15522 W TUBA ST 91345

Certificate Information: 15522 W TUBA ST 91345

Application / Permit
17010-20000-04615
Plan Check / Job No.
B17VN17982
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 21'-0"x37'-0" ACCESSORY DWELLING UNIT PER AB 2299 & SB 1069.WORK PER ENGINEER.
Permit Issued
Issued on 2/28/2018
Issuing Office
Valley
Current Status
CofO Issued on 7/7/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/21/2017 APPLICANT
Assigned to Plan Check Engineer 12/14/2017 TROY DEGUZMAN
Green Plans Picked Up 12/14/2017 APPLICANT
Corrections Issued 12/20/2017 TROY DEGUZMAN
Building Plans Picked Up 1/12/2018 APPLICANT
Quality Review Completed 2/28/2018 STEVEN KIM
Plan Check Approved 2/28/2018 TROY DEGUZMAN
Issued 2/28/2018 LADBS
CofO in Progress 5/21/2020 JENNIFER RABUCHIN
Permit Finaled 7/7/2020 MICHAEL SMITH
CofO Issued 7/7/2020 MICHAEL SMITH
Permit Finaled 7/7/2020 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 2/5/2018 KENNETH PHAM
Eng Process Fee Ord 176,300 Cleared 2/5/2018 KENNETH PHAM
Hydrant and Access approval Cleared 2/5/2018 JOHN DALLAS
Sewer availability Cleared 2/5/2018 KENNETH PHAM
Green Code Cleared 2/28/2018 MICHAEL AYERS
Low Impact Development Cleared 2/28/2018 RYAN HUDSON
Roof/Waste drainage to street Cleared 2/28/2018 CHRISTINE REUSCH

Contact Information

Contractor Owner-Builder       ,
Engineer Adams, Robert Charles; Lic. No.: C21234 22129 BRYANT STREET      CANOGA PARK, CA 91304

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/21/2018 No Access for Inspection MARK JOHNSON
PLUMBING-Rough 11/21/2018 No Access for Inspection MARK JOHNSON
Footing/Foundation/Slab 11/30/2018 Corrections Issued MARK JOHNSON
Footing/Foundation/Slab 12/4/2018 Approved MARK JOHNSON
BUILDING-Rough-Frame 6/5/2019 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 6/5/2019 Partial Approval JENNIFER RABUCHIN
Green Building Rough 6/5/2019 Not Ready for Inspection JENNIFER RABUCHIN
MERV13>=Rough 6/5/2019 Not Ready for Inspection JENNIFER RABUCHIN
Verify Sprinkler Sign Off 6/5/2019 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 7/8/2019 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 7/24/2019 Approved JENNIFER RABUCHIN
HVAC-Rough 7/24/2019 Approved JENNIFER RABUCHIN
PLUMBING-Rough 7/24/2019 Approved JENNIFER RABUCHIN
Underground Mechanical 7/24/2019 Partial Approval JENNIFER RABUCHIN
Interior/Exterior Lathing 7/30/2019 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 7/30/2019 Approved JENNIFER RABUCHIN
Insulation 8/5/2019 Approved MICHEL ABAJAN
PLUMBING-Rough 8/5/2019 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 8/9/2019 Approved JENNIFER RABUCHIN
Drywall Nailing 8/9/2019 Approved JENNIFER RABUCHIN
Green Building Rough 8/9/2019 Approved JENNIFER RABUCHIN
MERV13>=Rough 8/9/2019 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 8/19/2019 Approved JENNIFER RABUCHIN
Final 2/10/2020 No Access for Inspection ROBERT MINASSIANS
Green Building Final 2/10/2020 No Access for Inspection ROBERT MINASSIANS
MERV13>=Final 2/10/2020 No Access for Inspection ROBERT MINASSIANS
SGSOV-Seismic Gas S/O Valve 2/10/2020 SGSOV Not Ready ROBERT MINASSIANS
Service/Power Release 2/10/2020 No Access for Inspection ROBERT MINASSIANS
Smoke Detectors 2/10/2020 No Access for Inspection ROBERT MINASSIANS
ELECTRICAL-Final 2/12/2020 Corrections Issued JENNIFER RABUCHIN
Final 2/12/2020 Corrections Issued JENNIFER RABUCHIN
Gas Test 2/12/2020 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 2/12/2020 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 2/12/2020 Corrections Issued JENNIFER RABUCHIN
Final 2/18/2020 Partial Approval JENNIFER RABUCHIN
Green Building Final 2/18/2020 Approved JENNIFER RABUCHIN
MERV13>=Final 2/18/2020 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 2/18/2020 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 2/18/2020 Approved JENNIFER RABUCHIN
Smoke Detectors 2/18/2020 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 4/2/2020 Approved JENNIFER RABUCHIN
Final 4/2/2020 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 4/2/2020 Approved JENNIFER RABUCHIN
PLUMBING-Final 4/2/2020 Approved JENNIFER RABUCHIN