238 E AVENUE 38 90031

Certificate Information: 238 E AVENUE 38 90031

Application / Permit
17010-20000-04437
Plan Check / Job No.
B17VN17293
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 40' x 20' 2-STORY SINGLE FAMILY DWELLING WITH ATT GAR; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 3/8/2021
Issuing Office
Current Status
CofO Issued on 5/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/9/2017 APPLICANT
Assigned to Plan Check Engineer 11/16/2017 SELLA BENYAMIN
Corrections Issued 11/22/2017 SELLA BENYAMIN
Quality Review Completed 11/22/2017 GUANG MIN TUNG
Building Plans Picked Up 11/28/2017 APPLICANT
Green Plans Picked Up 11/28/2017 APPLICANT
Plan Check Approved 9/6/2018 SELLA BENYAMIN
Issued 3/8/2021 APPLICANT
CofO in Progress 5/16/2024 LILIANA PORTILLO
CofO in Progress 5/20/2024 LILIANA PORTILLO
CofO in Progress 5/21/2024 CHARLES BOGHOSKHAN
CofO Issued 5/22/2024 DEROLD HAUFF
Permit Finaled 5/22/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/13/2018 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 3/13/2018 LEE GUILBEAUX
Hydrant and Access approval Cleared 3/13/2018 OSCAR SALGADO JR
Permit Cleared 3/13/2018 LEE GUILBEAUX
Sewer availability Cleared 3/13/2018 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 3/13/2018 LEE GUILBEAUX
Low Impact Development Cleared 5/24/2018 SAM NAVID
Roof/Waste drainage to street Cleared 6/6/2018 KAREN LE
Green Code Cleared 6/15/2018 SELLA BENYAMIN
HPOZ Cleared 9/10/2018 KATIE DEBIASE
Miscellaneous Cleared 9/10/2018 KATIE DEBIASE

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/25/2021 Not Ready for Inspection CRAIG VAUGHAN
Pre-Inspection 3/25/2021 Partial Inspection CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 4/7/2021 Partial Inspection CRAIG VAUGHAN
PLUMBING-Rough 4/19/2021 Corrections Issued CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 4/22/2021 Approved OSVALDO PARAMO
PLUMBING-Rough 4/22/2021 Partial Approval OSVALDO PARAMO
PLUMBING-Rough 4/28/2021 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 5/11/2021 Partial Approval COREY HUPP
Footing/Foundation/Slab 6/11/2021 Approved COREY HUPP
BUILDING-Rough-Frame 6/24/2021 Partial Approval COREY HUPP
BUILDING-Rough-Frame 7/30/2021 Not Ready for Inspection COREY HUPP
Wood Frame 8/3/2021 Partial Approval COREY HUPP
Gas Test 9/22/2021 Partial Approval COREY HUPP
Underground Mechanical 9/22/2021 Partial Inspection COREY HUPP
Gas Test 11/24/2021 Partial Approval CRAIG DAVIS
PLUMBING-Rough 11/24/2021 Corrections Issued CRAIG DAVIS
HVAC-Rough 2/4/2022 Partial Approval COREY HUPP
HVAC-Rough 2/24/2022 Corrections Issued OSVALDO PARAMO
PLUMBING-Rough 2/24/2022 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 3/4/2022 Not Ready for Inspection COREY HUPP
PLUMBING-Rough 3/4/2022 Approved COREY HUPP
ELECTRICAL-Rough 3/11/2022 Approved OSVALDO PARAMO
HVAC-Rough 3/11/2022 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 3/30/2022 Corrections Issued AMY COLIN
Green Building Rough 3/30/2022 Not Ready for Inspection AMY COLIN
MERV13>=Rough 3/30/2022 Approved AMY COLIN
Rough-Elec/Plmb/HVAC 3/30/2022 Approved AMY COLIN
Verify Sprinkler Sign Off 3/30/2022 Not Ready for Inspection AMY COLIN
BUILDING-Rough-Frame 4/12/2022 Conditional Approval AMY COLIN
Green Building Rough 4/12/2022 Not Ready for Inspection AMY COLIN
Verify Sprinkler Sign Off 4/12/2022 Conditional Approval AMY COLIN
Interior/Exterior Lathing 5/9/2022 Not Ready for Inspection AMY COLIN
Green Building Rough 5/16/2022 Approved AMY COLIN
Interior/Exterior Lathing 5/16/2022 Partial Approval AMY COLIN
Insulation 5/24/2022 Approved AMY COLIN
Drywall Nailing 6/7/2022 Approved AMY COLIN
Shower Pan 6/7/2022 Approved AMY COLIN
Interior/Exterior Lathing 6/13/2022 Approved AMY COLIN
Gas Test 11/9/2022 Approved AMY COLIN
Gas Test 11/14/2022 Approved AMY COLIN
Underground Mechanical 8/17/2023 Approved AMY COLIN
ELECTRICAL-Final 12/13/2023 Corrections Issued AMY COLIN
Service/Power Release 2/13/2024 Not Ready for Inspection LILIANA PORTILLO
BUILDING-Rough-Frame 4/16/2024 Approved LILIANA PORTILLO
ELECTRICAL-Final 4/16/2024 Corrections Issued LILIANA PORTILLO
Final 4/16/2024 Corrections Issued LILIANA PORTILLO
Green Building Final 4/16/2024 Approved LILIANA PORTILLO
HVAC-Final 4/16/2024 Corrections Issued LILIANA PORTILLO
MERV13>=Final 4/16/2024 Approved LILIANA PORTILLO
PLUMBING-Final 4/16/2024 Corrections Issued LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 4/16/2024 SGSOV Approved LILIANA PORTILLO
Service/Power Release 4/16/2024 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 4/16/2024 Approved LILIANA PORTILLO
Verify Sprinkler Sign Off 4/16/2024 Approved LILIANA PORTILLO
ELECTRICAL-Final 4/25/2024 Approved LILIANA PORTILLO
Final 4/25/2024 Not Ready for Inspection LILIANA PORTILLO
HVAC-Final 4/25/2024 Approved LILIANA PORTILLO
PLUMBING-Final 4/25/2024 Approved LILIANA PORTILLO
Service/Power Release 4/25/2024 Not Ready for Inspection LILIANA PORTILLO
Final 5/15/2024 OK to Issue CofO LILIANA PORTILLO
Service/Power Release 5/15/2024 Approved LILIANA PORTILLO