/2018 KAYLA PEJI
Sewer availability Cleared 1/25/2018 KAYLA PEJI
Low Impact Development Cleared 2/9/2018 SAM NAVID
Roof/Waste drainage to street Cleared 2/9/2018 STEVE MELGAR
Miscellaneous Cleared 2/20/2018 DWAYNE WYATT
Private street Cleared 2/20/2018 DWAYNE WYATT
ZA Case Cleared 2/20/2018 TREVOR MARTIN
Miscellaneous Cleared 2/23/2018 DWAYNE WYATT
Green Code Cleared 3/2/2018 DAVID MATSON
Hydrant and Access approval Cleared 3/2/2018 JOHN DALLAS

Contact Information

Contractor Owner-Builder       ,
Engineer Saleh, Zouheir Toufic; Lic. No.: C42881 1304 CORTE MALTERA      COSTA MESA, CA 92626

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/26/2019 Partial Approval RONALD COWAN
Underground Mechanical 7/26/2019 Approved RONALD COWAN
Excavation/Setback/Form/Re-Bar 8/5/2019 Approved RONALD COWAN
Footing/Foundation/Slab 8/5/2019 Approved RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 8/19/2019 Partial Approval RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 9/6/2019 Not Ready for Inspection RONALD COWAN
Underground Mechanical 9/6/2019 Not Ready for Inspection RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 9/11/2019 Corrections Issued RONALD COWAN
Deputy Drilled-In Anchors 10/18/2019 Approved RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 10/21/2019 Partial Approval RONALD COWAN
ELECTRICAL-Rough 12/16/2019 Not Ready for Inspection RONALD COWAN
PLUMBING-Rough 12/16/2019 Not Ready for Inspection RONALD COWAN
Shower Pan 12/16/2019 Approved RONALD COWAN
BUILDING-Rough-Frame 12/23/2019 Corrections Issued RONALD COWAN
ELECTRICAL-Rough 12/23/2019 Not Ready for Inspection RONALD COWAN
Green Building Rough 12/23/2019 Partial Approval RONALD COWAN
MERV13>=Rough 12/23/2019 Approved RONALD COWAN
PLUMBING-Rough 12/23/2019 Approved RONALD COWAN
Verify Sprinkler Sign Off 12/23/2019 Not Ready for Inspection RONALD COWAN
Special/Order Compliance 2/5/2020 Corrections Issued RONALD COWAN
ELECTRICAL-Rough 3/2/2020 Not Ready for Inspection RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 3/2/2020 Not Ready for Inspection RONALD COWAN
HVAC-Rough 3/2/2020 Not Ready for Inspection RONALD COWAN
PLUMBING-Rough 3/2/2020 Not Ready for Inspection RONALD COWAN
Insulation 5/22/2020 Approved RONALD COWAN
Drywall Nailing 6/3/2020 Approved RONALD COWAN
Green Building Rough 6/3/2020 Approved RONALD COWAN
Interior/Exterior Lathing 1/21/2021 Approved RONALD COWAN
PLUMBING-Final 2/14/2022 Not Ready for Inspection ROBERT GOLD
Sewer 3/8/2022 Approved DAVID SANDOVAL
Special/Order Compliance 6/29/2022 Partial Inspection ROBERT GOLD
Special/Order Compliance 6/30/2022 Approved ROBERT GOLD
Special/Order Compliance 7/13/2022 Approved ROBERT GOLD
Special/Order Compliance 9/28/2022 Approved ROBERT GOLD
Special/Order Compliance 9/28/2022 Not Ready for Inspection VINCENT HANLEY
Service/Power Release 5/12/2023 Approved VINCENT HANLEY
Service/Power Release 6/5/2023 Approved VINCENT HANLEY
Underground Mechanical 8/23/2023 Partial Approval SEAN WIRCH
ELECTRICAL-Final 10/4/2023 Approved VINCENT HANLEY
PLUMBING-Final 10/4/2023 Approved VINCENT HANLEY
HVAC-Final 12/20/2023 Approved VINCENT HANLEY
BUILDING-Rough-Frame 1/3/2024 Approved VINCENT HANLEY
Final 1/3/2024 Corrections Issued VINCENT HANLEY
Green Building Final 1/3/2024 Approved VINCENT HANLEY
MERV13>=Final 1/3/2024 Corrections Issued VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 1/3/2024 SGSOV Approved VINCENT HANLEY
Smoke Detectors 1/3/2024 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 1/3/2024 Approved VINCENT HANLEY
Final 4/29/2024 Partial Approval VINCENT HANLEY
MERV13>=Final 4/29/2024 Approved VINCENT HANLEY
Final 5/6/2024 OK to Issue CofO VINCENT HANLEY