4509 N NOELINE AVE 91436

Certificate Information: 4509 N NOELINE AVE 91436

Application / Permit
17010-20000-04771
Plan Check / Job No.
B17VN18552
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Accessory Living Quarters
Work Description
NEW ACCESSORY LIVING QUARTER.
Permit Issued
Issued on 7/13/2018
Issuing Office
West Los Angeles
Current Status
CofO Issued on 6/4/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/4/2017 APPLICANT
Assigned to Plan Check Engineer 12/7/2017 VLADIMIR ARUTYUNYAN
Corrections Issued 12/12/2017 VLADIMIR ARUTYUNYAN
Quality Review Completed 12/13/2017 STEVEN KIM
Building Plans Picked Up 12/13/2017 APPLICANT
Green Plans Picked Up 12/13/2017 APPLICANT
Plan Check Approved 2/16/2018 VLADIMIR ARUTYUNYAN
Issued 7/13/2018 LADBS
CofO in Progress 5/20/2022 DAVID SANDOVAL
Permit Finaled 6/4/2022 MICHAEL SMITH
CofO Issued 6/4/2022 MICHAEL SMITH
Permit Finaled 6/4/2022 MICHAEL SMITH

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 1/11/2018 KAYLA PEJI
BHO/Hillside ordinance Cleared 1/11/2018 KAYLA PEJI
BHO/Hillside ordinance Cleared 1/11/2018 KAYLA PEJI
Eng Process Fee Ord 176,300 Cleared 1/11/2018 KAYLA PEJI
Sewer availability Cleared 1/11/2018 KAYLA PEJI
Low Impact Development Cleared 1/18/2018 SAM NAVID
Green Code Cleared 1/24/2018 MICHAEL AYERS
Hydrant and Access approval Cleared 2/13/2018 JOHN DALLAS
Roof/Waste drainage to street Cleared 2/13/2018 JOHN LIN

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon, Benigno S Jr; Lic. No.: S3454 25531 PRADO DELAS BELLOTAS      CALABASAS, CA 91302

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 9/11/2019 Partial Approval RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 11/13/2019 Approved RONALD COWAN
HVAC-Rough 11/13/2019 Not Ready for Inspection RONALD COWAN
PLUMBING-Rough 11/13/2019 Approved RONALD COWAN
Interior/Exterior Lathing 11/21/2019 Order to Comply Issued RONALD COWAN
BUILDING-Rough-Frame 12/23/2019 Approved RONALD COWAN
ELECTRICAL-Rough 12/23/2019 Approved RONALD COWAN
Green Building Rough 12/23/2019 Approved RONALD COWAN
HVAC-Rough 12/23/2019 Approved RONALD COWAN
Verify Sprinkler Sign Off 12/23/2019 Approved RONALD COWAN
Insulation 1/10/2020 Not Ready for Inspection RONALD COWAN
Insulation 1/13/2020 Approved RONALD COWAN
Shower Pan 1/13/2020 Corrections Issued RONALD COWAN
Shower Pan 1/15/2020 Approved RONALD COWAN
Drywall Nailing 1/21/2020 Approved RONALD COWAN
Drywall Nailing 1/23/2020 Approved RONALD COWAN
PLUMBING-Rough 1/23/2020 Partial Approval RONALD COWAN
Underground Mechanical 1/23/2020 Partial Approval RONALD COWAN
Underground Mechanical 5/6/2020 Approved RONALD COWAN
Gas Test 6/1/2021 Approved SEAN WIRCH
HVAC-Final 6/1/2021 Approved SEAN WIRCH
PLUMBING-Final 6/1/2021 Approved SEAN WIRCH
Gas Test 6/2/2021 No Access for Inspection DAVID SANDOVAL
ELECTRICAL-Final 6/4/2021 Approved RONALD COWAN
ELECTRICAL-Final 6/8/2021 Approved RONALD COWAN
Final 8/27/2021 Corrections Issued RONALD COWAN
Footing/Foundation/Slab 8/27/2021 Approved RONALD COWAN
Green Building Final 8/27/2021 Approved RONALD COWAN
SGSOV-Seismic Gas S/O Valve 8/27/2021 SGSOV Approved RONALD COWAN
Service/Power Release 8/27/2021 Approved RONALD COWAN
Smoke Detectors 8/27/2021 Approved RONALD COWAN
Service/Power Release 9/21/2021 Not Required RONALD COWAN
Final 5/9/2022 Corrections Issued VINCENT HANLEY
Service/Power Release 5/9/2022 Not Ready for Inspection VINCENT HANLEY
Final 5/18/2022 OK to Issue CofO DAVID SANDOVAL
Service/Power Release 5/18/2022 Approved DAVID SANDOVAL