9124 W GIBSON ST 90034

Certificate Information: 9124 W GIBSON ST 90034

Application / Permit
17010-20000-04913
Plan Check / Job No.
B17VN19199
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) (30' X 78'-3") 2-STORY IRREGULAR SHAPED SFD WITH 2-CAR GARAGE, BASEMENT & TRELLIS PATIO ALL WORK PER ENGINEERING. NFPA 13D SPRINKLER THROUGHOUT.
Permit Issued
Issued on 6/7/2018
Issuing Office
Valley
Current Status
CofO Issued on 12/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/14/2017 APPLICANT
Assigned to Plan Check Engineer 12/21/2017 RAPHAEL ROSAS
Corrections Issued 12/26/2017 RAPHAEL ROSAS
Quality Review Completed 12/26/2017 STEVEN KIM
Building Plans Picked Up 12/27/2017 APPLICANT
Green Plans Picked Up 12/27/2017 APPLICANT
Applicant returned to address corrections 3/9/2018 RAPHAEL ROSAS
Applicant returned to address corrections 3/14/2018 RAPHAEL ROSAS
Plan Check Approved 5/30/2018 RAPHAEL ROSAS
Issued 6/7/2018 LADBS
CofO in Progress 12/8/2025 ANDREW NAVE
Permit Finaled 12/12/2025 RICHARD STEINBACH
CofO Issued 12/12/2025 RICHARD STEINBACH
Permit Finaled 12/12/2025 RICHARD STEINBACH

Permit Application Clearance Information

CPC Cleared 1/23/2018 DAISY BENICIA
CPC Cleared 1/23/2018 DAISY BENICIA
ZA Case Cleared 1/23/2018 DAISY BENICIA
ZA Case Cleared 1/23/2018 DAISY BENICIA
Hydrant and Access approval Cleared 2/21/2018 JOHN CONNEALLY
Green Code Cleared 3/29/2018 MICHAEL AYERS
Low Impact Development Cleared 4/11/2018 RYAN HUDSON
Roof/Waste drainage to street Cleared 4/11/2018 ADRIAN SANCHEZ
Address approval Cleared 4/17/2018 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 4/17/2018 LEE GUILBEAUX
Permit Cleared 4/17/2018 LEE GUILBEAUX
Sewer availability Cleared 4/17/2018 LEE GUILBEAUX
Excavation more than 5-ft deep Cleared 5/30/2018 CALOSHA APPROVED
GPI Written Notices Cleared 5/30/2018 RAPHAEL ROSAS
Grading Pre-Inspection Cleared 5/30/2018 RAPHAEL ROSAS

Contact Information

Engineer Afsharhasani, Rouzbeh; Lic. No.: C87032 1133 CAMELBACK ST   9038    NEWPORT BEACH, CA 92658
Engineer Alemozafar, Jilla; Lic. No.: C36047 728 WESTBOURNE DRIVE      WEST HOLLYWOOD, CA 90069
Engineer Hakimian, Krikor Dikran; Lic. No.: GE939 601 E DEL MAR BLVD 303      PASADENA, CA 91101

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/18/2018 Approved KATHRYN BUTTERWORTH
Deputy Reinf. Concrete 7/23/2018 Conditional Approval KATHRYN BUTTERWORTH
Piling/Pier/Caisson 7/23/2018 Partial Approval KATHRYN BUTTERWORTH
Deputy Reinf. Concrete 7/25/2018 Conditional Approval KATHRYN BUTTERWORTH
Piling/Pier/Caisson 7/26/2018 Approved KATHRYN BUTTERWORTH
Deputy Reinf. Concrete 7/31/2018 Conditional Approval KATHRYN BUTTERWORTH
Excavation/Setback/Form/Re-Bar 9/4/2018 Partial Approval KATHRYN BUTTERWORTH
Footing/Foundation/Slab 9/4/2018 Partial Approval KATHRYN BUTTERWORTH
METHANE-Barrier 9/4/2018 Approved KATHRYN BUTTERWORTH
METHANE-Subgrade 9/4/2018 Approved KATHRYN BUTTERWORTH
Deputy Reinf. Concrete 10/1/2018 Conditional Approval ROBERT VORHIS
Footing/Foundation/Slab 10/1/2018 Partial Inspection ROBERT VORHIS
Excavation/Setback/Form/Re-Bar 10/11/2018 Corrections Issued ROBERT VORHIS
Excavation/Setback/Form/Re-Bar 10/19/2018 Partial Approval ROBERT VORHIS
PLUMBING-Rough 11/7/2018 Partial Approval ROBERT VORHIS
Footing/Foundation/Slab 11/27/2018 Approved ROBERT VORHIS
Deputy Reinf. Concrete 11/28/2018 Conditional Approval ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 1/2/2019 Partial Approval ROBERT VORHIS
Green Building Rough 1/2/2019 Partial Inspection ROBERT VORHIS
Deputy Wood Construction 1/3/2019 Conditional Approval ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 2/20/2019 Partial Approval MICHAEL TEMPLE
Floor/Roof Diaphrgm/Shear Wall 3/20/2019 Corrections Issued RONALD WEBER
HVAC-Rough 5/8/2019 Conditional Approval ROBERT VORHIS
PLUMBING-Rough 5/20/2019 Approved ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 6/4/2019 Approved ROBERT VORHIS
ELECTRICAL-Rough 6/7/2019 Partial Approval ROBERT VORHIS
HVAC-Rough 6/7/2019 Approved ROBERT VORHIS
BUILDING-Rough-Frame 6/24/2019 Partial Inspection ROBERT VORHIS
ELECTRICAL-Rough 6/24/2019 Partial Approval ROBERT VORHIS
Green Building Rough 6/24/2019 Not Ready for Inspection ROBERT VORHIS
METHANE-Rough 6/24/2019 Not Ready for Inspection ROBERT VORHIS
Verify Sprinkler Sign Off 6/24/2019 Approved ROBERT VORHIS
BUILDING-Rough-Frame 7/1/2019 Approved EVAN COOPER
Green Building Rough 7/1/2019 Approved EVAN COOPER
METHANE-Rough 7/1/2019 Approved EVAN COOPER
ELECTRICAL-Rough 7/15/2019 Approved EVAN COOPER
Insulation 7/15/2019 Approved EVAN COOPER
Drywall Nailing 7/23/2019 Approved OGANES TARAKHCHYAN
Shower Pan 8/14/2019 Approved EVAN COOPER
Interior/Exterior Lathing 8/21/2019 Approved EVAN COOPER
Gas Test 10/30/2019 Approved EVAN COOPER
Underground Mechanical 10/30/2019 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 1/27/2020 SGSOV Not Ready MICHAEL TEMPLE
Final 1/29/2020 Corrections Issued EVAN COOPER
Green Building Final 1/29/2020 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 1/29/2020 SGSOV Approved EVAN COOPER
Service/Power Release 1/29/2020 Approved EVAN COOPER
Smoke Detectors 1/29/2020 Approved EVAN COOPER
Structural Steel Frame 1/29/2020 Approved EVAN COOPER
Special/Order Compliance 1/30/2020 Partial Inspection EVAN COOPER
Final 12/5/2025 OK to Issue CofO EVAN COOPER