Pre-Inspection
|
5/1/2019
|
Approved
|
JEFFREY DURAN
|
|
Deputy Reinf. Concrete
|
6/21/2019
|
Conditional Approval
|
ALAN NOVAK
|
|
Excavation/Setback/Form/Re-Bar
|
6/21/2019
|
Partial Approval
|
ALAN NOVAK
|
|
Footing/Foundation/Slab
|
6/21/2019
|
Partial Approval
|
ALAN NOVAK
|
|
Deputy Reinf. Concrete
|
6/24/2019
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Reinf. Concrete
|
7/3/2019
|
Approved
|
JEFFREY DURAN
|
|
Excavation/Setback/Form/Re-Bar
|
7/3/2019
|
Partial Approval
|
JEFFREY DURAN
|
|
Footing/Foundation/Slab
|
7/3/2019
|
Partial Approval
|
JEFFREY DURAN
|
|
Deputy Reinf. Concrete
|
7/8/2019
|
Conditional Approval
|
JEFFREY DURAN
|
|
Footing/Foundation/Slab
|
9/5/2019
|
Corrections Issued
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
9/11/2019
|
Conditional Approval
|
JEFFREY DURAN
|
|
Structural Steel Frame
|
9/11/2019
|
Conditional Approval
|
JEFFREY DURAN
|
|
Structural Steel Frame
|
9/16/2019
|
Not Ready for Inspection
|
JEFFREY DURAN
|
|
Deputy Drilled-In Anchors
|
9/17/2019
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Reinf. Concrete
|
9/17/2019
|
Conditional Approval
|
JEFFREY DURAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/30/2019
|
Partial Approval
|
JAMES STEPHENS
|
|
Deputy Drilled-In Anchors
|
10/29/2019
|
Conditional Approval
|
JEFFREY DURAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/31/2019
|
Partial Approval
|
JEFFREY DURAN
|
|
Wall Anchors
|
10/31/2019
|
Partial Approval
|
JEFFREY DURAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/15/2019
|
Partial Approval
|
JEFFREY DURAN
|
|
Green Building Rough
|
11/22/2019
|
Not Ready for Inspection
|
JEFFREY DURAN
|
|
Insulation
|
11/22/2019
|
Not Ready for Inspection
|
JEFFREY DURAN
|
|
Verify Sprinkler Sign Off
|
11/22/2019
|
Not Ready for Inspection
|
JEFFREY DURAN
|
|
Wood Frame
|
11/22/2019
|
Partial Approval
|
JEFFREY DURAN
|
|
Insulation
|
12/2/2019
|
Partial Approval
|
JEFFREY DURAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/12/2019
|
Partial Approval
|
JEFFREY DURAN
|
|
Insulation
|
12/12/2019
|
Partial Approval
|
JEFFREY DURAN
|
|
Green Building Rough
|
12/23/2019
|
Partial Inspection
|
JEFFREY DURAN
|
|
Verify Sprinkler Sign Off
|
12/23/2019
|
Not Ready for Inspection
|
JEFFREY DURAN
|
|
Wood Frame
|
12/31/2019
|
Conditional Approval
|
JEFFREY DURAN
|
|
Green Building Rough
|
1/10/2020
|
Partial Inspection
|
JEFFREY DURAN
|
|
Verify Sprinkler Sign Off
|
1/10/2020
|
Not Ready for Inspection
|
JEFFREY DURAN
|
|
Wood Frame
|
1/10/2020
|
Partial Approval
|
JEFFREY DURAN
|
|
Interior/Exterior Lathing
|
1/13/2020
|
Partial Approval
|
JEFFREY DURAN
|
|
Excavation/Setback/Form/Re-Bar
|
1/23/2020
|
Partial Approval
|
JAMES STEPHENS
|
|
Masonry Wall/Backfill
|
1/23/2020
|
Not Ready for Inspection
|
JAMES STEPHENS
|
|
Green Building Rough
|
1/30/2020
|
Partial Approval
|
JEFFREY DURAN
|
|
Verify Sprinkler Sign Off
|
1/30/2020
|
Partial Approval
|
JEFFREY DURAN
|
|
Wood Frame
|
1/30/2020
|
Partial Approval
|
JEFFREY DURAN
|
|
Green Building Rough
|
2/4/2020
|
Partial Inspection
|
JEFFREY DURAN
|
|
Masonry Wall/Backfill
|
2/4/2020
|
Partial Approval
|
JEFFREY DURAN
|
|
Verify Sprinkler Sign Off
|
2/4/2020
|
Partial Inspection
|
JEFFREY DURAN
|
|
Wood Frame
|
2/4/2020
|
Not Ready for Inspection
|
JEFFREY DURAN
|
|
Special/Order Compliance
|
2/5/2020
|
Partial Approval
|
JEFFREY DURAN
|
|
Green Building Rough
|
2/7/2020
|
Partial Inspection
|
JEFFREY DURAN
|
|
Insulation
|
2/7/2020
|
Partial Approval
|
JEFFREY DURAN
|
|
Verify Sprinkler Sign Off
|
2/7/2020
|
Not Ready for Inspection
|
JEFFREY DURAN
|
|
Wood Frame
|
2/7/2020
|
Partial Approval
|
JEFFREY DURAN
|
|
Insulation
|
2/11/2020
|
Partial Approval
|
JEFFREY DURAN
|
|
Drywall Nailing
|
2/12/2020
|
Partial Approval
|
JEFFREY DURAN
|
|
Insulation
|
2/12/2020
|
Partial Approval
|
JEFFREY DURAN
|
|
Masonry Wall/Backfill
|
2/12/2020
|
Partial Approval
|
JEFFREY DURAN
|
|
Drywall Nailing
|
2/19/2020
|
Partial Approval
|
JEFFREY DURAN
|
|
Green Building Rough
|
2/19/2020
|
Partial Inspection
|
JEFFREY DURAN
|
|
Insulation
|
2/19/2020
|
Partial Approval
|
JEFFREY DURAN
|
|
Verify Sprinkler Sign Off
|
2/19/2020
|
Partial Inspection
|
JEFFREY DURAN
|
|
Drywall Nailing
|
2/26/2020
|
Partial Approval
|
JEFFREY DURAN
|
|
Green Building Rough
|
2/26/2020
|
Not Ready for Inspection
|
JEFFREY DURAN
|
|
Insulation
|
2/26/2020
|
Partial Approval
|
JEFFREY DURAN
|
|
Verify Sprinkler Sign Off
|
2/27/2020
|
Not Ready for Inspection
|
JEFFREY DURAN
|
|
Wood Frame
|
2/27/2020
|
Conditional Approval
|
JEFFREY DURAN
|
|
Insulation
|
2/28/2020
|
Partial Approval
|
JEFFREY DURAN
|
|
Drywall Nailing
|
3/5/2020
|
Partial Approval
|
JEFFREY DURAN
|
|
Green Building Rough
|
3/5/2020
|
Partial Inspection
|
JEFFREY DURAN
|
|
Insulation
|
3/5/2020
|
Partial Approval
|
JEFFREY DURAN
|
|
Drywall Nailing
|
3/9/2020
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Verify Sprinkler Sign Off
|
3/9/2020
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Drywall Nailing
|
3/12/2020
|
Partial Approval
|
JEFFREY DURAN
|
|
Green Building Rough
|
3/12/2020
|
Partial Approval
|
JEFFREY DURAN
|
|
Drywall Nailing
|
3/17/2020
|
Partial Approval
|
JEFFREY DURAN
|
|
Green Building Rough
|
3/17/2020
|
Partial Approval
|
JEFFREY DURAN
|
|
Drywall Nailing
|
3/23/2020
|
Partial Approval
|
JEFFREY DURAN
|
|
Green Building Rough
|
3/23/2020
|
Partial Inspection
|
JEFFREY DURAN
|
|
Drywall Nailing
|
3/24/2020
|
Partial Approval
|
JEFFREY DURAN
|
|
Insulation
|
3/24/2020
|
Not Ready for Inspection
|
JEFFREY DURAN
|
|
Drywall Nailing
|
3/26/2020
|
Not Ready for Inspection
|
JEFFREY DURAN
|
|
Green Building Rough
|
3/26/2020
|
Partial Approval
|
JEFFREY DURAN
|
|
Verify Sprinkler Sign Off
|
3/26/2020
|
Partial Inspection
|
JEFFREY DURAN
|
|
Wood Frame
|
3/26/2020
|
Conditional Approval
|
JEFFREY DURAN
|
|
Drywall Nailing
|
4/7/2020
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Green Building Rough
|
4/7/2020
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Insulation
|
4/7/2020
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Masonry Wall/Backfill
|
4/17/2020
|
Approved
|
HAMID PISHEHVAR
|
|
Drywall Nailing
|
4/27/2020
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Green Building Rough
|
4/27/2020
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Insulation
|
4/27/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Drywall Nailing
|
4/29/2020
|
Partial Approval
|
JONATHAN QUACH
|
|
Green Building Rough
|
4/29/2020
|
Not Ready for Inspection
|
JONATHAN QUACH
|
|
Insulation
|
5/1/2020
|
Partial Approval
|
DANIEL VARNUM
|
|
Drywall Nailing
|
5/7/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Masonry Wall/Backfill
|
5/7/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Wood Frame
|
5/7/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Drywall Nailing
|
5/11/2020
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
5/11/2020
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Drywall Nailing
|
5/13/2020
|
Not Ready for Inspection
|
HAMID PISHEHVAR
|
|
Green Building Rough
|
5/13/2020
|
Partial Approval
|
HAMID PISHEHVAR
|
|
Insulation
|
5/13/2020
|
Approved
|
HAMID PISHEHVAR
|
|
Drywall Nailing
|
5/15/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Green Building Rough
|
5/15/2020
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Insulation
|
5/15/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Insulation
|
5/18/2020
|
Partial Approval
|
ROBERT COLE
|
|
Drywall Nailing
|
5/19/2020
|
Partial Approval
|
ROBERT COLE
|
|
Drywall Nailing
|
5/20/2020
|
Partial Approval
|
ROBERT COLE
|
|
Excavation/Setback/Form/Re-Bar
|
5/20/2020
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Green Building Rough
|
5/20/2020
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Drywall Nailing
|
5/26/2020
|
Partial Approval
|
ROBERT COLE
|
|
Green Building Rough
|
5/26/2020
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Special/Order Compliance
|
5/29/2020
|
Partial Approval
|
HAMID PISHEHVAR
|
|
Excavation/Setback/Form/Re-Bar
|
6/17/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Drywall Nailing
|
6/18/2020
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Green Building Rough
|
6/18/2020
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Light Gage Steel Frame
|
6/19/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Masonry Wall/Backfill
|
6/22/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Light Gage Steel Frame
|
6/26/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Excavation/Setback/Form/Re-Bar
|
7/2/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Footing/Foundation/Slab
|
7/14/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Special/Order Compliance
|
7/14/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Masonry Wall/Backfill
|
7/16/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Drywall Nailing
|
7/23/2020
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Final
|
7/23/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Footing/Foundation/Slab
|
7/23/2020
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Green Building Final
|
7/23/2020
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Green Building Rough
|
7/23/2020
|
Conditional Approval
|
JEFFREY FULTON
|
|
SGSOV-Seismic Gas S/O Valve
|
7/23/2020
|
SGSOV Not Ready
|
JEFFREY FULTON
|
|
Smoke Detectors
|
7/23/2020
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Verify Sprinkler Sign Off
|
7/23/2020
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Wood Frame
|
7/23/2020
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Excavation/Setback/Form/Re-Bar
|
7/27/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Excavation/Setback/Form/Re-Bar
|
8/3/2020
|
Approved
|
HAMID PISHEHVAR
|
|
Deputy Reinf. Concrete
|
8/4/2020
|
Conditional Approval
|
JEFFREY FULTON
|
|
Green Building Rough
|
8/14/2020
|
Approved
|
JEFFREY FULTON
|
|
Verify Sprinkler Sign Off
|
8/14/2020
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Wood Frame
|
8/14/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Interior/Exterior Lathing
|
8/28/2020
|
Approved
|
JEFFREY FULTON
|
|
Special/Order Compliance
|
9/2/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Wood Frame
|
9/10/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Final
|
9/11/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Final
|
9/14/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Final
|
9/15/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Final
|
9/16/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Final
|
9/17/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Special/Order Compliance
|
10/2/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Special/Order Compliance
|
10/6/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Special/Order Compliance
|
10/8/2020
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Final
|
10/13/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Smoke Detectors
|
10/15/2020
|
Approved
|
JEFFREY FULTON
|
|
Final
|
10/19/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Drywall Nailing
|
10/26/2020
|
Approved
|
JEFFREY FULTON
|
|
Final
|
10/26/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Footing/Foundation/Slab
|
10/26/2020
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Green Building Final
|
10/26/2020
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
SGSOV-Seismic Gas S/O Valve
|
10/26/2020
|
SGSOV Approved
|
JEFFREY FULTON
|
|
Verify Sprinkler Sign Off
|
10/26/2020
|
Approved
|
JEFFREY FULTON
|
|
Wood Frame
|
10/26/2020
|
Approved
|
JEFFREY FULTON
|
|
Final
|
10/29/2020
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Footing/Foundation/Slab
|
10/29/2020
|
Approved
|
JEFFREY FULTON
|
|
Green Building Final
|
10/29/2020
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Final
|
11/16/2020
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Green Building Final
|
11/16/2020
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Final
|
12/1/2020
|
Partial Approval
|
HAMID PISHEHVAR
|
|
Green Building Final
|
12/1/2020
|
Partial Approval
|
HAMID PISHEHVAR
|
|
Final
|
12/10/2020
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Green Building Final
|
12/10/2020
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Final
|
12/15/2020
|
OK to Issue CofO
|
JEFFREY FULTON
|
|
Green Building Final
|
12/15/2020
|
Approved
|
JEFFREY FULTON
|