524 N FULLER AVE 90036
Certificate Information: 524 N FULLER AVE 90036
- Application / Permit
- 17010-20000-04679
- Plan Check / Job No.
- B17VN18214
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 72'3" X 30'0" TWO STORY DWELLING WITH ATTACHED GARAGE. FIRE SPRINKLER REQUIRED; NFPA 13.
- Permit Issued
- Issued on 10/4/2018
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 6/10/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/28/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 11/30/2017 | STANLEY RAAP |
| Corrections Issued | 12/4/2017 | STANLEY RAAP |
| Quality Review Completed | 12/11/2017 | CHON CHIO KUO |
| Building Plans Picked Up | 12/14/2017 | APPLICANT |
| Green Plans Picked Up | 12/14/2017 | APPLICANT |
| Applicant returned to address corrections | 1/12/2018 | STANLEY RAAP |
| Plan Check Approved | 2/15/2018 | STANLEY RAAP |
| Issued | 10/4/2018 | LADBS |
| CofO in Progress | 6/9/2020 | CHRIS CHRISTENSEN |
| Permit Finaled | 6/10/2020 | DEROLD HAUFF |
| CofO Issued | 6/10/2020 | DEROLD HAUFF |
| Permit Finaled | 6/10/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/19/2017 | KENNETH PHAM |
| Eng Process Fee Ord 176,300 | Cleared | 12/19/2017 | KENNETH PHAM |
| Hydrant and Access approval | Cleared | 12/19/2017 | JOHN DALLAS |
| Sewer availability | Cleared | 12/19/2017 | KENNETH PHAM |
| CPC | Cleared | 1/22/2018 | RICK TORRES |
| CPC | Cleared | 1/22/2018 | RICK TORRES |
| Low Impact Development | Cleared | 1/25/2018 | SAM NAVID |
| Green Code | Cleared | 1/31/2018 | MICKEY YAMASHITA |
| Roof/Waste drainage to street | Cleared | 2/14/2018 | KAYLA PEJI |
Contact Information
| Contractor | Ark Design & Construction; Lic. No.: 974839-B | 1739 S SHERBOURNE DR LOS ANGELES, CA 90035 |
| Engineer | Yuzon, Benigno S Jr; Lic. No.: S3454 | 25531 PRADO DELAS BELLOTAS CALABASAS, CA 91302 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Barrier | 10/30/2018 | Approved | DANNY TOLENTINO |
| Excavation/Setback/Form/Re-Bar | 11/8/2018 | Partial Approval | DANNY TOLENTINO |
| Footing/Foundation/Slab | 11/8/2018 | Partial Approval | DANNY TOLENTINO |
| METHANE-Subgrade | 11/8/2018 | Partial Approval | DANNY TOLENTINO |
| Underground Mechanical | 11/8/2018 | Partial Approval | DANNY TOLENTINO |
| METHANE-Subgrade | 11/16/2018 | Approved | DANNY TOLENTINO |
| Footing/Foundation/Slab | 11/20/2018 | Approved | DANNY TOLENTINO |
| METHANE-Barrier | 11/20/2018 | Approved | DANNY TOLENTINO |
| BUILDING-Rough-Frame | 12/11/2018 | Partial Approval | DANNY TOLENTINO |
| PLUMBING-Rough | 12/11/2018 | Partial Approval | DANNY TOLENTINO |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2018 | Partial Approval | DANNY TOLENTINO |
| Sewer | 12/28/2018 | Partial Approval | DANNY TOLENTINO |
| Floor/Roof Diaphrgm/Shear Wall | 1/14/2019 | No Access for Inspection | DANNY TOLENTINO |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2019 | Not Ready for Inspection | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2019 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2019 | Partial Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2019 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2019 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2019 | Not Ready for Inspection | JOSEPH MCGARRY |
| HVAC-Rough | 6/18/2019 | Corrections Issued | JOSEPH MCGARRY |
| METHANE-Rough | 6/18/2019 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 6/18/2019 | Corrections Issued | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 6/21/2019 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 6/21/2019 | Partial Approval | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 6/28/2019 | Partial Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 6/28/2019 | Partial Approval | JOSEPH MCGARRY |
| Green Building Rough | 6/28/2019 | Not Ready for Inspection | JOSEPH MCGARRY |
| HVAC-Rough | 6/28/2019 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 6/28/2019 | Partial Approval | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 6/28/2019 | Not Ready for Inspection | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 7/3/2019 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 7/3/2019 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 7/3/2019 | Not Ready for Inspection | JOSEPH MCGARRY |
| HVAC-Rough | 7/3/2019 | Approved | JOSEPH MCGARRY |
| Insulation | 7/3/2019 | Conditional Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 7/3/2019 | Approved | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 7/3/2019 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 7/8/2019 | Conditional Approval | JOSEPH MCGARRY |
| Green Building Rough | 7/8/2019 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 7/8/2019 | Partial Approval | JOSEPH MCGARRY |
| Drywall Nailing | 7/15/2019 | Not Ready for Inspection | JOSEPH MCGARRY |
| Shower Pan | 7/15/2019 | Corrections Issued | JOSEPH MCGARRY |
| Drywall Nailing | 7/17/2019 | Approved | JOSEPH MCGARRY |
| Shower Pan | 7/17/2019 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 12/5/2019 | Not Ready for Inspection | JOSEPH MCGARRY |
| Service/Power Release | 12/5/2019 | Not Ready for Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 1/8/2020 | Approved | JOSEPH MCGARRY |
| HVAC-Final | 1/8/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| HVAC-Rough | 1/8/2020 | Approved | JOSEPH MCGARRY |
| PLUMBING-Final | 1/8/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| Service/Power Release | 1/8/2020 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 2/18/2020 | Approved | MATTHEW NUCKOLLS |
| ELECTRICAL-Final | 2/18/2020 | Approved | MATTHEW NUCKOLLS |
| Final | 2/18/2020 | Not Ready for Inspection | MATTHEW NUCKOLLS |
| Green Building Final | 2/18/2020 | Approved | MATTHEW NUCKOLLS |
| HVAC-Final | 2/18/2020 | Partial Approval | MATTHEW NUCKOLLS |
| PLUMBING-Final | 2/18/2020 | Approved | MATTHEW NUCKOLLS |
| SGSOV-Seismic Gas S/O Valve | 2/18/2020 | SGSOV Approved | MATTHEW NUCKOLLS |
| Smoke Detectors | 2/18/2020 | Approved | MATTHEW NUCKOLLS |
| ELECTRICAL-Final | 2/21/2020 | Not Ready for Inspection | BRAD BESCOS |
| HVAC-Final | 2/21/2020 | Not Ready for Inspection | BRAD BESCOS |
| PLUMBING-Final | 2/21/2020 | Not Ready for Inspection | BRAD BESCOS |
| Final | 2/24/2020 | Not Ready for Inspection | BRAD BESCOS |
| Final | 3/12/2020 | Corrections Issued | BRAD BESCOS |
| Final | 4/6/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| Final | 4/27/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| Gas Test | 4/27/2020 | Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 4/27/2020 | Approved | CHRIS CHRISTENSEN |
| Final | 5/1/2020 | Corrections Issued | JOSEPH MCGARRY |