9124 W GIBSON ST 90034
Certificate Information: 9124 W GIBSON ST 90034
- Application / Permit
- 17010-20000-04913
- Plan Check / Job No.
- B17VN19199
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) (30' X 78'-3") 2-STORY IRREGULAR SHAPED SFD WITH 2-CAR GARAGE, BASEMENT & TRELLIS PATIO ALL WORK PER ENGINEERING. NFPA 13D SPRINKLER THROUGHOUT.
- Permit Issued
- Issued on 6/7/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/14/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 12/21/2017 | RAPHAEL ROSAS |
| Corrections Issued | 12/26/2017 | RAPHAEL ROSAS |
| Quality Review Completed | 12/26/2017 | STEVEN KIM |
| Building Plans Picked Up | 12/27/2017 | APPLICANT |
| Green Plans Picked Up | 12/27/2017 | APPLICANT |
| Applicant returned to address corrections | 3/9/2018 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 3/14/2018 | RAPHAEL ROSAS |
| Plan Check Approved | 5/30/2018 | RAPHAEL ROSAS |
| Issued | 6/7/2018 | LADBS |
| CofO in Progress | 12/8/2025 | ANDREW NAVE |
| Permit Finaled | 12/12/2025 | RICHARD STEINBACH |
| CofO Issued | 12/12/2025 | RICHARD STEINBACH |
| Permit Finaled | 12/12/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| CPC | Cleared | 1/23/2018 | DAISY BENICIA |
| CPC | Cleared | 1/23/2018 | DAISY BENICIA |
| ZA Case | Cleared | 1/23/2018 | DAISY BENICIA |
| ZA Case | Cleared | 1/23/2018 | DAISY BENICIA |
| Hydrant and Access approval | Cleared | 2/21/2018 | JOHN CONNEALLY |
| Green Code | Cleared | 3/29/2018 | MICHAEL AYERS |
| Low Impact Development | Cleared | 4/11/2018 | RYAN HUDSON |
| Roof/Waste drainage to street | Cleared | 4/11/2018 | ADRIAN SANCHEZ |
| Address approval | Cleared | 4/17/2018 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 4/17/2018 | LEE GUILBEAUX |
| Permit | Cleared | 4/17/2018 | LEE GUILBEAUX |
| Sewer availability | Cleared | 4/17/2018 | LEE GUILBEAUX |
| Excavation more than 5-ft deep | Cleared | 5/30/2018 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 5/30/2018 | RAPHAEL ROSAS |
| Grading Pre-Inspection | Cleared | 5/30/2018 | RAPHAEL ROSAS |
Contact Information
| Engineer | Afsharhasani, Rouzbeh; Lic. No.: C87032 | 1133 CAMELBACK ST 9038 NEWPORT BEACH, CA 92658 |
| Engineer | Alemozafar, Jilla; Lic. No.: C36047 | 728 WESTBOURNE DRIVE WEST HOLLYWOOD, CA 90069 |
| Engineer | Hakimian, Krikor Dikran; Lic. No.: GE939 | 601 E DEL MAR BLVD 303 PASADENA, CA 91101 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/18/2018 | Approved | KATHRYN BUTTERWORTH |
| Deputy Reinf. Concrete | 7/23/2018 | Conditional Approval | KATHRYN BUTTERWORTH |
| Piling/Pier/Caisson | 7/23/2018 | Partial Approval | KATHRYN BUTTERWORTH |
| Deputy Reinf. Concrete | 7/25/2018 | Conditional Approval | KATHRYN BUTTERWORTH |
| Piling/Pier/Caisson | 7/26/2018 | Approved | KATHRYN BUTTERWORTH |
| Deputy Reinf. Concrete | 7/31/2018 | Conditional Approval | KATHRYN BUTTERWORTH |
| Excavation/Setback/Form/Re-Bar | 9/4/2018 | Partial Approval | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 9/4/2018 | Partial Approval | KATHRYN BUTTERWORTH |
| METHANE-Barrier | 9/4/2018 | Approved | KATHRYN BUTTERWORTH |
| METHANE-Subgrade | 9/4/2018 | Approved | KATHRYN BUTTERWORTH |
| Deputy Reinf. Concrete | 10/1/2018 | Conditional Approval | ROBERT VORHIS |
| Footing/Foundation/Slab | 10/1/2018 | Partial Inspection | ROBERT VORHIS |
| Excavation/Setback/Form/Re-Bar | 10/11/2018 | Corrections Issued | ROBERT VORHIS |
| Excavation/Setback/Form/Re-Bar | 10/19/2018 | Partial Approval | ROBERT VORHIS |
| PLUMBING-Rough | 11/7/2018 | Partial Approval | ROBERT VORHIS |
| Footing/Foundation/Slab | 11/27/2018 | Approved | ROBERT VORHIS |
| Deputy Reinf. Concrete | 11/28/2018 | Conditional Approval | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 1/2/2019 | Partial Approval | ROBERT VORHIS |
| Green Building Rough | 1/2/2019 | Partial Inspection | ROBERT VORHIS |
| Deputy Wood Construction | 1/3/2019 | Conditional Approval | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 2/20/2019 | Partial Approval | MICHAEL TEMPLE |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2019 | Corrections Issued | RONALD WEBER |
| HVAC-Rough | 5/8/2019 | Conditional Approval | ROBERT VORHIS |
| PLUMBING-Rough | 5/20/2019 | Approved | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2019 | Approved | ROBERT VORHIS |
| ELECTRICAL-Rough | 6/7/2019 | Partial Approval | ROBERT VORHIS |
| HVAC-Rough | 6/7/2019 | Approved | ROBERT VORHIS |
| BUILDING-Rough-Frame | 6/24/2019 | Partial Inspection | ROBERT VORHIS |
| ELECTRICAL-Rough | 6/24/2019 | Partial Approval | ROBERT VORHIS |
| Green Building Rough | 6/24/2019 | Not Ready for Inspection | ROBERT VORHIS |
| METHANE-Rough | 6/24/2019 | Not Ready for Inspection | ROBERT VORHIS |
| Verify Sprinkler Sign Off | 6/24/2019 | Approved | ROBERT VORHIS |
| BUILDING-Rough-Frame | 7/1/2019 | Approved | EVAN COOPER |
| Green Building Rough | 7/1/2019 | Approved | EVAN COOPER |
| METHANE-Rough | 7/1/2019 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 7/15/2019 | Approved | EVAN COOPER |
| Insulation | 7/15/2019 | Approved | EVAN COOPER |
| Drywall Nailing | 7/23/2019 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 8/14/2019 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 8/21/2019 | Approved | EVAN COOPER |
| Gas Test | 10/30/2019 | Approved | EVAN COOPER |
| Underground Mechanical | 10/30/2019 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 1/27/2020 | SGSOV Not Ready | MICHAEL TEMPLE |
| Final | 1/29/2020 | Corrections Issued | EVAN COOPER |
| Green Building Final | 1/29/2020 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 1/29/2020 | SGSOV Approved | EVAN COOPER |
| Service/Power Release | 1/29/2020 | Approved | EVAN COOPER |
| Smoke Detectors | 1/29/2020 | Approved | EVAN COOPER |
| Structural Steel Frame | 1/29/2020 | Approved | EVAN COOPER |
| Special/Order Compliance | 1/30/2020 | Partial Inspection | EVAN COOPER |
| Final | 12/5/2025 | OK to Issue CofO | EVAN COOPER |