20320 W VOSE ST 91306
Certificate Information: 20320 W VOSE ST 91306
- Application / Permit
- 17010-20000-04942
- Plan Check / Job No.
- B17VN19338
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 24'-6" X 46'-0" IRREGULAR DETACHED ACCESSORY DWELLING UNIT PER AB 2299 AND SB 1069. ALL WORK PER WFPP.
- Permit Issued
- Issued on 10/23/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/15/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 12/28/2017 | JENNIFER LEE |
| Green Plans Picked Up | 12/29/2017 | APPLICANT |
| Corrections Issued | 1/4/2018 | JENNIFER LEE |
| Quality Review Completed | 1/8/2018 | STEVEN KIM |
| Building Plans Picked Up | 1/9/2018 | APPLICANT |
| Plan Check Approved | 10/16/2018 | JENNIFER LEE |
| Issued | 10/23/2018 | LADBS |
| CofO in Progress | 6/9/2025 | ALEXANDER HANDY |
| Permit Finaled | 7/21/2025 | DANIEL ORRANTE |
| CofO Issued | 7/21/2025 | DANIEL ORRANTE |
| Permit Finaled | 7/21/2025 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 1/11/2018 | KAYLA PEJI |
| Permit | Cleared | 1/11/2018 | KAYLA PEJI |
| Eng Process Fee Ord 176,300 | Cleared | 1/16/2018 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 1/16/2018 | MARKOS PEREZ-BRAN |
| Green Code | Cleared | 6/5/2018 | SARKIS HARABEDIAN |
| Low Impact Development | Cleared | 6/18/2018 | IDA MEISAMI-FARD |
| Roof/Waste drainage to street | Cleared | 6/20/2018 | RUDY TERRIQUEZ. |
| Construction near power lines | Cleared | 9/26/2018 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/26/2018 | Corrections Issued | JOHN COLEMAN |
| PLUMBING-Rough | 12/28/2018 | Partial Approval | JOHN COLEMAN |
| Excavation/Setback/Form/Re-Bar | 1/3/2019 | Not Ready for Inspection | JOHN COLEMAN |
| Excavation/Setback/Form/Re-Bar | 1/23/2019 | Corrections Issued | JOHN COLEMAN |
| Excavation/Setback/Form/Re-Bar | 1/25/2019 | Approved | JOHN COLEMAN |
| Footing/Foundation/Slab | 6/7/2019 | Approved | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2019 | Corrections Issued | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 10/9/2019 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 10/21/2019 | Not Ready for Inspection | JOHN JANSON |
| Footing/Foundation/Slab | 8/19/2020 | Approved | HENRY KIM |
| HVAC-Rough | 8/19/2020 | Not Ready for Inspection | HENRY KIM |
| ELECTRICAL-Rough | 11/12/2020 | Not Ready for Inspection | HENRY KIM |
| PLUMBING-Rough | 11/12/2020 | Not Ready for Inspection | HENRY KIM |
| Pre-Inspection | 11/12/2020 | Corrections Issued | HENRY KIM |
| Underground Mechanical | 11/12/2020 | Partial Approval | HENRY KIM |
| Sewer | 9/1/2021 | Partial Approval | HENRY KIM |
| Underground Mechanical | 9/1/2021 | Approved | HENRY KIM |
| Sewer | 9/16/2021 | Approved | HENRY KIM |
| ELECTRICAL-Rough | 3/14/2022 | Corrections Issued | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 3/14/2022 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Rough | 3/18/2022 | Corrections Issued | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2022 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 3/18/2022 | Partial Approval | STEVEN BACK |
| ELECTRICAL-Rough | 4/4/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| ELECTRICAL-Rough | 4/13/2022 | Approved | JOHNNY MIRANDA |
| HVAC-Rough | 4/18/2022 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Rough | 4/18/2022 | Corrections Issued | VINCENT HANLEY |
| HVAC-Rough | 5/16/2022 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 5/16/2022 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 8/11/2022 | Approved | STEVEN BACK |
| Green Building Rough | 8/11/2022 | Approved | STEVEN BACK |
| HVAC-Rough | 8/11/2022 | Approved | STEVEN BACK |
| Verify Sprinkler Sign Off | 8/11/2022 | Approved | STEVEN BACK |
| Insulation | 8/16/2022 | Approved | STEVEN BACK |
| Drywall Nailing | 9/9/2022 | No Access for Inspection | JESUS PINEDA |
| Drywall Nailing | 9/14/2022 | Approved | STEVEN BACK |
| PLUMBING-Final | 7/11/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Shower Pan | 7/11/2023 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 7/20/2023 | Approved | ALEXANDER HANDY |
| Final | 10/6/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Green Building Final | 10/6/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 10/6/2023 | SGSOV Not Ready | ALEXANDER HANDY |
| Service/Power Release | 10/6/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Smoke Detectors | 10/6/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Final | 9/24/2024 | Corrections Issued | ALEXANDER HANDY |
| Green Building Final | 9/24/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 9/24/2024 | SGSOV Approved | ALEXANDER HANDY |
| Service/Power Release | 9/24/2024 | Not Required | ALEXANDER HANDY |
| Smoke Detectors | 9/24/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| ELECTRICAL-Final | 6/6/2025 | Approved | ALEXANDER HANDY |
| Final | 6/6/2025 | OK to Issue CofO | ALEXANDER HANDY |
| Green Building Final | 6/6/2025 | Approved | ALEXANDER HANDY |
| HVAC-Final | 6/6/2025 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 6/6/2025 | Approved | ALEXANDER HANDY |
| Smoke Detectors | 6/6/2025 | Approved | ALEXANDER HANDY |