2635 N ADELBERT AVE 90039
Certificate Information: 2635 N ADELBERT AVE 90039
- Application / Permit
- 17010-20000-04600
- Plan Check / Job No.
- B17VN17950
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW (28'1" x 42'8") 3 STORY DWELLING AND BASEMENT GARAGE
- Permit Issued
- Issued on 10/12/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/21/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 12/14/2017 | JEFFREY TANGONAN |
| Green Plans Picked Up | 12/18/2017 | APPLICANT |
| Corrections Issued | 12/19/2017 | JEFFREY TANGONAN |
| Quality Review Completed | 12/21/2017 | DOUGLAS NAKATANI |
| Building Plans Picked Up | 12/27/2017 | APPLICANT |
| Applicant returned to address corrections | 5/3/2018 | JEFFREY TANGONAN |
| Applicant returned to address corrections | 7/24/2018 | JEFFREY TANGONAN |
| Plan Check Approved | 7/26/2018 | JEFFREY TANGONAN |
| Issued | 10/12/2018 | LADBS |
| CofO in Progress | 6/15/2023 | THOMAS LOGRASSO |
| Permit Finaled | 6/29/2023 | DEROLD HAUFF |
| CofO Issued | 6/29/2023 | DEROLD HAUFF |
| Permit Finaled | 6/29/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/14/2018 | LEE GUILBEAUX |
| Certificate of Compliance | Cleared | 3/14/2018 | DAISY BENICIA |
| Eng Process Fee Ord 176,300 | Cleared | 3/14/2018 | LEE GUILBEAUX |
| Miscellaneous | Cleared | 3/14/2018 | LEE GUILBEAUX |
| Permit | Cleared | 3/14/2018 | LEE GUILBEAUX |
| Sewer availability | Cleared | 3/14/2018 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 3/22/2018 | GILBERT URREA |
| GPI Written Notices | Cleared | 5/3/2018 | JEFFREY TANGONAN |
| Grading Pre-Inspection | Cleared | 5/3/2018 | JEFFREY TANGONAN |
| Green Code | Cleared | 6/19/2018 | SARKIS HARABEDIAN |
| Low Impact Development | Cleared | 7/19/2018 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 7/19/2018 | MARKOS PEREZ-BRAN |
Contact Information
| Architect | Glen, Charles; Lic. No.: C33143 | , |
| Contractor | Owner-Builder | , |
| Engineer | Robinson, Rory Anthony; Lic. No.: GE2491 | 963 EAST SANTA CLARA ST VENTURA, CA 93001 |
| Engineer | Soheil, Moeini; Lic. No.: C84000 | , |
| Geologist | Robinson, Rory Anthony; Lic. No.: EG1902 | 963 EAST SANTA CLARA STREET VENTURA, CA 93001 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/17/2019 | Partial Approval | DAVID CHAN |
| Footing/Foundation/Slab | 10/13/2020 | Not Ready for Inspection | COREY HUPP |
| Footing/Foundation/Slab | 11/17/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
| Deputy Reinf. Concrete | 11/18/2020 | No Access for Inspection | ELMER BLAND |
| Piling/Pier/Caisson | 11/20/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| Deputy Reinf. Concrete | 11/23/2020 | No Access for Inspection | ELMER BLAND |
| Excavation/Setback/Form/Re-Bar | 12/1/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 12/1/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| Deputy Reinf. Concrete | 12/3/2020 | No Access for Inspection | ELMER BLAND |
| Footing/Foundation/Slab | 1/7/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 1/12/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Deputy Reinf. Concrete | 1/13/2021 | Conditional Approval | THOMAS LOGRASSO |
| Deputy Reinf. Concrete | 2/2/2021 | Partial Approval | RUBEN SALAS |
| Excavation/Setback/Form/Re-Bar | 3/1/2021 | Not Ready for Inspection | RUBEN SALAS |
| Masonry Wall/Backfill | 3/1/2021 | Corrections Issued | RUBEN SALAS |
| Excavation/Setback/Form/Re-Bar | 3/11/2021 | Not Ready for Inspection | RUBEN SALAS |
| Masonry Wall/Backfill | 3/11/2021 | Corrections Issued | RUBEN SALAS |
| Excavation/Setback/Form/Re-Bar | 3/19/2021 | Partial Approval | STUART CHAPMAN |
| Masonry Wall/Backfill | 3/19/2021 | Corrections Issued | STUART CHAPMAN |
| Deputy Reinf. Concrete | 3/26/2021 | Partial Approval | RUBEN SALAS |
| Special/Order Compliance | 3/31/2021 | Corrections Issued | STUART CHAPMAN |
| Special/Order Compliance | 4/12/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Excavation/Setback/Form/Re-Bar | 7/9/2021 | Partial Approval | JUSTIN CURTIS |
| Footing/Foundation/Slab | 7/9/2021 | Partial Approval | JUSTIN CURTIS |
| Structural Steel Frame | 7/9/2021 | Conditional Approval | JUSTIN CURTIS |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2021 | Corrections Issued | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 11/1/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Rough | 11/1/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| MERV13>=Rough | 11/1/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Verify Sprinkler Sign Off | 11/1/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Wood Frame | 11/1/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 11/16/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2021 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Rough | 11/16/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| MERV13>=Rough | 11/16/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 11/16/2021 | Corrections Issued | THOMAS LOGRASSO |
| Verify Sprinkler Sign Off | 11/16/2021 | Corrections Issued | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 11/30/2021 | Partial Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 2/4/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 2/4/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Rough | 2/4/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| HVAC-Rough | 2/4/2022 | Corrections Issued | THOMAS LOGRASSO |
| MERV13>=Rough | 2/4/2022 | Approved | THOMAS LOGRASSO |
| PLUMBING-Rough | 2/4/2022 | Approved | THOMAS LOGRASSO |
| Verify Sprinkler Sign Off | 2/4/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 2/10/2022 | Corrections Issued | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 2/10/2022 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Rough | 2/10/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| HVAC-Rough | 2/10/2022 | Partial Approval | THOMAS LOGRASSO |
| Verify Sprinkler Sign Off | 2/10/2022 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 3/10/2022 | Conditional Approval | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 3/10/2022 | Partial Approval | THOMAS LOGRASSO |
| Green Building Rough | 3/10/2022 | Approved | THOMAS LOGRASSO |
| HVAC-Rough | 3/29/2022 | Approved | THOMAS LOGRASSO |
| Insulation | 3/29/2022 | Conditional Approval | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 3/29/2022 | Partial Approval | THOMAS LOGRASSO |
| Drywall Nailing | 4/18/2022 | Conditional Approval | THOMAS LOGRASSO |
| Shower Pan | 5/4/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Shower Pan | 6/7/2022 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 2/17/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Drywall Nailing | 2/17/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 2/17/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 2/17/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Final | 2/17/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| MERV13>=Final | 2/17/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 2/17/2023 | SGSOV Not Ready | THOMAS LOGRASSO |
| Service/Power Release | 2/17/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Smoke Detectors | 2/17/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 4/13/2023 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 4/13/2023 | Approved | THOMAS LOGRASSO |
| Final | 4/13/2023 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 4/13/2023 | Approved | THOMAS LOGRASSO |
| Green Building Final | 4/13/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| MERV13>=Final | 4/13/2023 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 4/13/2023 | SGSOV Not Ready | THOMAS LOGRASSO |
| Service/Power Release | 4/13/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Smoke Detectors | 4/13/2023 | Approved | THOMAS LOGRASSO |
| Final | 6/14/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Final | 6/14/2023 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 6/14/2023 | SGSOV Approved | THOMAS LOGRASSO |
| Service/Power Release | 6/14/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 6/15/2023 | OK to Issue CofO | THOMAS LOGRASSO |
| Service/Power Release | 6/15/2023 | Approved | THOMAS LOGRASSO |