813 N ROBINSON ST 90026
Certificate Information: 813 N ROBINSON ST 90026
- Application / Permit
- 17010-20000-04967
- Plan Check / Job No.
- B17VN19413
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 51'3' X 31'' 3-STORY SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE. ALL WORK DONE PER STRUCTURAL ENGINEERING.
- Permit Issued
- Issued on 3/4/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/24/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/18/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 12/28/2017 | DANNY MORALES |
| Green Plans Picked Up | 12/28/2017 | APPLICANT |
| Corrections Issued | 1/1/2018 | DANNY MORALES |
| Quality Review Completed | 1/9/2018 | STEVEN KIM |
| Plan Check Approved | 4/1/2019 | GURUNATH NESARAJAH |
| Issued | 3/4/2020 | LADBS |
| Building Plans Picked Up | 6/17/2021 | APPLICANT |
| CofO in Progress | 11/15/2022 | FREDDIE RIVERA |
| Permit Finaled | 12/24/2022 | DEROLD HAUFF |
| CofO Issued | 12/24/2022 | DEROLD HAUFF |
| Permit Finaled | 12/24/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 1/25/2018 | DANNY MORALES |
| Address approval | Cleared | 2/12/2018 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/12/2018 | MARKOS PEREZ-BRAN |
| Permit | Cleared | 2/12/2018 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 2/12/2018 | MARKOS PEREZ-BRAN |
| ZA Case | Cleared | 2/12/2018 | DAISY BENICIA |
| Grading Pre-Inspection | Cleared | 2/16/2018 | BARTON HOLMES |
| GPI Written Notices | Cleared | 3/21/2018 | DANNY MORALES |
| Construction near power lines | Cleared | 3/29/2018 | RIDWAN HARDY |
| Low Impact Development | Cleared | 5/17/2018 | SAM NAVID |
| Hydrant and Access approval | Cleared | 6/1/2018 | JOHN DALLAS |
| Miscellaneous | Cleared | 6/1/2018 | RICK TORRES |
| Roof/Waste drainage to street | Cleared | 6/1/2018 | EDUARDO PEDROZA |
| Tract Map conditions | Cleared | 6/1/2018 | RICK TORRES |
| Distance to fire station | Cleared | 6/5/2018 | OSCAR SALGADO JR |
| Excavation more than 5-ft deep | Cleared | 6/8/2018 | CALOSHA APPROVED |
Contact Information
| Architect | Maly, Farzin; Lic. No.: C33731 | PO BOX 57002 SHERMAN OAKS, CA 91413 |
| Contractor | I D C S Corporation; Lic. No.: 995061-B | 485 SOUTH ROBERTSON BLVD STE 8 BEVERLY HILLS, CA 90211 |
| Engineer | Minas,, Caro Jolfaie; Lic. No.: GE601 | 4742 SAN FERNANDO RD GLENDALE, CA 91204 |
| Engineer | Molai,, Mohamad Ali; Lic. No.: L9192 | 24308 BURBANK BLVD WOODLAND HILLS, CA 91367 |
| Engineer | Sayah, Daniel Hoshyar; Lic. No.: C67905 | 15233 VENTURA BLVD STE 1130 SHERMAN OAKS, CA 91403 |
| Geologist | Minas, Shant; Lic. No.: GEO8859 | 4225 DEL MAR AVENUE #215 LOS ANGELES, CA 90029 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/17/2020 | Partial Approval | ROBERT VORHIS |
| METHANE-Barrier | 4/17/2020 | Not Ready for Inspection | ROBERT VORHIS |
| METHANE-Subgrade | 4/17/2020 | Not Ready for Inspection | ROBERT VORHIS |
| Deputy Reinf. Concrete | 4/21/2020 | Conditional Approval | ROBERT VORHIS |
| Excavation/Setback/Form/Re-Bar | 4/21/2020 | Approved | ROBERT VORHIS |
| Deputy Other (see comments) | 4/30/2020 | Conditional Approval | ELMER BLAND |
| Special/Order Compliance | 4/30/2020 | Corrections Issued | ELMER BLAND |
| Footing/Foundation/Slab | 5/8/2020 | Approved | MATTHEW NUCKOLLS |
| METHANE-Barrier | 5/8/2020 | Approved | MATTHEW NUCKOLLS |
| METHANE-Subgrade | 5/8/2020 | Approved | MATTHEW NUCKOLLS |
| Underground Mechanical | 5/8/2020 | Partial Approval | MATTHEW NUCKOLLS |
| Reinforced Concrete Frame | 5/13/2020 | Partial Approval | RUBEN SALAS |
| Deputy Reinf. Masonry | 5/28/2020 | Approved | ROBERT VORHIS |
| Reinforced Masonry Frame | 5/28/2020 | Approved | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 6/8/2020 | Partial Approval | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 7/6/2020 | Partial Approval | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2020 | Partial Approval | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2020 | Partial Approval | ROBERT VORHIS |
| ELECTRICAL-Rough | 10/26/2020 | Approved | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 10/26/2020 | Not Ready for Inspection | ROBERT VORHIS |
| PLUMBING-Rough | 10/26/2020 | Corrections Issued | ROBERT VORHIS |
| HVAC-Rough | 11/5/2020 | No Access for Inspection | RUBEN SALAS |
| Interior/Exterior Lathing | 11/5/2020 | No Access for Inspection | RUBEN SALAS |
| PLUMBING-Rough | 11/5/2020 | No Access for Inspection | RUBEN SALAS |
| Shower Pan | 11/5/2020 | No Access for Inspection | RUBEN SALAS |
| Wood Frame | 11/5/2020 | No Access for Inspection | RUBEN SALAS |
| BUILDING-Rough-Frame | 11/12/2020 | Approved | ROBERT VORHIS |
| Green Building Rough | 11/12/2020 | Approved | ROBERT VORHIS |
| HVAC-Rough | 11/12/2020 | Approved | ROBERT VORHIS |
| Insulation | 11/12/2020 | Not Ready for Inspection | ROBERT VORHIS |
| Interior/Exterior Lathing | 11/12/2020 | Partial Approval | ROBERT VORHIS |
| METHANE-Rough | 11/12/2020 | Approved | ROBERT VORHIS |
| PLUMBING-Rough | 11/12/2020 | Approved | ROBERT VORHIS |
| Verify Sprinkler Sign Off | 11/12/2020 | Approved | ROBERT VORHIS |
| Insulation | 11/18/2020 | Approved | ROBERT VORHIS |
| Interior/Exterior Lathing | 11/18/2020 | Partial Approval | ROBERT VORHIS |
| Drywall Nailing | 12/3/2020 | Approved | STUART CHAPMAN |
| Underground Mechanical | 3/12/2021 | Corrections Issued | RUBEN SALAS |
| ELECTRICAL-Final | 10/4/2021 | No Access for Inspection | FREDDIE RIVERA |
| HVAC-Final | 10/4/2021 | No Access for Inspection | FREDDIE RIVERA |
| PLUMBING-Final | 10/4/2021 | No Access for Inspection | FREDDIE RIVERA |
| ELECTRICAL-Final | 2/8/2022 | Approved | ADAM ESCOTO |
| HVAC-Final | 2/8/2022 | Corrections Issued | ADAM ESCOTO |
| PLUMBING-Final | 2/8/2022 | Not Ready for Inspection | ADAM ESCOTO |
| Service/Power Release | 2/8/2022 | Not Ready for Inspection | ADAM ESCOTO |
| Special/Order Compliance | 3/7/2022 | Corrections Issued | SCOTT FINNILA |
| Final | 3/10/2022 | Not Ready for Inspection | AMY COLIN |
| Green Building Final | 3/10/2022 | Approved | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 3/10/2022 | SGSOV Not Ready | AMY COLIN |
| Service/Power Release | 3/10/2022 | Not Ready for Inspection | AMY COLIN |
| Smoke Detectors | 3/10/2022 | Not Ready for Inspection | AMY COLIN |
| Final | 3/29/2022 | No Access for Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 3/29/2022 | SGSOV Approved | FREDDIE RIVERA |
| Service/Power Release | 3/29/2022 | No Access for Inspection | FREDDIE RIVERA |
| Smoke Detectors | 3/29/2022 | No Access for Inspection | FREDDIE RIVERA |
| Final | 6/8/2022 | Corrections Issued | FREDDIE RIVERA |
| Service/Power Release | 6/8/2022 | Corrections Issued | FREDDIE RIVERA |
| Smoke Detectors | 6/8/2022 | Partial Inspection | FREDDIE RIVERA |
| Service/Power Release | 6/30/2022 | Approved | FREDDIE RIVERA |
| Final | 8/10/2022 | Corrections Issued | FREDDIE RIVERA |
| Service/Power Release | 8/10/2022 | Partial Inspection | FREDDIE RIVERA |
| Smoke Detectors | 8/10/2022 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 8/29/2022 | Approved | FREDDIE RIVERA |
| HVAC-Final | 8/29/2022 | Approved | FREDDIE RIVERA |
| PLUMBING-Final | 8/29/2022 | Approved | FREDDIE RIVERA |
| Final | 9/6/2022 | Partial Inspection | FREDDIE RIVERA |
| Service/Power Release | 9/6/2022 | Corrections Issued | FREDDIE RIVERA |
| Final | 9/12/2022 | Partial Inspection | FREDDIE RIVERA |
| Service/Power Release | 9/12/2022 | Partial Inspection | FREDDIE RIVERA |
| Service/Power Release | 9/15/2022 | Approved | FREDDIE RIVERA |
| Final | 11/15/2022 | OK to Issue CofO | FREDDIE RIVERA |