238 E AVENUE 38 90031
Certificate Information: 238 E AVENUE 38 90031
- Application / Permit
- 17010-20000-04437
- Plan Check / Job No.
- B17VN17293
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 40' x 20' 2-STORY SINGLE FAMILY DWELLING WITH ATT GAR; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 3/8/2021
- Issuing Office
- Current Status
- CofO Issued on 5/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/9/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 11/16/2017 | SELLA BENYAMIN |
| Corrections Issued | 11/22/2017 | SELLA BENYAMIN |
| Quality Review Completed | 11/22/2017 | GUANG MIN TUNG |
| Building Plans Picked Up | 11/28/2017 | APPLICANT |
| Green Plans Picked Up | 11/28/2017 | APPLICANT |
| Plan Check Approved | 9/6/2018 | SELLA BENYAMIN |
| Issued | 3/8/2021 | APPLICANT |
| CofO in Progress | 5/16/2024 | LILIANA PORTILLO |
| CofO in Progress | 5/20/2024 | LILIANA PORTILLO |
| CofO in Progress | 5/21/2024 | CHARLES BOGHOSKHAN |
| CofO Issued | 5/22/2024 | DEROLD HAUFF |
| Permit Finaled | 5/22/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/13/2018 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 3/13/2018 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 3/13/2018 | OSCAR SALGADO JR |
| Permit | Cleared | 3/13/2018 | LEE GUILBEAUX |
| Sewer availability | Cleared | 3/13/2018 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 3/13/2018 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 5/24/2018 | SAM NAVID |
| Roof/Waste drainage to street | Cleared | 6/6/2018 | KAREN LE |
| Green Code | Cleared | 6/15/2018 | SELLA BENYAMIN |
| HPOZ | Cleared | 9/10/2018 | KATIE DEBIASE |
| Miscellaneous | Cleared | 9/10/2018 | KATIE DEBIASE |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/25/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Pre-Inspection | 3/25/2021 | Partial Inspection | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 4/7/2021 | Partial Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 4/19/2021 | Corrections Issued | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 4/22/2021 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 4/22/2021 | Partial Approval | OSVALDO PARAMO |
| PLUMBING-Rough | 4/28/2021 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 5/11/2021 | Partial Approval | COREY HUPP |
| Footing/Foundation/Slab | 6/11/2021 | Approved | COREY HUPP |
| BUILDING-Rough-Frame | 6/24/2021 | Partial Approval | COREY HUPP |
| BUILDING-Rough-Frame | 7/30/2021 | Not Ready for Inspection | COREY HUPP |
| Wood Frame | 8/3/2021 | Partial Approval | COREY HUPP |
| Gas Test | 9/22/2021 | Partial Approval | COREY HUPP |
| Underground Mechanical | 9/22/2021 | Partial Inspection | COREY HUPP |
| Gas Test | 11/24/2021 | Partial Approval | CRAIG DAVIS |
| PLUMBING-Rough | 11/24/2021 | Corrections Issued | CRAIG DAVIS |
| HVAC-Rough | 2/4/2022 | Partial Approval | COREY HUPP |
| HVAC-Rough | 2/24/2022 | Corrections Issued | OSVALDO PARAMO |
| PLUMBING-Rough | 2/24/2022 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2022 | Not Ready for Inspection | COREY HUPP |
| PLUMBING-Rough | 3/4/2022 | Approved | COREY HUPP |
| ELECTRICAL-Rough | 3/11/2022 | Approved | OSVALDO PARAMO |
| HVAC-Rough | 3/11/2022 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 3/30/2022 | Corrections Issued | AMY COLIN |
| Green Building Rough | 3/30/2022 | Not Ready for Inspection | AMY COLIN |
| MERV13>=Rough | 3/30/2022 | Approved | AMY COLIN |
| Rough-Elec/Plmb/HVAC | 3/30/2022 | Approved | AMY COLIN |
| Verify Sprinkler Sign Off | 3/30/2022 | Not Ready for Inspection | AMY COLIN |
| BUILDING-Rough-Frame | 4/12/2022 | Conditional Approval | AMY COLIN |
| Green Building Rough | 4/12/2022 | Not Ready for Inspection | AMY COLIN |
| Verify Sprinkler Sign Off | 4/12/2022 | Conditional Approval | AMY COLIN |
| Interior/Exterior Lathing | 5/9/2022 | Not Ready for Inspection | AMY COLIN |
| Green Building Rough | 5/16/2022 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 5/16/2022 | Partial Approval | AMY COLIN |
| Insulation | 5/24/2022 | Approved | AMY COLIN |
| Drywall Nailing | 6/7/2022 | Approved | AMY COLIN |
| Shower Pan | 6/7/2022 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 6/13/2022 | Approved | AMY COLIN |
| Gas Test | 11/9/2022 | Approved | AMY COLIN |
| Gas Test | 11/14/2022 | Approved | AMY COLIN |
| Underground Mechanical | 8/17/2023 | Approved | AMY COLIN |
| ELECTRICAL-Final | 12/13/2023 | Corrections Issued | AMY COLIN |
| Service/Power Release | 2/13/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 4/16/2024 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 4/16/2024 | Corrections Issued | LILIANA PORTILLO |
| Final | 4/16/2024 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 4/16/2024 | Approved | LILIANA PORTILLO |
| HVAC-Final | 4/16/2024 | Corrections Issued | LILIANA PORTILLO |
| MERV13>=Final | 4/16/2024 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 4/16/2024 | Corrections Issued | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 4/16/2024 | SGSOV Approved | LILIANA PORTILLO |
| Service/Power Release | 4/16/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Smoke Detectors | 4/16/2024 | Approved | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 4/16/2024 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 4/25/2024 | Approved | LILIANA PORTILLO |
| Final | 4/25/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| HVAC-Final | 4/25/2024 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 4/25/2024 | Approved | LILIANA PORTILLO |
| Service/Power Release | 4/25/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 5/15/2024 | OK to Issue CofO | LILIANA PORTILLO |
| Service/Power Release | 5/15/2024 | Approved | LILIANA PORTILLO |